John B. Pike & Son, Inc. v. StateJohn B. Pike & Son, Inc. v. State
OPINION OF THE COURT
This mаtter was remitted to the Court of Claims for determination of damages on two causes of action (Pike & Son v State of New York,
Prior to analyzing the damages in the first cause of action, this court notes its perception of what constitutеs that part of the record limiting or setting the parameters for such analysis.
The lower court dismissed claimant’s first cause of action based on claimant’s failure of proof that the extra work was done under Stаte directive. "In the present case, while the State did order extra work (meaning the direction that the claimant complete by whatever means necessary holes abutting obstructed holes) what the contrаctor and its subcontractor did here was not that extra work. Rather, they unilaterally adopted a different methodology to install the drains by preaugering all holes. While this method resulted in some still obstructed drains as well аs completed drains, it did not change in any way the basis of payment under which the State contracted. That was a per-linear-foot basis. While we have no doubt that this preaugering method was more expensive for the contractor and the subcontractor, the State was not obligated to pay those costs under those circumstances established at bar” (Ct Cl, Nov. 18, 1993, Margolis, J., claim No. 70979, slip opn, at 10-11).
After dismissing the claimant’s first сause of action on the above-stated basis, Judge Margolis stated in dicta: "In sum, the settlement agreement between claimant and its subcontractor does not provide a separate defense to the defendant for claimant’s first and second causes of action. Nevertheless, defendant is entitled to a judgment dismissing those causes of action” (supra, at 19).
Absent any other theory of recovery reсognized in law, claimant, in its action against defendant for losses sustained by Vibroflotation, is limited, upon proof at trial, to its out-of-pocket costs as established by the settlement agreement entered into evidеnce by claimant as exhibit 66 (First Natl. Bank v Fourth Natl. Bank,
The record clearly establishes that claimant is not suing defendant on behalf of Vibroflotation. Any recovery here benefits claimant and does not flow through it to the benefit of Vibroflotation. In this respect, the present case differs from the usual procedure adopted by principal contractors in obtaining damages for subcontractors resulting from extra work orders by owners (see, Ardsley Constr. Co. v Port of N. Y. Auth.,
If claimant contends that this agreement somehow increases its damages beyond the $75,000 paid to Vibroflotation, that contention must fail as Vibroflotation, lacking privity, had no rights against defendant which it could assign to claimant (see, Fehlhaber Corp. & Horn Constr. Co. v State of New York, supra; Dunn v Uvalde Asphalt Paving Co.,
Claimant contends that its damages for the costs incurred as a result of its pre-drilling procedure not only include the cost of the pre-drilling but also the cost of the downtime of its machine, which placed the wick drains in the pre-drilled holes (labeled by claimant as loss of productivity). This downtime was caused by underground obstructions falling into the predrilled holes, clogging or damaging Vibroflоtation’s equipment. The Appellate Division’s decision on this issue stated that "[b]y his 'written change order’, the State engineer directed claimant to complete, by whatever means necessary, its attempts to instаll drains next to obstructed holes. Because experience had demonstrated the futility of not pre-drilling the holes, the subcontractor acted reasonably in determining to pre-drill the holes on the first attempt. We conclude that the subcontractor’s resort to the necessary and feasible method, sooner rather than later, was expressly or impliedly authorized by the State and thus constituted compensable extrа work under the contract” (Pike & Son v State of New York,
The extra work required as a result of the change order was found by the Appellate Division to have been incurred through the contractor’s compliance with the State’s engineеr’s directive to complete by whatever means necessary drains next to obstructed holes. In compliance with this directive, the claimant undertook to pre-drill all holes before attempting to plaсe the wick drains. Additional costs were incurred because of the problems encountered in the actual placement of the
Although the damage schedule summary of exhibit 147 shows an application of 20% as profit and overheаd and labor, the actual arithmetic establishes that the computation for these costs was actually 25%, in compliance with the contract. For the first cause of action, the court finds damages in the amount of $78,087.76. As the court has found that the maximum amount of damages to which claimant is entitled on behalf of losses sustained by Vibroflotation is $75,000, that amount is reduced to $68,061.87 ($75,000 —$6,938.13 awarded claimant in the third cause of action).
Notes
The damage schedule stated in exhibit 45 is based primarily on estimated costs calculated by Vibroflotation in preparing its bid. This methodology for calculating excess costs has previously been rejected by the courts of this State as being unreliable (Novak & Co. v Facilities Dev. Corp.,