88 Neb. 469 | Neb. | 1911
Upon a former appeal this case was remanded to the district court with directions to ascertain how much of the plaintiff’s delay in completing the building was caused by the owner’s failure to have the site in proper condition and how much was owing to other causes for which the owner was not repsonsible, and to allow the defendant the stipulated damage of $25 a day for every day’s delay for which the plaintiff and not the defendant was responsible. 84 Neb. 735. The parties were given the right to introduce more testimony upon the issues. Upon the second hearing considerable additional testimony was taken, and upon a consideration of all the evidence the court found that the defendant should be allowed damages for 71 days, and modified the judgment first rendered. The defendant appeals.
The defendant’s first contention, that it should have been allowed $11,588.77 damages for six months’ delay in delivering possession of the basement and subbasement, must be resolved against it. It is true that although the
The former opinion of this court (84 Neb. 735), written by Mr. Commissioner Calkins, will not bear the construction contended for by the defendant. Judge Calkins reasoned that, although the defendant’s promise to waive the time clause was made, it was not sustained by a consideration, and should not be enforced as a contract, but that, if the plaintiff relied thereon, the defendant would be estopped from insisting upon the provision in the contract that no allowance shall be made for delays unless within 24 hours after cause therefor arose the contractor shall have delivered to the architect a written claim for an extension of time because of such delay. The defendant now contends that whether or not the plaintiff did rely upon that promise is a question of fact and should have been determined by the court upon the second appeal; that no such finding was made, and that there is no evidence to sustain a finding of that character, and for that reason it should recover damages at $25 a day from September 1, 1905, to July 25, 1906.
The finding that the defendant should recover for but 71 days’ delay is vigorously criticised by the defendant and as earnestly commended by the plaintiff. The evidence upon this issue is in hopeless conflict. Some of the witnesses by their testimony evince considerable feeling, and while all of them are apparently intelligent men, the weight to be given their testimony depends to a considerable extent upon their credibility, a factor the trial court could determine much better than we can.
The building as originally designed was to cost but $52,963, but alterations and extras increased its cost to $66,124. Many of these departures from the original plan compelled the plaintiff to order new and different structural steel, and these altered beams could only be procured in Pennsylvania upon special orders which were not always promptly filled. In but one particular are we inclined to disturb the findings of the district court. The court found that possession of the building was delivered to the defendant July 1, 1906. Mr. Joseph Hayden, president of the defendant, testified that they were not given that possession until July 25 or July 27. Counsel for
The defendant complains because the court permitted the plaintiff to file an amendment to his petition wherein the delay occasioned by the alterations is specifically pleaded. Our former opinion and mandate justifies this ruling. It is not just that the plaintiff should pay $25 a day to the defendant for delays caused by acceding to its demands. Carter v. Root, 84 Neb. 723.
The judgment of the district court, therefore, is modified by increasing the allowance of damages in favor of the defendant to $2,025, and, as modified, the judgment is affirmed; the defendant to recover the costs of this appeal.
Affirmed as modified.