| Mo. Ct. App. | Nov 4, 1913

REYNOLDS, P. J.

Plaintiff, tenant for life of certain premises in the city of St. Louis, commenced Ms action on the 15th of September, 1910, in the circuit court of the city of St. Louis, for damages alleged to *712have been sustained by reason of defendant piling lumber in his lumber yard so negligently and carelessly as to cause the rain and melting snow to be discharged upon and against the north walls of the premises of plaintiff, flooding and submerging his back yard and the first floor of his two-story brick building as well as the basement and floors of a one-story brick building on the same lot, and permanently injuring the north walls of the building. It is charged that erecting these piles on the 9th of February, 19091, defendant had maintained them down to the time of the institution of the suit, that is the 15th of September, 1910, in such shape as to cause the rain and snow to drop down and flow from them to the damage of the premises of plaintiff as above, the damages being laid at $5000'.

Defendant answered by general denial. At a trial before the court and a jury, a verdict was rendered in favor of plaintiff in the sum of $400'. Judgment followed from which defendant, filing a motion for new trial as well as one in arrest and excepting to the action of the court in overruling these motions, duly perfected his appeal to this court.

Learned counsel for appellant make eight assignments of error.

The first assignment is to the admission in evidence, over the objection and exception of appellant, of the testimony of a witness as to what would be the cost of building a new wall on the north of respondent’s buildings, the wall to he rebuilt thirteen inches thick and of new pressed brick, whereas the old wall was only nine inches thick and of handmade brick. It is true that that witness testified that to rebuild the wall, he would use new brick, arid that the wall he was figuring on was a thirteen-inch wall. His attention being called to the fact that the old wall was a nine-inch wall of handmade brick, he stated that the city ordinances do not allow the construction of a brick building of the height of the one in controversy with a wall of less than *713thirteen inches in thickness. He further testified that it would cost as much to replace it with old brick as with new brick, provided you could get old brick, which was not always the case. We see no error in the admission of this testimony to the prejudice of appellant. Necessarily the wall, if rebuilt,'would have to be in conformity with the requirements of the city ordinances and we know of no rule of law that would require plaintiff to replace old brick with old brick, assuming that they could be had. This is especially so when, according to this witness’s testimony, one. could not always obtain old brick, and if they did manage to secure them, they would cost as much as new brick, he testifying that it did not cost any more for the thirteen-inch than the nine-inch brick because to lay the nine-inch would cost more than for laying the thirteen-inch brick.-

. The second and third assignments are to the alleged error of the court in giving two instructions which the court did of its own motion, and the fourth, fifth, sixth, seventh and eighth are to the alleged error of the court in refusing to give instructions Nos. 2, 4, 7, 9 and 10, asked by appellant. It appears from an examination of the record that the court took the instructions asked by the parties and gave instructions he had himself prepared. We have no means of determining with any accuracy as to whose instructions the court used, whether those of appellant or those of respondent, in framing the instructions he gave. Counsel for appellant complain that the court changed the instructions they asked and substituted others for them, but they have not preserved this point by proper exception and accurately, contenting themselves with ■bringing up the instructions as given by the court of its own motion, of which there are twelve, and bringing up eleven instructions which are designated as the “defendant’s refused instructions.” It is true that we might set these side by side with those given by the *714court of its own motion and pick out the changes in verbiage between them, but that is not a labor that should be imposed upon us. If counsel desired to have this court pass upon the instructions as asked and modifications made in them by the court, they should have distinctly pointed out the modifications and not have thrown the labor upon the appellate court of endeavoring to determine the variance between them, if any.

We have, however, read the instructions given by the court of its own motion, in connection with the refused instructions asked by the court and can say, generally, of them, that we find no error in the action of the court either in the giving of the instructions which it did of its own motion or in the refusal of those asked by appellant. As to those given, it has been noted that error is assigned on only two of those so given. We find them correct as to the propositions covered by them, one covering plaintiff’s case as pleaded and proved, the other as to the measure of damages.

The instructions asked by defendant and refused were either covered, in a more correct form, by the instructions given by the court of its own motion, or were not correct propositions of the law as applied to the facts in evidence. As an instance of the latter, appellant asked an instruction to the effect that if they found for plaintiff, the jury would allow him such damages as under the instructions given they believed and found from the evidence were caused by the piles of lumber which plaintiff erected and constructed on or about the 9th day of February, 1909, if the jury believed and found from the evidence that plaintiff so' constructed piles of lumber on that date, and “you are further instructed that the plaintiff is not entitled to-recover any damages that may have been caused, by piles of lumber other than those constructed on or about the 9th day of February, 19091, and is not entitled to recover any damages which may have occurred previous to May 29,1909'. ’ ’ The point sought to be cov*715ered by this instruction is, that in tbe petition in tbe case, plaintiff laid tbe date of tbe erection of tbe piles as of the 9th of February, 1909', whereas it appeared by tbe testimony in tbe case that plaintiff’s interest in tbe premises only fell in on tbe 29th of May, 1909, when on tbe death of bis wife be became a tenant for life of tbe premises in controversy. We see no error in tbe action of tbe court in refusing this instruction in this form. It appears on an examination of tbe testimony as set out in tbe record that when this point was made, that is that be was confined to piles of lumber erected on tbe 9th of February, 1909, tbe court announced in passing on tbe objection made, that, as he understood tbe petition, plaintiff bad alleged that in tbe early part of 1909, that is, in February,"defendant erected certain piles of lumber on this lot adjoining this property; that be maintained those same piles for some time after that; that tbe water ran from those piles onto tbe premises of plaintiff. “Of course,” said tbe court, “be will be restricted to what be alleges, but you do not contend that if be took one or more pieces of lumber off of a pile and put on two or three pieces that that will be a different pile ? . . . Tbe point is they were maintained during bis tenancy.” In effect, tbe court ruled that it was not incumbent upon plaintiff to show that defendant bad maintained tbe identical piles of lumber which be bad put up on tbe day named; that tbe allegation is to be construed as an averment that in February, 1909, defendant erected certain piles of lumber and that be continued those up to September 16th, 1910 and that they caused tbe damage. “You will be restricted to those piles,” said the court. Under this ruling, which we consider absolutely right, tbe court correctly refused this instruction, the ninth one asked by defendant.

That tbe court carefully and strictly held plaintiff down to a definite period is clear. Thus, although plaintiff filed an amended petition sometime after tbe *716institution of the action, the court confined the period to which he was entitled to recover damages to between the date upon which the life estate of plaintiff accrued and the date of the filing of the original petition in the case, refusing to extend it down to the time of the filing of the third amended petition or to the time of the trial. Whether that action of the court was right or wrong, most certainly defendant has no cause to complain of it.

Looking at the instructions given and those refused, it is clear that the case was tried in exact accordance with the law as announced by this court in Thoele v. Marvin Planing Mill Co., 165 Mo. App. 707, 148 S. W. 413. That case has very many features in common with the case at bar. We have there considered the law applicable to cases of this character so fully that we do not consider it necessary to go into it any further and content ourselves by reference to that decision. We hold that this case at bar was tried upon the law as there announced and find no error in the action of the trial court in the premises.

Defendant challenges the whole of the testimony, as well as the amended petition. The testimony was ample to sustain the verdict and the petition does state a cause of action with sufficient accuracy to sustain the judgment. On the testimony in the case as to 'the extent of damage suffered by plaintiff, the verdict is entirely within that testimony, some of the witnesses placing the damage at over $1000'. We find no reason to disturb the verdict. The judgment of the circuit court is affirmed.

Nortoni and Allen, JJ., concur.
© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.