112 Mich. 57 | Mich. | 1897
The plaintiff commenced the present suit in the circuit court for the county of Bay, filing a declaration therein upon all the common counts in assumpsit, with the following bill of particulars annexed:
Bay City, Mich., Oct. 35, 1895.
The Jennison Hardware Co.
Sold to John Godkin.
1895.
June 37. 6 No. 5 dies for park swage, 75------------ $4 50
July 19. 3 53 ft. x 10 x Ga. 14 band saws, $183...$864
Less 50-10 per cent____________ —........ 168 80
Boxing saws------------------------------ 1 35
Prepaid express ........................ 11 45
$181 00
“Before the filing of the declaration in this suit, to wit, on the 10th day of October in the year 1895, this defendant commenced a suit against the above-named plaintiff, in justice’s court, before Alfred M. King, a justice of the peace in and for Bay City, in the county of Bay and State of Michigan, and this defendant, in that suit, which is an action in assumpsit, has declared against the defendant therein, being the plaintiff in this suit, in a cause of action the determination of which involves, and which suit will adjudicate, the cause of action as is set forth in the plaintiff’s declaration in this suit, by means of which there is in said justice’s court an action of assumpsit pending, in which and whereby the same cause of action will be litigated and adjudicated as in this suit; and this defendant further says that the parties in this and the said former suit are the same, and not other or different parties, and that said former suit, so brought and prosecuted, is still pending in the said court; and this the said defendant is ready to verify. Wherefore he prays judgment,” etc.
The plaintiff in this suit joined issue upon said plea by filing a replication thereto. The issue thus framed on the plea in abatement came on to be heard before the court without a jury, and, after hearing the evidence therein, the court found the said plea to be true, and that a determination of said suit involved and would adjudicate the cause of action set forth in the plaintiff’s declaration in this suit, except the claim of plaintiff in this suit on account of the item of goods sold at $4.50. The court further found that the action in justice’s court had been determined in favor of the plaintiff in that suit, and had been appealed by the defendant in that suit to the circuit court, wherein and whereby the same cause of action would be litigated in that suit as would be litigated
The errors assigned, upon which the defendant' in the present suit relies, are:
1. That the court erred in finding and determining, as matter of law, that the pendency of the former suit referred to in the findings of fact and law was not a bar to the further progress of this suit, and did not abate said cause in the court below.
2. That the court erred in entering an order or judgment overruling the defendant’s plea in abatement.
3. That the court erred in entering final judgment in favor of the plaintiff.
The plaintiff’s contention is:
1. That the court below entered no final judgment upon the plea in abatement; that the order made did not finally
2. That no exceptions were taken to the findings of the court, either upon the facts or law, by the defendant, and that, therefore, the finding of law is not reviewable in this court.
3: That the findings of fact show that the matters involved in this and in the former suit were not the same; that the pleadings in the former suit are set out in the findings; that the first count is based upon the purchase by Godkin of a band saw in 1894, and that under that count, as amended, Godkin claimed as follows: Expense in taking the saw to the mill, $7.55; expense in taking it from the mill to Bay City, $12; repairing saw, $15; loss of sawing 420,000 feet of lumber (amount not stated); that the second count is based upon a breach of warranty with respect to two saws purchased by Godkin in July, 1895, and under this count his claim is: Freight and teaming on saws to mill, $10; putting them up and attempting to work them, $10; loss of time of mill, $50; lost time of men employed in mill, $50; expense of returning saws to Bay City, $12; loss and damages in attempting to operate saws (amount not stated); that, in the ad damnum clause in the declaration, damages in the sum of $290 were claimed. It is further insisted that it was not possible, under the pleadings in the former suit, for the Jennison Hardware Company, the defendant therein, to have recovered judgment for its claim as set forth in the declaration and copy of account in this case; that even if the claim might have been interposed as a defense to the former suit, by way of set-off, if due notice of set-off had been given under the plea of the general issue, it is certain that, under the plea of the general issue alone, the right of the Jennison Hardware Company to recover judgment upon its claim was not involved, and judgment in that case would not determine the right of the Jennison Hardware Company to recover the amount of its claim, and therefore would not be a bar to this suit.
4. That the Jennison Hardware Company was not bound to offset its claim against that made by Godkin in the first case.
We may pass the first, second, and third points made by counsel for the plaintiff, as we are satisfied that his fourth point is well taken. The Jennison Hardware
“No set-off was pleaded in that case [referring to another suit which had been litigated between the same parties], but the association denied any liability, and rested upon that defense. In the present case the circuit judge finds as follows: ‘ None of the items involved in this claim were before the court by evidence; nor were the same, or either of them, considered, allowed, applied, or adjudicated on said trial.’ It is distinctly returned that the present bill of exceptions does not contain all the evidence, and also that there was evidence showing that none of the items claimed for in this action were included in the former case referred to. This finding is therefore conclusive, unless it be held, as a matter of law, that, through its failure to plead set-off, the plaintiff is concluded from afterwards bringing suit upon its counterclaim. Such is not the law,”—citing Huntoon v. Russell, supra, and other cases.
It was further said:
“The authorities cited by defendant’s counsel are cases in which the counterclaim was set up by the defendant, and was within the issue tried.”
We are therefore satisfied that the court below was not in error in holding, as matter of law, that the commence
The judgment, therefore, will be affirmed.