50 Ind. 339 | Ind. | 1875
Action by the appellee against the railroad company. The complaint alleges a special contract, by which the railroad company agreed with the plaintiff’s testator to transport sixteen car loads-of hogs from Shelby ville to Jeffersonville, at the price of twenty-five dollars per car; that the decedent shipped in the sixteen cars eight hundred and forty hogs, on the evening of February 3d, 1872, which the defendant agreed to deliver in Jeffersonville on the following day, at nine o’clock A. m. ; that the train on which the hogs were shipped, by running as specified in the time-card, would have arrived in said city of Jeffersonville at that hour, but, by the negligence of the defendant, the cars were detained upon a side-track for thirty-six hours longer than they should have been, and the hogs were not delivered until five o’clock of February 5th, 1872; that, owing to the cold and inclement weather, sixteen of the hogs died, and the others lost flesh from being deprived of food and water; the value of the hogs which died and the damage to the others are alleged.
An answer, consisting of the general denial and three special paragraphs, was filed, to the special paragraphs of which there was a reply in denial.
A trial by jury was had, and there was a general verdict for
“ 1. State if there was any special contract between the plaintiff and the defendant for the carrying of the hogs.
“Ans. None.
“ 3. Did the defendant agree to deliver the hogs at Jeffersonville at any certain time?
“Ans. No certain time.
“4. If there were any delays in the transportation of the hogs, from what reason did such delay occur ?
“Ans. From not furnishing cars on time.
“ 5. If the jury find any negligence on the part of the defendant, state in what said negligence consisted.
“Ans. By not furnishing power to move it.”
There was no answer to the second interrogatory, and hence we do not set out that interrogatory.
The defendant moved the court for judgment on the special findings, on the ground that they were inconsistent with and contradicted the general verdict, and because the jury had found that there was no special contract proved between the parties, and that the delay in the transportation of the hogs was occasioned by not furnishing cars on time. This motion was overruled, and the defendant moved for a new trial, which was also overruled, and there was final judgment for the plaintiff.
The errors assigned are:
1. Overruling the defendant’s motion for judgment on the special findings; and,
2. Overruling his motion for a new trial.
It seems to have been held by the court, in overruling the motion for judgment on the special findings and instructions given to the jury, that the plaintiff could recover, although he failed to prove the special contract alleged in the complaint.
This presents the question, whether the plaintiff, in such a case, can count upon a special contract and recover upon an implied contract to carry in a reasonable time, or for a breach ^f the legal duty of the corporation as a common carrier. In
The judgment is reversed, with costs, and the cause remanded, with instructions to sustain the motion of the defendant for judgment on the special findings.