OPINION
On аppeal in this public-contract dispute, appellant Allen Javinsky argues that (1) the district court improperly denied appellant’s request for mandamus and declaratory relief, and (2) summary judgment was improper on appellant’s promissory-estoppel claim. Because appellant failed to timely appeal the district court’s denial of his mandamus and declaratory relief claims and because he has not provided evidence of reasonable, detrimental reliance in his promissory-estoppel claim, we affirm.
In 1999, respondent Commissioner, Minnesota Department of Administration (DOA) began a multi-stage sewer-system replacement project at the Minnesota Correctional Facility-Faribault. At issue here is a contraсt for project 04-01 to reshape and grout the deep tunnel at the correctional facility. Generally, the DOA is responsible for administering construction projects under Minn. Stat §§ 16B.001-16B.282 (2004) and awards state contracts based on a selection process it coordinates. For certain projects, however, the selection of contractors is made by the State Design Selection Board (SDSB), an independent agency whose authority is defined by Minn.Stat. § 16B.33. Agencies must use the SDSB to select the primary designer on building construction or remodeling projects when estimated costs exceed a certain amount. The SDSB had previously selected the primary designer to perform the sewer-system-replacement project.
In 2003, the DOA decided to have the Statе Architect’s Office (SAO) rather than the SDSB select an alternate project designer for the final phase of the project. The SAO requested proposals from four design engineers, including appellant, a subcontractor who had worked on the original project. In February 2004, after learning that he had not been chosen as the designer for the project, appellant objected to the selection process and contended that the SDSB, not the SAO, should have made the designer determination, as it had for earlier phases of the sewer-system-replacement project. The SAO reconsidered its decision and agreed, in a letter to the SDSB, that “the authority for selecting an alternative design firm remains with the [SDSB], not the [SAO] ” and stated “[w]e reviewed the statute and agree that, technically, we did not have the authority to solicit proposals and make an alternate selection.” The SDSB then requested proposals for the project and received submissions from appellant and a competitor. In April 2004, the SDSB notified appellant that he had been selected as the designer for the project. After the competitor challenged the SDSB’s selection of appellant, respondent placed the contract process for the project on hold and requested information from the SDSB about its selection criteria and evaluation process.
In September 2004, respondent withdrew the responsibility for selecting a designer for the project from the SDSB because it had not provided the information respondent requested. Respondent ordered the SAO to issue a new request for proposals without further involvement from the SDSB. Respondent stated that “use of the [SDSB] is not statutorily mandated for infrastructure work (see definition of project in [Minn.Stat. § 16B.33, subd. 1(h)]).” Appellant objected to respondent’s decision to reject him as the designer for the project аnd to withdraw authority from the SDSB.
In October 2004, the SAO issued a request for proposals for the project. In November 2004, appellant sued respondent, seeking a writ of mandamus, declaratory judgment, promissory estoppel, and other relief. Following submissions of proposals in response to the SAO’s request for proposals for the project, the competitor was selectеd as the designer. Appellant moved for injunctive relief, and the district court conducted a hearing on November 30, 2004.
Because legislative authority for the project was set to expire by December 31, 2004, if there was no contract, the parties agreed to treat the district court’s decision on appellant’s motion for injunctive relief as a summary judgment on his mandamus
ISSUES
I. Is appellant’s appeal of the December 2004 judgment timely?
II. Did the district court err in granting summary judgment in favor of respondent on the promissory-es-toppel claim?
ANALYSIS
I.
Appellant argues that he was not required to appeal the December 2004 judgment because it was an interlocutory judgment that did not resolve all of his claims. His notice of appeal only refers to the district court’s judgment entered in November 2005. The district court “may direct the entry of a final judgment as to one or more but fewer than all of the claims of parties only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment.” Minn. R. Civ. P. 54.02. It can be inferred from Minn. R. Civ.App. P. 104.01, subd. 1, that timely appeal of a judgment containing rule 54.02 certification is mandatory because rule 104.01 states “the time to appeal from any other judgment entered pursuant to [r]ule 54.02 shall not begin to run until the entry of a judgment which adjudicates all the claims and rights and liabilities of the remaining parties.”
Minn. R. Civ. P. 54.02 is substantively identical to Fed.R.Civ.P. 54(b). The United States Supreme Court explained that federal rule 54(b) was promulgated to prоvide clarity to the parties when some but not all of the claims at issue have been decided, stating that “[a] party adversely affected by a final decision thus knows that his time for appeal will not run against him until this certification has been made,” i.e., until the district court makes an express determination that there is no just reason for delay and expressly directs entry of judgment.
Sears, Roebuck & Co. v. Mackey,
In
Semiconductor Automation, Inc. v. Lloyds of London,
this court dismissed an appeal taken from a final judgment, holding that (1) an interlocutory order and judgment dismissing one defendant for lack of jurisdiction was immediately ap-pealable, (2) “the inclusion of rule 54.02
This view is consistent with an earlier decision of the Minnesota Supreme Court in which it considered whether a judgment, certified under rule 54.02, determining liability but not damages, “is a final judgment from which an appeal must be taken[.]”
See In re Commodore Hotel Fire & Explosion Case,
Here, the district court, in accordance with rule 54.02, expressly determined that “there is no just reason for delаy,” and directed entry of judgment. The district court apparently made the rule 54.02 certification without being requested to do so by either party. The district court was operating under the parties’ agreement to expedite the proceeding by treating it as one for summary judgment on appellant’s mandamus and declaratory relief claims because legislative funding for the project would expire on December 31, 2004, if a contract had not yet been finalized.
Appellant argues that because the district court’s language made no reference to rule 54.02 he had no notice that this was a rule 54.02 order, and he would have no reason to believe that the 60-day appeal period had commenced. Appellant does not dispute that the distriсt court entered judgment on part of his claims pursuant to rule 54.02 when it stated “There is no just reason for delay” and “Let judgment be entered accordingly.” Appellant cites no authority for his proposition that the district court’s order must explicitly state that it is being issued pursuant to rule 54.02.
Because the time to appeal from the district court’s judgment expired on February 27, 2005, we may not consider appellant’s appeal of the district court’s decision or its inherent issues. Minn. R. CivApp. P 104.01, subd. 1. Therefore, we must accept the district court’s decision that respondent acted reasonably and within his authority to withdraw authority from the SDSB to select the designer for the pro
II.
Appellant argues that the district court erred in granting summary judgment in favor of respondent on the promissory-estoppel claim. On appeal from summary judgment, we examine the record in the light most favorable to the party against whom summary judgment was granted to determine whether there are any genuine issues of material fact and whether the district court erred in applying the law.
Lubbers v. Anderson,
The record does not contain evidence of a clear and definite promise. In April 2004, the SDSB sent a letter to appellant confirming his selection as the primary designer for the project. But selection by the SDSB does not constitute a “clear and definite” promise that appellant will be given a contract nor does it automatically lead to the development of a contract. If a contractor’s selection led to a clear and definite contract formation, then there would be no opportunity for a disappointed bidder to initiate a successful objection, as appellant had done after the first request for proposals, and as appellant’s competitor did after the SDSB selected appellant. Therefore, the first element of promissory estoрpel — a clear and definite promise — fails as a matter of law.
The second element of a promissory-estoppel claim is reliance. There is some evidence that the DOA intended for appellant to rely on being awarded the contract for the project. The request for proposals that appellant responded to required a statement from him of his commitment to be available to do the work promptly if he were selected. A DOA official also testified that a selected designer would be expected to be available to do the work. After his selection by the SDSB, appellant and the DOA entered into and completed contract negotiations in May 2004. Appellant also testified that while he did not turn down business, he did nоt pursue other opportunities because he was expected to be available to do the work for the project. If appellant had been made a clear-and-definite promise, the evidence would be sufficient to establish appellant’s reliance for the purpose of defeating summary judgment on the reliance element. However, because we have concluded that a clear and definite promise did not exist, appellant’s reliance was unreasonable.
The third element of promissory estoppel, that the promise must be enforced to prevent injustice, is a question of law.
Faimon v. Winona State Univ.,
The situation in this case is similar to one that this court faced in
Faimon,
where this court addressed the reasonableness of an instructor’s reliance on the university’s promise that her job would be available to her for an additional year.
Faimon,
Wе conclude that appellant’s promissory-estoppel claim fails not only for lack of a clear and definite promise upon which appellant could have reasonably relied, but also because there is no evidence that appellant relied on such a promise to his detriment. There is no evidence that appellant had turned down other jоbs or that appellant had other jobs available to him while he remained available to perform the project. Appellant’s lost-profits estimate is based solely on his assertion that he did not pursue other jobs while he waited for the project contract to materialize.
See
DECISION
Because the time to appeal the district court’s December 27, 2004 judgment expired, we may not consider appellant’s appeal of the district court’s decision or its inherent issues. Further, because there are no material facts to support appellant’s claim that a clear and definite promise to enter a contract for the project, or that he reasonably relied to his detriment on such a promise, the district court did not err by granting summary judgment to respondent on appellant’s promissory-estoppel claim.
Affirmed.
