526 F.2d 922 | 5th Cir. | 1976
Lead Opinion
The facts and issues in this litigation revolve around the construction of defendant Westvaco’s pulp plant at Wickliffe, Kentucky. In the spring of 1969, the plaintiff, Jamison Company, and the defendant entered into two contracts, each covering a different construction phase, under which Jamison agreed to supply and install piping at Westvaco’s new mill. The first contract, set to begin on May 1, 1969, required completion by December 1, 1969, while the second contract contemplated that work would commence on May 5, 1969 and be finished by March 3, 1970. Westvaco obligated itself to pay Jamison $667,000 for the first contract and $1,042,000 for the second — a total contract price of $1,709,-000. The parties’ agreement provided for the contingencies of “termination with cause” and of “termination without cause.”
I. THE SUFFICIENCY OF THE EVIDENCE
Initially, we examine defendant’s assertion that the evidence in support of plaintiff’s theories of liability — the termination without cause and the settlement counts — was insufficient to justify jury submission.
A. The “Termination Without Cause” Claim.
On September 9, 1969, defendant Westvaco terminated plaintiff Jamison, hiring another contractor to finish Jami-son’s work. The events occurring between May 1, 1969, and the termination date are much disputed and, not unexpectedly, provide the substance for Jami-son’s first contention — that the termination was without cause. Jamison asserts that it did not breach the contract, and that if it did breach the contract, the breach is excused because it resulted in all material respects from the hindrance and interference of defendant. Plaintiff draws our attention to evidence supporting its contentions that at the time of termination it was in substantial compliance with the contract; that it could have completed the piping job on time; and that any delays or difficulties ensued from Westvaco’s wrongful actions— specifically defendant’s failures 1) adequately to prepare the work site, 2) to deliver final drawings at the required times, and 3) to coordinate work among the various contractors. Westvaco denies these contentions, asserting instead that the overwhelming evidence supports its conclusion that plaintiff’s work did not constitute substantial compliance, and that Westvaco in no way prevented plaintiff from fulfilling its contractual obligations. Our review of the record convinces us that the facts and inferences do not so strongly favor Westvaco that a jury of reasonable persons could not return a verdict for the plaintiff.
B. The Settlement Claim.
Also, as noted, plaintiff argues that at the September 9, 1969, termination meeting the parties entered into a definite, certain and unambiguous settlement agreement under which Westvaco was to pay Jamison the amount of its costs incurred, and that later, Westvaco breached that agreement. Defendant counters that the evidence will not support a jury finding of a legally sufficient settlement contract. Examining the record, we encounter sharply conflicting and somewhat confused testimony with respect to the purported agreement. However, although apparently inconsistent at points, Mr. Jamison’s testimony with respect to a cost basis settlement, if believed by the jury, would justify a verdict under the settlement count.
II. THE EXCESSIVENESS OF THE VERDICT
Westvaco argues that the $607,000 jury award so far surpasses “the maximum recovery supported by the evidence and authorized by the Court’s instruction” that the district court’s refusal of a new trial amounted to an abuse of discretion. Specifically, defendant asserts that no legally viable calculations under either the “termination without cause” or the settlement claim can support the jury’s verdict.
In Glazer v. Glazer, 5 Cir. 1967, 374 F.2d 390, 413, Judge Wisdom set forth the legal test for evaluating a damages finding in cases such as this. He said:
Here . . . abuse of discretion is present in the court’s failure to grant the defendants’ motion for a new trial or for remittitur. The verdict was excessive as a matter of law in that it exceeds any rational appraisal or estimate of the damages that could be based upon the evidence before the jury.
See Natco Inc. v. Williams Brothers Engineering Co., 5 Cir. 1974, 489 F.2d 639, 641; Glazer v. Glazer, 278 F.Supp. 476, 481-82 (E.D.La.1968). Cf. United States v. Simmons, 5 Cir. 1965, 346 F.2d 213, 218.
The question for this Court is whether viewing the testimony and exhibits most favorably to the plaintiff, there is within the standard quoted above sufficient evidence as to damages to support a verdict of $607,000. The plaintiff, asserting in oral argument that “there are an infinite number of ways to arrive at the magic figure,” outlined three basic approaches.
A. Termination Without Cause 1. The Cost Approach.
According to plaintiff’s counsel, the “.most plausible way” that the jury might have reached its verdict begins with an evaluation of Jamison’s costs under the district court’s “termination without cause” instruction. That in
The measure of Jamison’s damages, if any, as a result of the termination of the contracts, should you find that such termination by Westvaco was unjustified, is the proportionate share of the contract price, based on work done, plus the reasonable expenses of the termination, without deduction for the cost of the completion of the work after termination. I further charge you that such damages would include the proportionate share of profits that would have been realized by Jamison if full performance had been permitted. However, in order to recover lost profits, Jamison has the burden of proving to you that it would have made a profit had it been allowed to complete the contract and how much that profit would have been. From that amount, should you determine that Jamison is entitled to recover, should be deducted any payments made by Westvaco to or for the benefit of Jamison.5
Jamison’s analysis begins with the nonprofit portion of the instruction. Equating the contractual term “the proportionate share of the contract price, based on work done” with those costs actually incurred,
$487.000 direct costs
43.000 allocated overhead
$530,000 sub-total
(225 000) prior payments to Jamison
$305,000 sub-total forward
Plaintiff rightfully increases this subtotal of $305,000 by $76,000 which represents the monies Westvaco admitted owing Jamison on an unrelated contract (Luke).
$305,000 subtotal
76,000 owed to Jamison (Luke)
$381,000 subtotal forward
If we accept arguendo $381,000 as the amount due under the first part of the “termination without cause” jury in
$607,000 verdict
(381,000) subtotal
$226,000 shortfall
Appellee Jamison attempts to make up this shortfall with additions for lost profits and a contingency fund. First, Jami-son contends that the evidence before the jury indicated a budgeted profit of 61/2% on the first contract and 7% on the second for a total of $116,000.
Assuming that Jamison offered proof sufficient to demonstrate that if it had been permitted to complete the contract, it would have made a profit and benefited from the contingency fund, we must determine the maximum portion of the $266,000 ($116,000 budgeted profit plus $150,000 contingency fund) which the jury could have added to the verdict. The judge’s instruction ordered inclusion of “the proportionate share of profits that would have been realized by Jami-son if full performance had been permitted.” Although the district court was woefully imprecise in its charge, the “termination without cause” clause, which the instruction must follow, dictates that Jamison receive only that percentage of its realizable profits (and contingency fund
While it is true, as plaintiff observes, that the jury members are arbiters of the percentage of “work done,” their decision cannot reach beyond the evidence introduced at trial. See Natco, Inc. v. Williams Engineering Co., 5 Cir. 1974, 489 F.2d 639, 641; Glazer v. Glazer, 5 Cir. 1967, 374 F.2d 390, 413. Here an 85% figure is the lowest number the jury could have agreed on which would have eventuated in an award of $607,000.
We think that with minor alterations Westvaco’s calculations come much closer to the maximum viable numbers while also correctly following the contractual damage formula. Westvaco, indulging all the aforementioned assumptions in Jamison’s favor, argues that the maximum percentage of profit which the jury could lawfully grant plaintiff could not exceed 33% of the realizable budgeted profit plus contingency fund.
$381,000 previous subtotal
83,000 proportionate share of budgeted profit & contingency
_ fund
$464,000 subtotal
$607,000 verdict
(464.0001 subtotal
$143,000 shortfall per Westvaco calculations
Plaintiff, attempting to overcome this deficiency, observes that the district court’s instruction, reflecting the language of the contract, called for recovery of termination expenses. Jamison then recounts certain testified to termination expenses — Mr. Jamison’s plane trip to Wickliffe and New York; shipping welding fittings to Wickliffe; litigation with another company; and calculations undertaken for settlement purposes. However, even assuming that the aggregate of these four items equals the needed $143,000, plaintiff failed to introduce any evidence as to their dollar amount. The jury cannot be left to speculate as to the size of attorney’s fees or the cost of airplane tickets, nor can we correct on appeal counsel’s failure to offer the needed evidence.
Finally, still under this first theory, plaintiff contends that even if it cannot offer a viable rationale for the $607,000 damage award, that award “was within the range of evidence,” and “not so gross as to shock the conscience of the court.” Plaintiff’s statements have no significance here. A verdict in excess of the maximum amount calculable from the evidence is not legally “within the range of evidence.” In addition, the “shock the conscience standard” is not appropriate in this case. The decisions. Jamison cites in support of this test are tort controversies.
2. The Time Elapsed Approach.
Appellee’s second theory for supporting the verdict argues that the jury could have decided that “a proportionate share of the work done was reasonably related to the time spent on the job by Jamison Company.” Continuing, Jami-son argues that because of the time elapsed under the first contract represented 4/r of the contractually allocated time for that job and 4/io of the time provided for the second contract, the jury could have awarded those fractional parts of the actual contract price. This manner of calculation permits a maximum verdict of nearly $800,000.
3. The Previous Success Approach.
Appellee’s third effort to buoy the verdict begins with a recitation of testimony of plaintiff’s previous commercial successes. Plaintiff then reasons that this evidence “fully supported a finding that . . . Jamison Company would have completed the Wickliffe project with flying colors and enjoyed its just deserts.” However, even if we accept previous successes as probative of plaintiff’s likely profit realization,
B. The Settlement Count
The district court correctly instructed the jury that it could award
$487,000 direct costs
43.000 allocated overhead
76.000 owed to Jamison (Luke)
$606,000
(225.000) prior payments to Jamison
$381,000 Total per settlement claim
$607,000 verdict
(381.000) total per settlement claim
$226,000 shortfall
Having examined the plaintiff’s arguments, we remain unconvinced that any set of calculations with a rational basis in the evidence can justify the jury’s $607,000 award. Plaintiff claims many roads lead to his Rome; yet we encounter only insurmountable roadblocks and unending detours. Therefore, this Court finds that the district court abused its discretion in denying appellant’s motion for a new trial.
III. THE TERMINATION WITHOUT CAUSE INSTRUCTION
The controversy described at note 6 supra concerning Jamison’s usé of figures reflecting costs incurred rather than value rendered underlines the unfortunate ambiguity of the district court’s “termination without cause” instruction.
Although noting the charge’s fatal deficiencies ourselves, we think that the district court, pursuant to its duty to interpret the contract, see generally S. Williston Contracts § 601 "(3 ed. 1961), ought to have the first opportunity to draft a proper “termination without cause” instruction on retrial. This approach commends itself principally because the necessary prior determination of the parties’ intent often depends on evidence relating to contract formation, customary usages, and other surrounding circumstances which may be presented at a new trial and therefore is not before us now. Although we do not here versify a charge, the importance of this question at retrial merits a few brief remarks.
We consider first the problem raised by the cost incurred-value rendered dispute. See note 6 supra. Initially, the language of the two termination clauses suggests that when the parties intended to use the “value to Westvaco” measure, they wrote, as we encounter in the “termination with cause” clause,
We also note that the “termination without cause” clause speaks of a percentage “of the contract price.” The District Court should inquire as to whether the parties intended 1) a percentage of the entire contract price ($1,709,000) or 2) a percentage of the non-profit element of the contract ($1,709,000 less the contractor’s expected profit margin) plus a separate addition of the same percentage of that part of the profit element which the contractor can demonstrate he would have realized. The second measure reflects both the instruction given at the first trial and the general contract concept that profits can be awarded only if the jury finds a reasonable certainty that they would have been earned. See generally S. Williston, Contracts § 1345 (3 ed. 1968). However, by the literal language “a proportionate share of the Contract price,” the parties may have intended the first measure— that is, a portion of the contract price without regard to any division into profit and non-profit components and consequently without consideration of the likelihood of the contractor’s actually achieving a profit.
The same analysis would apply with respect to Jamison’s claim to another element of damages — a contingency against losses fund.
We realize that this case is not simple, and the charge is not easily constructed. Yet determinations of contract damages cannot be a guessing game. The butcher, the baker, and the candlestick maker, and all who although unversed in the jargon of today’s complex contracts comprise our juries cannot be left to founder on the shoals of inexactitude or to experience the confusion engendered by the dim light of a vague instruction. The district court and the parties must provide the jury with the instructional equivalent of the mariner’s compass and sea-lane map in order that the lay jurors might successfully complete their voyage.
We realize that all of the points discussed above raise difficult questions requiring careful consideration. We hope that at retrial the district court, in the light of all of the testimony and evidence, will resolve these questions and thereafter translate the answers into a jury charge more precise and more helpful than the one pronounced at the original trial.
IV. THE USE OF SPECIAL INTERROGATORIES
Because this litigation is nearly six years old and because the original trial lasted three weeks, we hesitate to re.quire a new trial on all issues. However, the district court’s use of a general verdict leaves us' no alternative.
Generally, in cases such as this, the appellate court avoids a wasteful retrial of the entire controversy through the use of one of two devices. First, the court can order remittitur, setting the approved figure itself, see generally C. Wright & A. Miller, Federal Practice & Procedure § 2820 (1973), or remanding to the district court for that determination. See, e. g., Natco, Inc. v. Williams Brothers Engineering Co., 5 Cir. 1974, 489 F.2d 639, 641. Yet without knowing whether the jury found for the plaintiff on the “termination without cause” or on the
Chief Judge Brown has on many occasions considered the problems discussed above and wisely expounded on the role to be played in their solution by properly administered Rule 49(a) special interrogatories.
Admittedly, the decision to use Rule 49(a) remains within the informed discretion of the trial court. Miskell v. Southern Food Co., 5 Cir. 1971, 439 F.2d 790; see C. Wright & A. Miller, Federal Practice & Procedure § 2505 (1971). However, we would be remiss were we not to remind the District Judge that in lengthy multi-issue cases such as this one, the additional exertion initially required to instruct the jury pursuant to that rule is miniscule when compared to the efforts which the district court, as well as the parties, will expend on retrial. We believe that special interrogatories would be particularly appropriate here.
After analyzing the contract, evidence, charge, and jury verdict with their many possible alternatives, asymetrical incongruencies, potential solecisms, and error compounded upon error, we have no doubt but that the jury verdict was ei
Reversed and remanded.
. The “termination with cause” clause stated:
If, in the opinion of the Owner, the Contractor’s financial condition shall become impaired or he should persistently or repeatedly refuse or fail to supply enough properly skilled workmen or proper materials, or if he should fail to make prompt payment for material, services or labor, or if he should persistently disregard laws, ordinances or the instructions of the Owner of if he should violate any provision of the Contract, the Owner may, without prejudice to its other rights or remedies, stop the Work forthwith, take possession of the Work, terminate the Contract and finish the Work by whatever method the Owner may deem expedient. In case such right is exercised by the Owner, the amount due the Contractor shall be that portion of the costs incurred beneficial to the Owner’s interest. Such sums shall not be payable to the Contractor until final payment would otherwise be due. If the expense of finishing the Work shall exceed the difference between the Contract price and the beneficial costs incurred, the Owner shall, in paying the Contractor, deduct such difference from the amount otherwise due.
If the Owner exercises such right for any ■ other than the above reasons [those expressed in the “termination with cause” clause], the Contractor shall be entitled to receive a proportionate share of the Contract price based on the amount of the Work completed plus the reasonable expenses of such termination.
. All figures have been rounded down to the nearest $1000 for purposes of this opinion.
. The district court unfortunately used a general verdict, thereby obscuring any determination of which count' the jurors might have found decisive. See Section IV infra. It is possible that the jury, rejecting Jamison’s contentions, found that the termination was for cause, but for the reasons suggested at note 27 infra, returned a verdict in Jamison’s favor. However, we need not analyze the sufficiency of the evidence under the “termination with cause” theory because our determinations with respect to the evidence supporting the other two claims and with respect to the excessive damages question render irrelevant to the disposition of this case any decision as to the sufficiency of the evidence on the “termination with cause” claim.
. Mr. Jamison testified:
Well ... to the best of my memory, Mr. Noble [Westvaco] said, “Ernie [Jami-son], I’m sorry that we just don’t think we had better go along with you in this particular setup. If you will go back to Atlanta and get your figures together as quickly as possible, we will settle with you.”
Now, I had said I would settle with them 011 a cost basis that would show my concern and feeling that their best interests should serve, that we would settle on a cost basis, and that is the way 1 understood it was terminated,
. The Court gave the following instructions in connection with the other claims:
[With respect to the “termination with cause” clause and related counterclaim] if you find that the termination of the contracts by Westvaco was justified and proper, Jamison then would be entitled to recover of Westvaco only that portion of its costs incurred which were beneficial to Westvaco, less any excess expense which was necessary and reasonable for Westvaco to finish the work of Jamison and less any payments made by Westvaco to or for the benefit of Jamison. [S]hould you find that Westvaco reasonably exercised its termination rights . in terminating Jamison and selecting another contractor to complete the work, then you would be authorized in returning a verdict for Westvaco against Jamison for the amount, if any, in excess of the price for which Jamison had agreed to perform the work less the value of the work which Jami-son had performed up to the time of termination.
[With respect to the settlement agreement count] if you should find from the evidence that the parties did enter into a definite, certain and unambiguous settlement agreement to pay Jamison the amount of Jamison’s direct costs incurred in performing the Wickliffe contracts, then you could find in favor of Jamison against Westvaco in the amount of such direct costs, less payments made by Westvaco to or on behalf of Jamison.
. For purposes of our analysis, we employ plaintiff’s cost theory and its accompanying estimates, as introduced at trial, of its actual costs. Defendant, objecting to these cost calculations, argues that the instruction “the proportionate share of the contract price, based on work done” does not encompass all costs incurred by Jamison. Rather, Westvaco suggests that that phrase means the value to Westvaco of Jamison’s work. The difference between these two measures might have been significant given Westvaco’s argument that Jamison incurred substantial inefficiencies and cost overruns which created expense for the plaintiff but no corresponding benefit to the defendant. For a discussion of the propriety of using either standard as well as the need for a clearer, more precise instruction see Section III infra.
.
614% X $667,000 (1st contract) = $ 43,000
7% X $1,042,000 (2nd contract) = 73.000
$116,000/
. Jamison’s argument for inclusion of the contingency fund treats the fund like an element of profit. The court’s instruction was silent with respect to the existence of the contingency fund. See Section III infra. For purposes , of this analysis only, we accept Jamison’s contention that the contingency fund should be part of the cost based calculations and treat the fund as an additional element of profit. '
. Insofar as one might read “proportionate share of profits. . . . ” as requiring inclusion of the share of realizable profits rather than a proportion (“based on work done”) of the share of realizable profits, we confront a charge which is erroneous for the reason that it is inconsistent with the governing contractual clause. See Section III & n. 22 infra.
. This manner of calculating damages varies from the normal rules governing an award for breach of a construction contract. See Crankshaw v. Stanley Homes, Inc., 131 Ga.App. 840, 207 S.E.2d 241 (1974); J. Calamari & J. Perillo, Contracts § 229 (1970); J. Corbin, 5 Contracts § 1094 (1951). The parties may devise and the courts will enforce a contractual provision for damages different from the common law remedy so long as the provision is not unreasonable. See, e. g., United States v. Harris, 9 Cir. 1938, 100 F.2d 268, 278.
.
85% X $266,300^ $226,000 budgeted profit * & contingency fund
381.000 previous subtotal
607.000 verdict met
. Speculating as to possible jury calculations, Jamison adds $266,000. The use of the $266,-000 figure has the virtue from plaintiffs point of view of justifying the jury verdict. However, $266,000 does not represent a number based on the percentage of “work done” but instead is the whole amount (100%) of the budgeted profit plus contingency fund. As noted above, we find no evidentiary justification even for an 85% figure.
For this same reason, among- others, we reject Jamison’s effort to attach crucial significance to Westvaco’s counsel’s closing argument to the jury wherein counsel said: “If they [Jamison Company] had done what they said they would do and it had worked for them; they would have gotten $250,000 to keep. ...”
. Westvaco figures that if plaintiff received credit for its Wickliffe costs ($487,000), then the “proportionate share of the contract price, based on work done” must equal the ratio of those costs ($487,000) on the one hand to the total contract price ($1,709,000) less the budgeted profited ($116,000) and contingency fund ($150,000) on the other hand.
$487,000 $487,000 _
_ $1,709,000-$266,000 $1,443,000 0/0
. In its brief, plaintiff asserts “[w]hile no precise figures were presented as to the amounts of these expenses, the jury could easily and properly have valued these expenses in accordance with the lower court’s charge.” Plaintiff not only does not tell us how the jury might have valued the individual expenses, but also neglects to inform the appellate court of the actual total expense. It is possible that the termination costs might not even equal the $143,000 discussed above as necessary to reach the $607,000 verdict.
. Brown v. Louisiana & Ark. Ry., 5 Cir. 1970, 429 F.2d 1265; Massachusetts Bonding & Ins. Co. v. Abbott, 5 Cir. 1961, 287 F.2d 547.
$667,000 contract 1 price X .5714 (4/7 — time elapsed)
$381,000 $381,000
$1,042,000 contract 2 price
X_A (4/10 — time elapsed)
$ 417,000 $407.000
$709,000
. See Section III infra.
. In fact, our former cost analysis assumed a jury finding that plaintiff would have realized the full measure ($266,000) of budgeted profit and contingency funds had it been permitted to complete the contracts. See Section II.A. supra. However, plaintiff still has failed to justify the needed 85% allocation of those potentially realizable profits.
. See note 5 supra.
. See text at note 5 supra.
. See note 1 supra.
. Other instances of ambiguous and potentially misleading language in the instruction delivered at the first trial include the judge’s statement, “I further charge you that such damages would include the proportionate share of profits that would have been realized by Jamison if full performance had been permitted.” To compute damages correctly, the jurors would have had to figure out that “proportionate share of profits” means not that part of the profits which were realizable but instead that portion of the realizable profits reflecting the percentage of “work done.” See note 9 supra. If the jurors had reached this stage, they would have had to understand that they were not to add the just calculated “proportionate share of profits” to the earlier calculated total representing “the proportionate share of the contract price, based on work done.” Instead, they were to leave unchanged the “proportionate share of the contract price, based on work done” unless the realizable profits were less than 100% of the anticipated profits. If the realizable profits had been less than 100% of the anticipated profits, then the jurors would have had to reduce the “proportionate share of the contract price, based on work done” by the amount equal to the unrealizable profits times the percentage of “work done.”
Another problem involves the trial court’s statement, “From that amount should be deducted any payments made by Westvaeo to or for the benefit of Jamison.” It is not clear whether “that amount” refers a) to the immediately preceding discussion of the “proportionate share of the profits that would have been realized by Jamison if full performance had been permitted,” or b) to the earlier mentioned “proportionate share of the contract price, based on work done.” If the jurors had determined that the reference was to the immediately preceding discussion (a above) and if the prior payments had exceeded the amount of the realizable profits reflecting the percentage of “work done” (i. e. “the proportionate share of the profits”), then a negative number would have resulted upon juror subtraction. Unless the jurors carried this negative number back and deduoted it from their calculation of the “proportionate share of the contract price, based on work done,”
Finally, we note that the district court sent the actual contract to the jury room. However, the availability of the contractual language cannot be said to obviate the potential confusion discussed above.
. See Sections II.A.l., H.A.2., & II.A.3. supra.
. See note 1 supra.
. Id.
. See note 8 supra.
. Although unlikely, it is not inconceivable that the jury premised its verdict on neither of the above theories but instead on the “termination with cause” clause. Under that provision, the district court had instructed the jury to award Jamison those “costs incurred which were beneficial to Westvaco, less any excess expense which was necessary and reasonable for Westvaco to finish the work of Jamison. . ” The jury might have agreed on $607,000 in beneficial costs to Westvaco (an amount not supported by the evidence) and also found unreasonable the excess costs for finishing the job claimed by Westvaco. Here again, the general verdict forecloses ascertainment of the liability basis of the jury’s award.
. Rule 49(a) states in pertinent part:
The court may require a jury to return only a special verdict in the form of a special written finding upon each issue of fact. In that event the court may submit to the jury written questions susceptible of categorical or other brief answer or may submit written forms of the several special findings which might properly be made under the pleadings and evidence; or it may use such other method of submitting the issues and requiring the written findings thereon as it deems most appropriate.
Concurrence Opinion
(specially concurring).
I concur in Judge Goldberg’s able and enlightening opinion. As to part IB (The ' Settlement Claim), however, I would like to add this: It may be acceptable to assume, arguendo, there was evidence to go to the jury that the parties made a settlement agreement, since we hold such agreement anyway fails to support the verdict as returned, but I feel considerable doubt about the testimony quoted in fn. 4. Whether the evidence most favorable for plaintiff shows an enforceable agreement is not a question of fact for the jury, but one of law for the judge. Suppose the offer and acceptance were to “settle on a cost basis”, I read this as only an undertaking to negotiate a settlement on the basis of cost figures. If such negotiation had occurred, the parties would have had several matters to decide, on which their minds had not yet met, e. g., was the basis direct costs only, as the trial judge instructed, or all costs?
As to part II, text after fn. 7, the so-called “contingency fund” was only the percentage usually added by a construction contractor to his cost estimates in preparing his bid, to allow a cushion for the operation of Murphy’s law. It does not represent profit the bidder expects to realize, but rather profit he expects to lose, one way or another. The record showed here, it was almost all lost even before termination. I would not add it to the expected profit even arguendo, as it is not properly awardable.
If, contrary to my view, the parties made a valid and enforceable agreement settling plaintiff’s claim, it would be a defense against that claim so far as founded on either branch of the termination clause. The questions for the special verdict should be so framed as to effectuate this consequence.