On 30 August 2004, the trial court dismissed plaintiff’s tort, contract, and equity claims against defendants Mecklenburg Utilities, Inc., (“Mecklenburg”) and the Orange County Board of Education (“the Board”), with prejudice. Plaintiff appeals. We affirm in part and reverse in part and remand.
In 2000, the Board entered a contract with Mecklenburg for grading services for construction of a new high school. Under the contract, Mecklenburg would furnish the payment bond required by state *339 law; Mecklenburg procured a payment bond from Amwest Surety Insurance Company (“the surety”). Mecklenburg, the general contractor, sub-contracted with Tharpe’s Excavating, Inc., (“Tharpe’s”), with Jeffrey W. Tharpe as guarantor, for a portion of the grading work. In turn, Tharpe’s rented equipment from plaintiff, James River Equipment. Tharpe’s failed to pay over $500,000 owed to plaintiff and, in April 2001, plaintiff gave notice of non-payment to the Board, Mecklenburg, and the surety. In June 2001, the surety gave notice to the Board and Mecklenburg that it was insolvent and had been placed in receivership. Mecklenburg did not furnish a replacement bond.
In 2002, plaintiff brought this suit against the Board, Mecklenburg, Tharpe’s and Tharpe. Plaintiff’s complaint sets forth the following counts: Count I claims breach of the contract between Tharpe’s and plaintiff; Count II seeks recovery from Tharpe as guarantor of plaintiff’s contract with Tharpe’s; Count III claims a lien on funds held by the Board and Mecklenburg at the time they learned the surety was insolvent; Count IV is a claim of quantum meruit against all defendants; Count V seeks an equitable lien against the Board and Mecklenburg to prevent unjust enrichment; Count VI claims breach of a contract between the Board and Mecklenburg; Count VII against the Board claims breach of warranty; and Count VIII against the Board claims negligence for failure to retain funds. Plaintiff later amended the complaint to add equal protection and due process claims against the Board. Upon motions to dismiss by defendants Mecklenburg and the Board, the trial court dismissed all claims against the Board and Mecklenburg pursuant to Rule 12(b)(6). The trial court also found no just reason for delay of appellate review of the dismissed claims and thus certified the case for appeal pursuant to Rule 54(b). The court did not dismiss the counts against Tharpe’s and Tharpe for breach of contract and guaranty, which were still pending in superior court at the filing of this appeal.
Orders which do not dispose of the action as to all parties are treated as interlocutory.
Cunningham v. Brown,
In its brief, James River has included a statement of grounds for appellate review, as required by Rule 28(b)(4). N.C. R. App. P. 28(b)(4) (2004). When the Supreme Court amended Rule 28(b) in 2001, it added subsection 4, which reads in its entirety as follows:
Such statement shall include citation of the statute or statutes permitting appellate review. When an appeal is based on Rule 54(b) of the Rules of Civil Procedure, the statement shall show that there has been a final judgment as to one or more but fewer than all of the claims or parties and that there has been a certification by the trial court that there is no just reason for delay. When an appeal is interlocutory, the statement must contain sufficient facts and argument to support appellate review on the ground that the challenged order affects a substantial fight.
Id.
We read this rule as requiring that, when an appeal is from an order which is
final
as to one party, but not all, and where the trial court has certified the matter under Rule 54(b), we must review the issue. This interpretation is consistent with the Supreme Court’s previous holding that where the trial court issued a Rule 54(b) certification on a final judgment as to one or more party but not all, this Court is required to review the case.
DKH Corp. v. Rankin-Patterson Oil Co., Inc.,
However, we note that when an appeal is from an interlocutory,
not final,
order as to any party (e.g., one which disposes of some but not all claims against that party), the appellant must include an explanation of why the case affects a substantial right, even if the trial court has certified that there is no just reason for delay. “[T]he trial court’s determination that there is no just reason for delay of appeal, while accorded deference, cannot bind the appellate courts because ruling on the interlocutory nature of appeals is properly a matter for the appellate division, not the trial court.”
Anderson v. Atlantic Cas. Ins. Co.,
Plaintiff first argues that the trial court erred in dismissing its claim in Count VI of its complaint, that the Board and Mecklenburg breached their contractual and statutory duty to provide an adequate bond throughout the life of a project. We review the trial court’s grant of a 12(b)(6) motion to dismiss
de novo. Grant Constr. Co. v. McRae,
N.C. Gen. Stat. §§ 44A-25 through 44A-35 (2003)', commonly known as the Little Miller Act (“the Act”), governs payment and performance bonds for state construction contracts. Section 44A-26, entitled
“Bonds Required,” states in pertinent part that,
(a) When the total amount of construction contracts awarded for any one project exceeds three hundred thousand dollars ($ 300,000), a performance and payment bond as set forth in (1) and (2) is required by the contracting body from any contractor or construction manager at risk with a contract more than fifty thousand dollars ($ 50,000).
***
(2) A payment bond in the amount of one hundred percent (100%) of the construction contract amount, conditioned upon the prompt payment for all labor or materials for which a contractor or subcontractor is liable. The payment bond shall be solely for the protection of the persons furnishing materials or performing labor for which a contractor, subcontractor, or construction manager at risk is liable.
*342 (b) The performance bond and the payment bond shall be executed by one or more surety companies legally authorized to do business in the State of North Carolina and shall become effective upon the awarding of the construction contract.
Id. (emphasis addded). Defendants do not dispute that they were required to provide a bond, but assert that they complied with the Act when they, secured a surety that “became effective upon the awarding of the construction contract.” However, the statute is silent regarding whether the bond is required for the life of the project and this issue is one of first impression.
Pursuant to fundamental principles of statutory construction, we must first seek to discern the intent of the legislature, and in seeking to ascertain the legislative intent, the statutory language should be construed in context.
See Powell v. State Employees’ Retirement System,
Although we conclude that N.C. Gen. Stat. § 44A-26 requires that the contracting body and the general contractor provide a payment *343 bond for the life of the project, we also conclude that plaintiff here has no civil remedy against the Board for this alleged violation of the duty to maintain a bond. N.C. Gen. Stat. § 44A-32 provides that “[e]ach contracting body shall designate an official thereof to require the bonds described by this Article. If the official so designated shall fail to require said bond, he shall be guilty of a Class 1 misdemeanor.” Id. The North Carolina Supreme Court has held that as against a government contracting body,
criminal indictment is the only remedy prescribed by the statute, and we must declare the law as we find it. The Legislature alone may change it, if it is thought to be inadequate. Plaintiffs rights and remedies against the defendant board and its members are statutory, and the courts are not at liberty to extend a penal statute, or one of this kind, beyond the clear meaning of its terms. The legislative intent must be the controlling spirit in the construction and application of statutes of this nature.
Noland Company, Inc., v. Board of Trustees of Southern Pines School,
In claim VI of its complaint, plaintiff also argues that Mecklenburg is liable for failure to provide an adequate bond for the life of the project. Plaintiff was not a party to the contract between the Board and Mecklenburg, and thus seeks recovery as a third-party beneficiary. “[A] third party beneficiary to an agreement may properly maintain an action for its breach, where the agreement is made for the third party’s direct benefit and the benefit accruing to him is not merely incidental.”
Woolard v. Davenport,
[t]o execute bond with one or more solvent sureties before beginning any work under said contract, payable to said county, city, town or other municipal corporation, and conditioned on payment of all labor done on and material and supplies furnished for said work under a contract or agreement made directly with the principal contractor or subcontractor.
Id. As the Act has since been amended, we conclude that we are not bound by Carolina Builders on this issue. Pursuant to N.C. Gen. Stat. § 44A-26(a)(2), as amended in 1973, the statutory bond requirement of the contract between the Board and Mecklenburg is clearly and explicitly for the direct benefit of laborers and subcontractors such as plaintiff. Thus, the allegations in count VI are sufficient to state a claim on this basis, and we reverse the trial court’s dismissal of this claim as to Mecklenburg.
In its next argument, plaintiff argues that the trial court erred in denying plaintiffs motion to reconsider the dismissal of certain of their claims. As to the dismissals we are affirming, we disagree; as to the dismissals we are reversing, we need not address this issue. Plaintiff filed a motion for reconsideration, alleging that it had new information that the Board required Mecklenburg to provide a replacement bond after it learned of the surety’s insolvency, but only for contractors doing work from that point forward, which excluded plaintiff. Plaintiff asserts that this was unequal and arbitrary treatment of subcontractors, in violation of plaintiff’s constitutional rights to Equal Protection and Due Process under the United States and North Carolina Gonstitutions.
We review the trial court’s denial of a motion for reconsideration for abuse of discretion and reverse only upon “a showing that [the] ruling was so arbitrary that it could not have been the result of a reasoned decision.”
Muse v. Charter Hospital of Winston-Salem, Inc.,
Plaintiff also contends in count III that the trial court erred in dismissing its claim that it had a lien on funds in the hands of the Board and Mecklenburg at the time they learned that the surety was insolvent. A materialmen’s lien on funds is a statutory remedy which arises under Article 2 of Chapter 44A of our General Statutes. N.C. Gen. Stat. § 44A-18(l)-(4) (2004). However, section 44A-34 states that “this Article shall not be construed as making the provisions of Articles 1 and 2 of Chapter 44A of the General Statutes apply to public bodies or public buildings.”
Id.
We conclude that the trial court properly dismissed this claim as to the Board. In contrast, Mecklenburg is not a public body, and plaintiff sought a lien against funds, not the public building itself, and we find nothing in the Act which would exclude a private general contractor from the provisions of Article 2. Accordingly, we conclude that the trial court erred in dismissing plaintiff’s claim III for a lien on funds against Mecklenburg. Plaintiff also argues that it was entitled to an equitable lien against both defendants. However, an equitable lien is available only where a party has no adequate remedy at law.
Embree Const. Group, Inc., v. Rafcor, Inc.,
*346 Plaintiff next argues that the trial court erred in dismissing its claim, count VIII, that the Board violated its duty of reasonable care to require a payment bond for the protection of subcontractors through the life of the project. As discussed earlier, plaintiff has no civil remedy against the Board for its violation of the duty to maintain a bond. N.C. Gen. Stat. § 44A-32. We overrule this assignment of error.
In its final argument, plaintiff asserts that the trial court erred in dismissing count IV of its complaint, its claim in
quantum meruit
against the Board and Mecklenburg. As previously discussed, we conclude that plaintiff has no civil remedy against the Board in this action. However, we conclude that the trial court erroneously dismissed plaintiffs
quantum meruit
claim against Mecklenburg. Plaintiff alleges that Mecklenburg has been unjustly enriched because it received the benefit of the services and materials it provided. “An implied contract rests on the equitable principle that one should not be allowed to enrich himself unjustly at the expense of another and on the principle that what one ought to do, the law supposes him to have promised to do.”
Orange County Water and Sewer Authority v. Town of Carrboro,
Finally, we must address defendants’ cross-assignments of error. The Board and Mecklenburg argue that the trial court erred in denying their Rule 41(b) motions to dismiss for failure to prosecute. We disagree. Plaintiff originally filed its action in March 2002 and subsequently obtained ten alias and pluries summons between the original filing and October 2003. The Board and Mecklenburg moved to dismiss for failure to prosecute pursuant to N.C. Rule. Civ. P. 41(b). N.C. Gen. Stat. § 1A-1, Rule 41(b) (2003). The trial court denied these motions, finding that “although the delay in service of the Complaint was substantial and unusual, the delay was not deliberate or for an improper motive or purpose and no material prejudice was caused to either [defendant]... and therefore, both the Defendants’ Motions to
*347
Dismiss pursuant to Rule 41 (b) should be denied.” It is well-established that dismissal under Rule 41(b) is left to the sound discretion of the trial court.
Smith v. Quinn,
Affirmed in part; reversed in part and remanded.
