James River Equipment, Inc. v. Tharpe's Excavating, Inc.James River Equipment, Inc. v. Tharpe's Excavating, Inc.
On 30 August 2004, the trial court dismissed plaintiff’s tort, contract, and equity claims against defendants Mecklenburg Utilities, Inc., (“Mecklenburg”) and the Orange County Board of Education (“the Board”), with prejudice. Plaintiff appeals. We affirm in part and reverse in part and remand.
In 2000, the Board entered a contract with Mecklenburg for grading services for construction of a new high school. Under the contract, Mecklenburg would furnish the payment bond required by state law; Mecklenburg procured a payment bond from Amwest Surety Insurance Company (“the surety”). Mecklenburg, the general contractor, sub-contracted with Tharpe’s Excavating, Inc., (“Tharpe’s”), with Jeffrey W. Tharpe as guarantor, for a portion of the grading work. In turn, Tharpe’s rented equipment from plaintiff, James River Equipment. Tharpe’s failed to pay over $500,000 owed to plaintiff and, in April 2001, plaintiff gave notice of non-payment to the Board, Mecklenburg, and the surety. In June 2001, the surety gave notice to the Board and Mecklenburg that it was insolvent and had been placed in receivership. Mecklenburg did not furnish a replacement bond.
Orders which do not dispose of the action as to all parties are treated as interlocutory.
Cunningham v. Brown,
In its brief, James River has included a statement of grounds for appellate review, as required by Rule 28(b)(4).
Such statement shall include citation of the statute or statutes permitting appellate review. When an appeal is based onRule 54(b) of the Rules of Civil Procedure, the statement shall show that there has been a final judgment as to one or more but fewer than all of the claims or parties and that there has been a certification by the trial court that there is no just reason for delay. When an appeal is interlocutory, the statement must contain sufficient facts and argument to support appellate review on the ground that the challenged order affects a substantial fight.
Id.
We read this rule as requiring that, when an appeal is from an order which is
final
as to one party, but not all, and where the trial court has certified the matter under
However, we note that when an appeal is from an interlocutory,
not final,
order as to any party (e.g., one which disposes of some but not all claims against that party), the appellant must include an explanation of why the case affects a substantial right, even if the trial court has certified that there is no just reason for delay. “[T]he trial court’s determination that there is no just reason for delay of appeal, while accorded deference, cannot bind the appellate courts because ruling on the interlocutory nature of appeals is properly a matter for the appellate
Plaintiff first argues that the trial court erred in dismissing its claim in Count VI of its complaint, that the Board and Mecklenburg breached their contractual and statutory duty to provide an adequate bond throughout the life of a project. We review the trial court’s grant of a 12(b)(6) motion to dismiss
de novo. Grant Constr. Co. v. McRae,
“Bonds Required,” states in pertinent part that,
(a) When the total amount of construction contracts awarded for any one project exceeds three hundred thousand dollars ($ 300,000), a performance and payment bond as set forth in (1) and (2) is required by the contracting body from any contractor or construction manager at risk with a contract more than fifty thousand dollars ($ 50,000).
***
(2) A payment bond in the amount of one hundred percent (100%) of the construction contract amount, conditioned upon the prompt payment for all labor or materials for which a contractor or subcontractor is liable. The payment bond shall be solely for the protection of the persons furnishing materials or performing labor for which a contractor, subcontractor, or construction manager at risk is liable.
(b) The performance bond and the payment bond shall be executed by one or more surety companies legally authorized to do business in the State of North Carolina and shall become effective upon the awarding of the construction contract.
Id. (emphasis addded). Defendants do not dispute that they were required to provide a bond, but assert that they complied with the Act when they, secured a surety that “became effective upon the awarding of the construction contract.” However, the statute is silent regarding whether the bond is required for the life of the project and this issue is one of first impression.
Pursuant to fundamental principles of statutory construction, we must first seek to discern the intent of the legislature, and in seeking to ascertain the legislative intent, the statutory language should be construed in context.
See Powell v. State Employees’ Retirement System,
Although we conclude that
criminal indictment is the only remedy prescribed by the statute, and we must declare the law as we find it. The Legislature alone may change it, if it is thought to be inadequate. Plaintiffs rights and remedies against the defendant board and its members are statutory, and the courts are not at liberty to extend a penal statute, or one of this kind, beyond the clear meaning of its terms. The legislative intent must be the controlling spirit in the construction and application of statutes of this nature.
Noland Company, Inc., v. Board of Trustees of Southern Pines School,
In claim VI of its complaint, plaintiff also argues that Mecklenburg is liable for failure to provide an adequate bond for the life of the project. Plaintiff was not a party to the contract between the Board and Mecklenburg, and thus seeks recovery as a third-party beneficiary. “[A] third party beneficiary to an agreement may properly maintain an action for its breach, where the agreement is made for the third party’s direct benefit and the benefit accruing to him is not merely incidental.”
Woolard v. Davenport,
[t]o execute bond with one or more solvent sureties before beginning any work under said contract, payable to said county, city, town or other municipal corporation, and conditioned on payment of all labor done on and material and supplies furnished for said work under a contract or agreementmade directly with the principal contractor or subcontractor.
Id.
As the Act has since been amended, we conclude that we are not bound by
Carolina Builders
on this issue. Pursuant to
In its next argument, plaintiff argues that the trial court erred in denying plaintiffs motion to reconsider the dismissal of certain of their claims. As to the dismissals we are affirming, we disagree; as to the dismissals we are reversing, we need not address this issue. Plaintiff filed a motion for reconsideration, alleging that it had new information that the Board required Mecklenburg to provide a replacement bond after it learned of the surety’s insolvency, but only for contractors doing work from that point forward, which excluded plaintiff. Plaintiff asserts that this was unequal and arbitrary treatment of subcontractors, in violation of plaintiff’s constitutional rights to Equal Protection and Due Process under the United States and North Carolina Gonstitutions.
We review the trial court’s denial of a motion for reconsideration for abuse of discretion and reverse only upon “a showing that [the] ruling was so arbitrary that it could not have been the result of a reasoned decision.”
Muse v. Charter Hospital of Winston-Salem, Inc.,
Plaintiff also contends in count III that the trial court erred in dismissing its claim that it had a lien on funds in the hands of the Board and Mecklenburg at the time they learned that the surety was insolvent. A materialmen’s lien on funds is a statutory remedy which arises under Article 2 of Chapter 44A of our General Statutes.
Plaintiff next argues that the trial court erred in dismissing its claim, count VIII, that the Board violated its duty of reasonable care to require a payment bond for the protection of subcontractors through the life of the project. As discussed earlier, plaintiff has no civil remedy against the Board for its violation of the duty to maintain a bond.
In its final argument, plaintiff asserts that the trial court erred in dismissing count IV of its complaint, its claim in
quantum meruit
against the Board and Mecklenburg. As previously discussed, we conclude that plaintiff has no civil remedy against the Board in this action. However, we conclude that the trial court erroneously dismissed plaintiffs
quantum meruit
claim against Mecklenburg. Plaintiff alleges that Mecklenburg has been unjustly enriched because it received the benefit of the services and materials it provided. “An implied contract rests on the equitable principle that one should not be allowed to enrich himself unjustly at the expense of another and on the principle that what one ought to do, the law supposes him to have promised to do.”
Orange County Water and Sewer Authority v. Town of Carrboro,
Finally, we must address defendants’ cross-assignments of error. The Board and Mecklenburg argue that the trial court erred in denying their Rule 41(b) motions to dismiss for failure to prosecute. We disagree. Plaintiff originally filed its action in March 2002 and subsequently obtained ten alias and pluries summons between the original filing and October 2003. The Board and Mecklenburg moved to dismiss for failure to prosecute pursuant to N.C. Rule. Civ. P. 41(b).
Affirmed in part; reversed in part and remanded.