Landowners in Louisiana sued the United States Government for blocking a local land reclamation project. The United States Court of Federal Claims held that the statute of limitations bars their takings claims.
Creppel v. United States,
BACKGROUND
The claimants оwn swamp and marshland in Jefferson Parish, Louisiana. This land floods during the wet season. To control these floods, the Army Corps of Engineers (Corps) approved the Harvey Canal-Barata-ria Levee Project (Project) in 1964. The Corps designed the Project to close two navigable bayous and to build new levees and a pumping station. The Corps’ budgеt was $1 million. In 1967 Jefferson Parish issued $3.6 million in bonds to guarantee the remaining costs of the Project.
The Project had two phases. Phase I, completed on November 24, 1973, dredged the bayous and used the mud to begin the new levee system. Phase I exhausted the Corps’ $1 million budget. Before completion of Phase I, Congress passed the Clean Water Act of 1977 (CWA). Pub.L. No. 95-217, 91 Stat. 1567 (codified as amended in scattered sections of 33 U.S.C.). Section 404 of the CWA prohibits the discharge of dredge or fill material into navigable waterways without a permit. 33 U.S.C. § 1344 (1986 & Supp. V 1993) (section 404 of the CWA).
Under Phase II of the Project, the Corps planned to complete the levee system, close the bayous, and drain the land behind the levees. Phase II began in March 1974. The Parish lеt a contract for the pumping station to drain the land in August 1974. Mean *630 while, on July 10, 1974, the Parish stopped construction until the Corps could determine whether the Project complied with section 404.
On March 26,1975, the Corps decided that the Project should continue as originally planned. The Environmental Protection Agency (EPA) objected and suggested alternatives to draining the wetlands. The EPA also notified the Corps of its intention to use section 404(c) to prohibit construction of the levees with dredged or fill material.
After negotiations with the EPA and Parish representatives, Brigadier General Drake Wilson issued an order modifying the Project on November 16, 1976 (the Wilson Order). General Wilson ordered construction of the pumping station to halt and ordered the replacement of dikes with flood gates. This order would have eliminated the land reclamation benefits of the original Project. The EPA concurred with the Wilson Order.
Local property owners, many of whom are claimants in this case, obtained a court order permanently enjoining the Parish from abandoning the оriginal Project.
Creppel v. Parish of Jefferson,
No. 199-345 (24th Jud.Dist.Jefferson Parish, Jan. 12, 1979). They also had obtained a preliminary injunction barring the Parish from abandoning the land reclamation project on October 31,1977. This injunction became permanent as well.
Creppel v. Parish of Jefferson,
In 1977, while the state action was pending, the same landowners sued in federal district court to overturn the Wilson Order. The district court held, on summary judgmеnt, that General Wilson did not abuse his discretion in adopting the modified Project.
Creppel v. United States Army Corps of Eng’rs,
The EPA began proceedings on December 17, 1984, to determine whether to block the Project by denying a permit under section 404(c). On August 30,1985, the EPA regional administrator issued a Recommended Determination that the EPA use a section 404(c) veto. The EPA issued a Final Determination on October 16, 1985, permanently blocking the Project.
In May 1986, the landowners sought to overturn the EPA’s decision. The district court upheld the EPA’s Final Determination and remanded the case to the Corps to determine whether the Parish would grant assurances for the modified Project.
Creppel v. United States Army Corps of Eng’rs,
No. 77-25,
The claimants then filed four consolidated takings claims in the Court of Federal Claims on July 5, October 10, and October 11, 1991. The Government moved for summary judgment on the basis of a time bar under the statute of limitations. The claimants sought to amend their complaints to allege that the limitations period began only when the district court upheld the EPA’s Final Determination on June 30, 1988. The Court of Federal Claims held that the claimants’ cause of action accrued when the Wilson Order issued on November 16, 1976. The court granted summary judgment to the Government.
Creppel v. United States,
DISCUSSION
A trial court proрerly grants summary judgment only when no genuine issue of material fact exists and the law entitles the
*631
movant to judgment as a matter of law. Fed.R.Civ.P. 56(c);
Mingus Constructors, Inc. v. United States,
A six-year statute of limitations governs claims before the United States Court of Federal Claims:
[EJvery claim of which the United States Court of Federal Claims has jurisdiction shall be barred unless the [claim] thereon is filеd within six years after such claim first accrues.
28 U.S.C. § 2501 (1988 & Supp. V 1993). A claim accrues when all events have occurred that fix the alleged liability of the Government and entitle the plaintiff to institute an action.
Japanese War Notes Claimants Ass’n v. United States,
The claimants аllege two distinct takings: (1) a temporary taking commencing when the Wilson Order issued in 1976 and ending in 1988 when the district court upheld the EPA’s Final Determination; and (2) a permanent taking commencing when the EPA issued its Final Determination in 1985. The temporary taking claim is time-barred; the permanent taking claim is not.
I.
When presented with a regulatory taking claim, this court analyzes three sеparate criteria: (1) the character of the governmental action; (2) the economic impact of the regulation on the claimant; and (3) the extent that the regulation interferes with distinct investment-backed expectations of the property owmer.
Penn Cent. Transp. Co. v. City of New York,
The first criterion — the character of the governmental action — examines the challenged restraint under the lens of state nuisance law. If the regulation prevents what would or legally could have been a nuisance, then no taking оccurred. The state merely acted to protect the public under its inherent police powers.
Lucas v. South Carolina Coastal Council,
— U.S. —, —,
The second criterion — the economic impact of the regulation on the claimant — is designed to insure that not every restraint on private property results in a takings claim. This concern evolved into the threshold requirement that a claimant show that the Government denied him “economically viable use” of his land.
Agins v. Tiburon,
This criterion requires this court to determine whether a partial denial of use constitutes a taking. In this context, this court has recognized a dichotomy between noncompensable “mere diminutions” and compensable “partial takings” in borderline cases.
Florida Rock Indus., Inc. v. United States,
*632
property. Removal of all use indicates a fully compensable “categorical taking” of the property.
Lucas,
— U.S. at —,
The third criterion — the extent to which the regulation interferes with the property owner’s expectations — limits recovery to owners who can demonstrate that they bought their property in rejiance on the nonexistence of the challenged regulation. One who buys with knowledge of a restraint assumes the risk of economic loss.
Concrete Pipe & Prods., Inc. v. Construction Laborers Pension Trust for S. Cal.,
— U.S. —, —,
Finally, the Constitution recognizes a distinction between a temporary and a permanent taking. U.S. Const., amend. V;
First English Evangelical Lutheran Church v. County of Los Angeles,
II.
This case features allegations of both temporary and permanent takings. First, the temporary taking claim. On November 16, 1976, General Wilson ordered a halt to the land reclamation project. This order did not bar a nuisance, did significantly affect the economic value of the perennially flooded lands, and did abridge the owners’ expectations of gaining valuable dry lands.
As the Court of Federal Claims noted, “[i]t is evident that the act first effecting any taking of plaintiffs’ properties was the modifiсation of the original Project by the Wilson Order.”
Creppel,
The temporary taking allegedly ended on August 13, 1984, when the federal district court ordered the original Project to proceed. By restoring sоme measure of value to the claimants’ property, this action concluded the “temporary” taking.
See Hendler v. United States,
III.
This court’s recent opinion in
Loveladies Harbor, Inc. v. United States,
Thus, in
Loveladies,
this court clarified that a litigant may file a suit challenging the validity of governmental regulatory activity concurrently with a takings claim arising from the same set of facts. Furthermore, if a district court finds the regulatory activity valid, the Court of Federal Claims must hear the takings claim even if the regulatory challenge consumes more than six years. Accordingly, the Court of Federal Claims may stay a takings action pending completion of a related action in a district court.
Cf. Pennsylvania R.R. Co. v. United States,
The claimants, therefore, did not face the Hobson’s choiсe either to challenge the validity of the Wilson Order or bring a takings claim. They could have brought both suits contemporaneously and had the takings challenge stayed pending resolution of the validity issue. Instead, the claimants elected to pursue a single remedy. This conscious choice militates against “equitably tolling” the statute of limitations on the basis of the
Loveladies
decision. Otherwise, claimants would be able to file in the Court of Federal Claims as an afterthought, once their challenge in the district court was resolved. Requiring that suits be filed contemporaneously, as in
Loveladies,
better insures the claimants’ good faith and rewards the diligent prosecution of grievances. It also encourages claimants to mustеr their evidence early, and to preserve it. In addition, it prevents claimants from surprising the Government with potentially stale claims based on events that transpired many years before. Not coincidentally, these are the very reasons that statutes of limitation themselves exist.
See Chase Sec. Corp. v. Donaldson,
In addition, a federal district judge told the claimants as early as 1980 that thе Court of Federal Claims was the proper forum in which to seek compensation.
Creppel,
IV.
The claimants’ permanent taking-claim presents different questions. As this court recently held, a claim under the Fifth Amendment accrues when the taking action occurs.
Alliance of Descendants of Texas v. United States,
The sequence of events discloses an error in the trial court’s conclusion. On August 13, 1984, the federal district court ordered that the original Project proceed. Creppel, No. 77-25 (E.D.La. Aug. 13, 1984). This order rendered the Wilson Order nugatory. The EPA then commenced proceedings on December 17, 1984 to determine whether it would issue a veto under section 404(c). The district court stayed its order, *634 pending the EPA’s decision. On August 30, 1985, the EPA regional administrator issued a Recommended Determination that the EPA use a section 404(c) veto. The EPA issued a Final Determination on October 16, 1985, preventing completion of the Project.
The cоurt order that the original Project proceed, which issued on August 13, 1984, restored some potential expectation of completion of the Project and thus some measure of the property’s value. This value was maintained at least until December 1984, when the district court stayed its order. Between the invalidation of the Wilson Order in August 1984, and the stay in Dеcember 1984, the landowners owned 3,200 acres of land that appeared destined for development. By virtue of the district court’s temporary restoration of the original Project, the landowners regained the “reasonable expectation” that their property value would increase. The EPA began hearings on whether to issue a sеction 404(c) order upon expiration of the district court’s stay in December 1984. The EPA issued its order in October 1985.
Again, this court must determine when the events fixing any potential Government liability occurred.
Japanese War Notes,
The claimants filed their permanent taking claim in the Court of Federal Claims within six years after it accrued on October 16, 1985. The claim thus was not time-barred by the statute of limitations.
CONCLUSION
The claimants’ temporary taking claim is barred by the statute of limitations. Their permanent taking claim is not barred. The Court of Federal Claims shall evaluate the permanent taking claim on remand.
COSTS
Each party shall bear its own costs.
AFFIRMED-IN-PART, REVERSED-IN-PART, and REMANDED.
