Jacobs v. Northeastern Corporation, Appellant.
Supreme Court of Pennsylvania
January 12, 1965
417 Pa. 418 | 206 A.2d 49
Accordingly, I dissent.
Jacobs v. Northeastern Corporation, Appellant.
A. Richard Nernberg, with him Bernard Goodman, and McCrady & Kreimer, for appellant.
Howard K. Hilner, for appellee.
Carl A. Eck, with him J. Michael Doherty, and Meyer, Darragh, Buckler, Bebenek & Eck, for appellee.
OPINION BY MR. JUSTICE ROBERTS, January 12, 1965:
On November 11, 1961, Northeastern Corporation entered into a contract with the General State Author
Northeastern defaulted in payment of certain labor and materialmen on each project and the sureties made payment in compliance with the bonds. On the petition of James C. Jacobs, a shareholder of Northeastern, that corporation was placed in receivership.
Final payment under both construction contracts is due and owing, but the amounts due on each are less than the amounts paid to labor and materialmen by the sureties. Each surety petitioned the court below for distribution to it of the moneys due on the respective contracts. Northeastern‘s receiver resisted the petitions and counterclaimed for the retained funds contending that the sureties are entitled to only their pro rata share as general creditors, not to the entire amounts as successors to the rights of the contractor.
The court below granted the petitions of the surety companies. This appeal followed from the dismissal of the exceptions filed by the receiver. After careful consideration, we are convinced that the court below correctly determined the issues.
I
The right of the sureties to the funds rests upon the application of the doctrine of equitable subrogation. It is clear that our rule has been that the right of a
A.
In part, the construction contract with the General State Authority explicitly recites: “WHEREAS, The Contractor has given his bonds to The Authority with sufficient surety in the sum determined upon by The Authority conditioned respectively for the faithful performance of the terms of this contract, the payment of claims for labor and material ....” Paragraph Nine of this contract reads: “The Contract Bond given by the Contractor conditioned upon the faithful performance of the Contract; the payment of labor, material and equipment rental claims . . . is attached hereto and made part hereof.” Paragraph Thirteen adds: “Any person or corporation furnishing labor or material or actually renting . . . equipment to the Contractor or any Sub-contractor in connection with performance of this contract shall have a right of action to recover the cost thereof from the Contractor and the surety on the bond given to secure the payment for such labor, material or equipment rental as though such person or corporation had been named as obligee in such bond . . . .”
The pertinent provision of the bond referred to in the construction contract provides: “[I]f the above
This contract with the General State Authority, therefore, contains the specific obligation of the contractor to pay labor and materialmen. The obligation is created as a condition of the bond, and the bond is expressly made a part of the construction contract. Moreover, this particular contract gives unpaid labor and materialmen a right to recover from the principal and from the surety on the bond. A contract which explicitly grants such a right of action necessarily creates and imposes upon the contractor the obligation to pay for labor and material.
B.
The construction contract with the Secretary of Highways provides, inter alia: “2. The contractor further covenants and agrees that all of said work and labor shall be done and performed in the best and most workmanlike manner and that prompt payment will be made in full for labor and materials used in the work . . . .”
“8. The bond given by the contractor . . . to secure a proper compliance with the terms and provisions of this contract and as well as the Additional Bond . . . for the prompt payment in full for labor and material are hereto attached and made a part hereof.”
It is manifestly clear that paragraph 2, above, alone or in conjunction with paragraph 8 and the bond, creates an express undertaking upon the part of the contractor to pay labor and materialmen under the terms of the construction contract itself.
II
The practical and legal effect of the language in both contracts is identical with the language of the contract in Lancaster County Nat‘l Bank‘s Appeal, 304 Pa. 437, 155 Atl. 859 (1931). In that case, the construction contract provided that the contractor “shall not assign . . . any right to any moneys to be paid him hereunder . . . without the consent in writing of the Secretary of Highways,” and that “the Secretary will withhold the payment of any semi-final or final estimate, pending the receipt of the ‘Application for Release of Bond,‘” which application (the required form being attached) further stated it would not be granted until “all claims for labor and materials [incurred in the performance of the contract] have been satisfac
In the instant case, both the General State Authority and the Department of Highways had an implied right to withhold moneys, regardless of any express contractual provision to that effect, if they determined that there were unsatisfied claims for labor and material. Payment by the contractor of such claims being a condition in both construction contracts, the governmental agencies had the right to withhold funds, if there had been a breach of the condition, in order to protect the labor and material claimants under the construction contracts. The rule announced in Lancaster County Nat‘l Bank‘s Appeal, supra, is applicable and binding here.
III
Moreover, the time is appropriate to reconsider our earlier decisions in this area and to review the significance of the applicable statutes governing public work contracts as they affect the subrogation rights at issue. Contrary to the import of Sundheim and DuBois, the federal rule, see Pearlman v. Reliance Ins. Co., 371 U.S. 132, 83 S. Ct. 232 (1962), and the rule prevailing in most jurisdictions, see 43 Am. Jur. Public Works & Contracts §197 (1942), is that the surety, upon payment of claims of labor and materialmen, is entitled
The bond for the payment of labor and material claims on the building contract is required by the
Martin v. Nat‘l Surety Co., 300 U.S. 588, 57 S. Ct. 531 (1937), involved a situation similar to the one before us, but the case was decided on a much narrower basis. The Supreme Court held that labor and material claimants had an equitable lien on a fund as a result of an assignment in the contract between the primary contractor and the surety. However, Mr. Justice CARDOZO made the following observation: “[W]e have assumed that the failure to pay materialmen was a default of such a nature as to impose a duty on the contractor to turn over the payments to the surety upon appropriate demand. There is argument to the contrary. According to that argument the moneys were to be assigned in the event of default in the performance of the contract between the contractor and the Government, and not upon the failure to pay persons other than the Government who had claims against the
Recently in Pearlman v. Reliance Ins. Co., supra, the Supreme Court of the United States noted it was arriving at the same conclusion reached in Martin, but, in doing so, it did not limit itself to the narrow basis upon which that prior decision was rendered. In Pearlman the dispute was between the trustee in bankruptcy of a government contractor and the payment bond surety. Under the particular contract in question, the government withheld in excess of $87,000 which would have been due the contractor had he paid labor and material claimants. In sustaining the surety‘s right to this fund and in concluding that the fund was in no way an asset of the bankrupt estate, the Supreme Court held that: (1) the government had the right to use the retained fund to pay labor and material claims; (2) labor and material claimants had a right to be paid out of the fund; (3) the contractor would have been entitled to the fund had he paid labor and materialmen; and (4) the surety, having paid them, became subrogated to the fund.
The Supreme Court further observed that: “Traditionally sureties compelled to pay debts for their principal have been deemed entitled to reimbursement, even without a contractual promise such as the surety here had. And probably there are few doctrines better established than that a surety who pays the debt of an-
The Supreme Court also quoted from Memphis & Little Rock R.R. v. Dow, 120 U.S. 287, 301-02, 7 S. Ct. 482, 489 (1887): “The right of subrogation is not founded in contract. It is a creature of equity; is enforced solely for the purpose of accomplishing the ends of substantial justice; and is independent of any contractual relations between the parties.”
Even if we were able to accept appellant‘s view that the contracts here in question did not create an obligation in Northeastern to pay labor and materialmen, the surety companies should still prevail. The doctrine of subrogation is not founded upon contract, and, under these circumstances, is equally generated by the contractor‘s compliance with the statutory obligations to provide the bonds in question.
Labor and materialmen involved in public construction are a group specially protected by statute as well as by these particular contracts. Payment to them is secured by the bond of the contractor‘s surety. The funds available for the protection and payment of these claims are separate and apart from the relationship between the contractor and his general creditors. This is so irrespective of whether there exists a surety bond for payment. The execution of the surety bond for this special but well known purpose in no way involved or prejudiced the general creditors or the receiver.
The sum retained by the Commonwealth was an added mechanism for achieving performance, as well as providing a further resource for paying labor and materialmen, especially since that sum is less than the total amount due those claimants. Had the surety not paid the labor and materialmen, the funds held by the
IV
Appellant poses an additional problem in his effort to preclude the surety companies from retaining the proceeds in issue. Appellant urges that the sureties did not file financing statements, as he contends is required by the
Article 9 of the
It seems exceedingly clear that, in the present suretyship situation, filing is not needed to prevent deceiving or misleading the creditors about the state of the contractor‘s available assets. Furthermore, filing in this instance could in no conceivable way be beneficial to or protective of the general creditors. They are completely unaffected by the filing or absence of filing. Since the funds here at issue represent an asset never available to general creditors, there is no reason for requiring the filing of a financing statement by the sureties. As a legal and practical matter, no creditor could or did advance credit on the basis of the funds withheld by the Commonwealth for payment to labor and materialmen. Furthermore, creditors are bound to know of the substantive law requiring the filing of
Of basic importance is the general rule of
We are thus convinced that the Code does not preclude recovery in this case.
Judgment of the court below affirmed.
DISSENTING OPINION BY MR. JUSTICE JONES:
I agree with the views expressed in the majority opinion except in one important respect. In the case at bar, the sureties did not file financing statements as defined in the
Accordingly, I dissent and for this reason would reverse the judgment entered in the court below.
Mr. Justice COHEN joins in this opinion.
