100 Wash. 524 | Wash. | 1918
The plaintiffs, Jacobs and wife, seek recovery of compensation for damage to their real property, caused and to be caused by the defendant, city of Seattle, in the exercise of its power of eminent domain, the amount of which compensation had not been in any manner ascertained or determined prior to
This is the second appeal of this case to this court. The first appeal was taken by the plaintiffs from a judgment of the superior court dismissing the case upon sustaining the city’s demurrer to the plaintiffs’ complaint and their electing not to plead further. That appeal was disposed of by our decision reported in 93 Wash. 171, 160 Pac. 299, L. R. A. 1917B 329, reversing the judgment of the superior court and remanding the case to that court, holding that the first cause of action of the complaint alleged facts entitling them to recover, though their second cause of action did not. The allegations of respondents’ first cause of action are set out, in substance, in considerable detail in our former decision. We deem it sufficient here to state that it is therein alleged, in substance, that the city erected a garbage incinerator building and plant on a lot adjoining respondents’ lot, upon which they have three dwelling houses; that the city has commenced and continues to operate its plant, causing to he brought to it large quantities of refuse and garbage which it burns therein, and in doing so causes damage to respondents’ property, in that obnoxious vapors, steam, smoke, ashes and pieces of partly burned garbage are thrown over and upon respondents’ property, which it threatens to continue to do, materially and permanently impairing its desirability and usefulness and lessening its value; and that the city has never acquired the right to so maintain and operate its incinerator, and thereby so damage respondents’ property, by any condemnation proceeding looking to the ascertainment and payment of the damage so suffered
The principal contention here made in the city’s behalf, to which all other contentions worthy of serious consideration are incidental, is that respondents’ right of recovery is barred by the statutes of limitation. It appears from the evidence, and is conceded, that the city built its incinerator building and plant more than three years prior to the commencement of this action. The city also began to operate its plant to some extent more than three years prior to the commencement of this action. It, however, became a question in the trial of the case, according to respondents’ theory, which was adopted by the trial court, when the operation of the incinerator first became such as to result in actual damage to respondents’ property. This question was accordingly submitted by the court to the jury for a special finding thereon in addition to its general verdict, and in response thereto, a special verdict was returned by the jury with its general verdict, as follows:
“We, the jury find that the damage to the plaintiffs’ property by reason of the operation of the defendant’s incinerator commenced in May, 1912.”
This action was commenced in November, 1914, which, it will be noticed, was two and one-half years after the commencement of respondents’ damage as found by the jury. The evidence is conclusive that the mere building of the city’s incinerator building and plant did not, and would hot, result in any damage to
Let us be reminded as we proceed that this is not an action seeking recovery of damages as for a tort committed by the city, but is an action to recover compensation for damages resulting from the operation of the incinerator by the city, which it is doing, and avowedly intends to continue to do, in the exercise of its power of eminent domain, in so far as resulting damage to respondents’ property is concerned. Of course, if this were an action seeking recovery of damages for the commission of a tort, and treated as such by both respondents and the city, respondents’ right of action would not be barred as to damages accruing within the statutory period immediately prior to the commencement of the action. Counsel for the city carefully avoid making defense upon any such theory, but adopt the eminent domain theory upon which respondents prosecute their claim for compensation, manifestly to make sure that there shall be but one recovery, if any be had by respondents; and, also, to the end that the statute of limitation may be invoked against respondents’ claim as one.entire claim of compensation for the acquiring by the city of the right to so continue to operate its incinerator in the future to the damage, if any, of respondents’ property. In keep
Counsel for the city contend that the limitation applicable to respondents’ cause of action is that prescribed by Eem. Code, § 165, reading as follows:
“An action for relief not hereinbefore provided for shall be commenced within two years after the cause of action shall have accrued.”
While counsel for respondents contend that the three years prescribed for the commencement of the several kinds of action mentioned in Eem. Code, § 159, is applicable; relying upon subd. 3 of that section, reading as follows:
“An action upon a contract or liability, express' or implied, which is not in writing, and does not arise out of any written instrument. ’ ’
Does the obligation on the part of the city to pay the compensation here sought by respondents arise upon “a contract or liability . . . implied,” within subd. 3 of § 159 above quoted? We are of the opinion that it does, even though that subdivision relates only to contractual obligations, as seems to be held by our own and other decisions. Having in mind that the state has granted to the city the power of eminent domain, and that the city is manifestly maintaining and operating its incinerator, and intends to continue to do so, as an exercise of that sovereign power, in so far as thereby damaging respondents’ property is con
In United States v. Great Falls Mfg. Co., 112 U. S. 645, there was involved the taking of private property, land and water rights, by the government in connection with the construction of a water works dam in the Potomac river, without condemnation proceedings, and the seeking of compensation therefor by the owner in a suit against the government prosecuted in the court of claims. The jurisdiction of the court of claims depending upon the obligation of the government being one arising upon implied contract, it became necessary to determine the nature of the obligation in that re
“We are of opinion that the United States, having by its agents, proceeding under the authority of an act of Congress, taken the property of the claimant for public use, are under an obligation, imposed by the Constitution, to make compensation. The law will imply a promise to make the required compensation, where property, to which the government asserts no title, is taken, pursuant to an act of Congress, as private property to be applied for public uses. Such an implication being consistent with the constitutional duty of the government, as well as with common justice, the claimant’s cause of action is one that arises out of implied contract, within the meaning of the statute which confers jurisdiction upon the Court of Claims of actions founded ‘upon any contract, express or implied, with the government of the United States.’ ”
While that decision dealt with what seems to have been an actual taking of property rather than the mere damaging of it, we are reminded that our constitutional guaranty is that “compensation” shall be made when private property is “damaged,” as well as when it is “taken” for public use. Manifestly there can be no difference in the nature of the city’s obligation, whether it takes or damages private property for a public use, under our constitutional guaranty. We here note that the words “contracts, express or implied,” used in the statute defining the jurisdiction of the court of claims, are identical in meaning with-the words ‘ ‘ contract, . . . express or implied, ’ ’ used in our statute of limitation, subd. 3, Rem. Code, § 159, above quoted.
“The government may take real estate for a post office, a court house, a fortification or a highway; or in time of war it may take merchant vessels and make them-part of its naval force. But can this be done without an obligation to pay for the value of that which is so taken and appropriated? Whenever in the exercise of its governmental rights it takes property, the ownership of which it concedes to be in an individual, it impliedly promises to pay therefor. Such is the import of the cases cited as well as of many others.”
In the case before us, the question is presented in substance exactly as in the Great Falls Mfg. Co. and Lynah cases, above quoted from, in that title to the
This court, in Kincaid v. Seattle, 74 Wash. 617, 134. Pac. 504, 135 Pac. 820, expressed views quite in harmony with those of the supreme court of the United States upon this subject. Though not involving our statutes of limitation, the decision does deal with the nature of a claim of compensation for damages resulting from an act of the city done in the exercise of its power of eminent domain. The question was as to the necessity of the plaintiff filing his claim of compensation with the city as a prerequisite to his right to sue in the courts thereon. At page 621, Judge Chadwick, speaking for the court, said:
“Having the right to take, a municipality, whatever its procedure or even lack of procedure, is not a wrongdoer. The remedy of the one whose property is taken is immaterial so long as it leads to compensation as provided in the constitution. The city is bound to make compensation under a compact no less formal than the constitution itself, and it cannot defeat this constitutional right by a charter provision or an ordinance, nor can the legislature take it away by any arbitrary requirement, although we may admit that it could, as in all other cases, fix a time within which an action must be brought to recover damages that have not been first ascertained and paid. The city must be held to adopt the guarantee of the constitution and make it its promise, for we know of no law that will impute to the city, when exercising the sovereign power of the state, a wilful intention to disregard the right of a citizen. ’ ’
The logic of that decision is that the claim was not required to be filed with the city as a prerequisite to the right to sue in the courts thereon, because it did not rest upon tort, nor was it a claim for damage,
The word “damage” has been often loosely used as descriptive of the recovery an owner becomes entitled to because of the exercise of the power of eminent domain resulting in damaging instead of the taking of his property. It seems to us that the word has not been so used in its proper legal sense. We do not use the word “damage” to describe the recovery upon a promissory note or any other promise, express or implied. The word “damage,” when used as descriptive of the recovery to be awarded as the result of damage flowing from an act done in the exercise of the power of eminent domain, plainly means only compensation impliedly promised to be paid for such damage. Section 16 of art. 1 of our constitution uses the word “compensation,” not “damage,” as descriptive of the recovery the owner of damaged property is entitled to. This suggests that the word “compensation” was used therein advisedly in recognition of the fact that such recovery is not upon the theory of tort obligation, whether it be awarded in a condemnation proceeding or in an action seeking recovery of compensation after the damaging of property for public use. We make these observations not in a spirit of criticism, yet we apprehend that this indiscriminate use of the word ‘ ‘ damage ’ ’ has led both the bar and the courts to forget sometimes the real nature of a claim such as is here involved.
We now proceed to notice the decisions of this court relied upon by counsel for the city to support their contention that the two-year statute of limitation, § 165 above quoted, is controlling in this case. It may be conceded that some of these decisions, read apart from the
In Sargent v. Tacoma, 10 Wash. 212, 38 Pac. 1048, there was involved a cause of action accruing more than three years prior to the suing thereon. It was an attempt' to recover for injury to property resulting from a change of street grade. The trial court held the action to be barred, apparently upon the theory that it was for trespass and was, therefore, barred by subd. 1, § 115, Hill’s Code (now subd. 1, § 159, Rem. Code), prescribing three years as the limitation for the commencement of actions for waste or trespass upon real property. Affirming the trial court upon appeal, this court said:
“If actions of this kind are regarded as trespasses upon real property, the three years’ limitation created by Code Proc. § 115, covered this case; but if they are not, then Code Proc. § 120, limiting actions for relief not otherwise provided for to two years, did cover it.”
No mention of, and apparently no consideration whatever was given to, subd. 3 of the same section, here relied upon by respondents. Nor was any consideration given to the claim other than as a trespass or pure damage claim arising in tort. We do not regard that decision as a controlling holding that subd. 3 did not apply to the facts of that case.
In Suter v. Wenatchee Water Power Co., 35 Wash. 1, 76 Pac. 298, 102 Am. St. 881, we have a case of damage to the plaintiff’s property by the overflow of water from the company’s ditch. While the company, we as
In Denney v. Everett, 46 Wash. 342, 89 Pac. 934, 123 Am. St. 934, it seems to have been squarely held that compensation for damage resulting to private property from the city’s change of a street grade must be sought in an action commenced within two years following the change; this, upon the theory that the two-year general statute, Bal. Code, § 4805, now Bern. Code, § 165, applies to such an action. There is but brief discussion of the law in that decision, the court being content to rest it upon the decision in Suter v. Wenatchee Water Potoer Co., and noticing only as to whether the three-year trespass statute or the two-year general statute applies. We think that decision does not furnish an answer to this case.
Our attention is also called to Welch v. Seattle & Montana R. Co., 56 Wash. 97, 105 Pac. 166, 26 L. R. A. (N. S.) 1047. A critical reading of that case will disclose that it was prosecuted and defended upon the theory of recovering damages for trespass and tort. The only question presented or discussed was whether the three-year trespass statute or the two-year general statute applied.
We now notice three decisions of other courts relied upon by counsel for the city. In Chicago & E. I. R. Co.
“Actions to recover damages for an injury done to property, real or personal, . . . and all civil actions not otherwise provided for, shall be commenced within five years next after the cause of action accrued. ’ ’
We find the whole of that section in Hurd’s Revised Statutes of Illinois of 1874, reading as follows:
“Actions on unwritten contracts, expressed or implied, or on awards of arbitration, or to recover damages for an injury done to property, real or personal, or to recover the possession of personal property or damages for the detention or conversion thereof, and all civil actions not otherwise- provided for, shall be commenced within five years next after the cause of action accrued.” (p. 675.)
We italicize the words to be noticed particularly. The notes thereunder indicate that the section had been the law since 1849. The damage in question appears to have commenced in 1872, while this section was in force; so, even if counsel and the court had treated the action as one to recover on an implied contract, the holding would have been the same. We think this decision is not out of harmony with our conclusion here reached.
In Luckey v. City of Brookfield, 167 Mo. App. 167, 151 S. W. 201, recovery was sought for damages resulting from the construction and commencement of
In Atchison, T. & S. F. R. Co. v. Lauterback, 8 Kan. App. 15, 54 Pac. 11, recovery was sought for damages resulting from the construction of the company’s railroad six years prior to the commencement of the action. The right of action was held barred under § 12, ch. 95, General Statutes of that state of 1897. No part of the statute is quoted, nor is its substance stated in the opinion; but turning to that section in the compilation of the statutes referred to, we find that “an action upon a contract not in writing, express or implied,”
It is contended in the city’s behalf that the trial court erred in its rulings upon the admission of evidence and in its instructions to the jury, in that it did not rule that respondents’ right to compensation for damages, if any they had, accrued, and the statute of limitation began to run against such right, at the time of the construction of the incinerator, which, as we have noticed, was more than three years prior to the commencement of this action. We think it is clear that the trial court could not have so ruled as a matter of law; first, because the court could not determine, as a matter of judicial knowledge, that the mere construction of the incinerator building and plant would cause damage to respondents’ property, nor could it judicially know that the then prospective operation of the incinerator would damage respondents’ property; and second, because the evidence all but conclusively shows that respondents’ property was not damaged by the construction of the incinerator nor by the operation thereof until May, 1912, two and one-half years prior to the commencement of this action, as found by the jury. It is argued that our decision upon the former appeal in effect holds that the damage must, as a matter of law, be deemed to have commenced, if at all, upon the construction of the incinerator. We do not so read it. That decision may mean that it might be
Some contention is made against the allowance of costs and disbursements to respondents incurred by them upon the first trial. It seems that, at the time the court sustained the city’s demurrer to respondents’ complaint and dismissed the case, it had proceeded to the stage that a jury had been empaneled and
The judgment is affirmed.