235 P. 277 | Or. | 1925
This is an action to recover for the breach of a contract of hiring. The material allegations are pleaded as follows:
"`That Joseph Jacobberger be employed as architect to design and superintend the construction of *576 the new Rose City Park school building, eight rooms of which are to be erected this year, and that he be paid a total of 5 per cent commission for this work on the following terms:
"`Two per cent on the estimated cost of the entire building when plans for entire building are accepted.
"`Three per cent as the units of the building are built.'
"Wherefore, plaintiff demands judgment against defendant in the sum of $2,382 and for his costs and disbursements herein."
A general demurrer was interposed, which was overruled by the court, and defendant filed an answer, admitting the contract as set up in the complaint, and alleging that during the term of the directors *578 who then constituted the board of directors of said school district plaintiff prepared sundry plans and specifications for said Rose City Park school building, and supervised the construction of two units of said school building; that the services of the plaintiff to said board of directors were fully paid and discharged in accordance with the terms of said resolution; that said board of directors, as then constituted, did not then contemplate nor provide for the construction of other or additional units to said building, nor did the school population of the community wherein said school is located warrant or demand the construction of any additional units to said school; that the terms of office of the members who constituted the board of directors who adopted said resolution have long since expired, and said board of directors has been succeeded by other boards during the interval of eleven years since the adoption of said resolution, and that the present board of directors does not contain any of the members of the board of directors who passed said resolution; that during the month of May, 1921, the present board of directors decided to complete the remaining unit, namely, the north wing of said Rose City Park school building, and thereafter proceeded to let contracts and to construct said north wing; that said north wing now has practically been completed and the total cost thereof is not the sum of $79,400, nor any other or greater sum than $64,418.92; that said resolution passed by said former board of directors, as aforesaid, and the employment of the plaintiff thereunder, in so far as it related to the construction of said north wing of said Rose City Park school, or was intended to relate to said north wing, was wholly unreasonable and was legally fraudulent and *579 void, in view of the existing circumstances, namely: that said former board of directors did not contemplate the erection of any further units during the continuance of its term in office, did not provide funds for the construction of any further units, nor for the payment of the fees of plaintiff, nor was the school population of the community wherein said school is located sufficiently large to require the erection of any further units to said school building, nor had the school population of said community increased so as to make said additional unit necessary or desirable during the period of ten years subsequent to the passage of said resolution; that the situation and circumstances of said district at the time of the adoption of said resolution by the former board of directors did not carry any element of necessity for the appointment of plaintiff to supervise the erection of the north wing of said school when such north wing should become necessary, and said board was without power to tie the hands of the people of said district and subsequent boards in so important a matter as the appointment of an architect to supervise said north wing when it should become necessary to construct the same; that the present board of directors, at the time it entered upon the construction of said north wing, refused to recognize or be bound by the terms of said resolution so adopted, as aforesaid, and refused to accept the services of plaintiff and notified said plaintiff accordingly.
The case was tried by a jury, which returned a verdict for the plaintiff in the sum of $2,040, and from a judgment on such verdict the defendant appeals.
REVERSED AND REMANDED WITH DIRECTIONS. REHEARING DENIED. *580
The demurrer in this case should have been sustained. There is no allegation in the complaint that the plaintiff's claim herein was ever presented to the school board for audit, and such presentation has been distinctly held to be necessary: Barrow
v. School Dist. No. 8,
It is urged that this is cured by evidence introduced by the plaintiff tending to show that such presentation had been made, and it is urged that, this evidence having been introduced, the alleged omission is cured by the verdict. The introduction of such testimony was strenuously objected to by the defendant, and the lack of a necessary allegation in the complaint cannot be cured by a verdict based upon evidence improperly admitted.
The judgment will be reversed and the cause remanded to the court below, with instructions to sustain the demurrer.
REVERSED AND REMANDED WITH DIRECTIONS. REHEARING DENIED.
BURNETT, RAND and COSHOW, JJ., concur. *581