90 So. 647 | La. | 1922
“The wharfhouse to be divided into four (4) groups, each group to be driven simultaneously.
“Group 1 to consist of all piles bounded by Piers 20-216-34-202.
“Group 2 to be bounded by Piers 35-61-201-175.
“Group 3 to be bounded by Piers 62-88-174-148.
“Group 4 to be bounded by Piers 89-102-147-134.
“Not less than forty (40) piles to be driven in each group per day.
“If warehouse E and the balance of the wharfhouse are to be built the piling for same is to be furnished at the same rate and under the same contract conditions.”
The subcontractor, Carey & Boettner, and the defendant United States Fidelity & Guaranty Company, agreed and bound themselves in solido at their own proper cost to furnish all materials, apparatus, falsework, machinery, tools, and labor necessary and requisite for and to perform, construct, complete, and deliver in a substantial and workmanlike manner, to. the entire satisfaction of Ford, Bacon & Davis, engineers, all of the work embraced in the plans and specifications of the Port Commission for the construction of wharfhouse warehouse E, attached runways, and other appurtenances in strict accordance with the specifications of date June 5, 1915, and with the plans accompanying said specifications, Which were signed by said contracting parties as -a part of said subcontract.
The subcontractor agreed to begin active work within 5 days after the signing of the contract and to fully complete same before October 10, 1915. See XII Contract.
It is provided in said contract that, if it should appear -by the report of the engineers that the rate of progress of the work is not such as to insure satisfactory completion of same within the time designated in said contract, or within any additional time which may have been granted as in said contract provided; or in case the works, for want of sufficient or proper workmen or material, are not progressing with what the engineers shall consider to be due dispatch, that the contractor shall notify the subcontractor in writing wherein they believe the specifications are being violated, and, at the same time, demand immediate compliance with same, and should" the subcontractor fail, upon receipt of notifi
The subcontractor under said contract agreed to furnish a bond with a surety company satisfactory to the contractor, as surety for the amount of $6,000, so as to guarantee to the contractor the proper performance by the subcontractor of all and singular the obligations assumed by said contractor under said contract, which bond was furnished by the defendant United States Fidelity & Guaranty Company.
The plaintiff, Jacob A. Zimmerman & Son, Inc., bound itself to fully complete the construction of the wharfhouse and warehouse E and runways before April 1, 1916, and to have all tools, equipment, surplus, and waste materials removed from the site before April 1, 1916, and in default thereof to pay the Port Commission the sum of $300 for each and every day thereafter until the work is so completed and tools and materials removed.
Alleging the failure of the subcontractor, Carey & Boettner, to prosecute the work of driving these piles in a substantial and workmanlike manner, or to the satisfaction of the engineers, and their failure to divide the work into four groups as provided in the contract, and to operate a pile driver on each group, driving not less that 40 piles in each group per day, petitioner avers that toward the beginning of September, 1915, it was beginning to become apparent that Carey & Boettner would not be able to complete their contract within the time and in the manner therein provided, and that, after repeated complaints by the engineers to petitioner, and by petitioner to the subcontractor and the surety company, without avail, and after putting both defendants in default, it was compelled to relet one-half of the work to Doul-lut & Williams at' 7% cents per foot and itself to undertake to do the rest of the work, and that petitioner completed its half of the work with all possible dispatch and at a minimum cost of $12,778.50, and that petitioner was compelled to pay to Doullut & Williams the sum of $16,933.20.
Petitioner avers that,' after allowing said subcontractor, Carey & Boettner, all credits due them, they owe a balance to petitioner of $16,305.10, and that to the extent of $6.-000 defendant surety company is liable to petitioner in solido with the said Carey & Boettner upon its bond, and prays for judgment accordingly.
The driving of these piles was preliminary work, which had to be finished before the construction of the wharfhouse could be commenced, and any delay in driving same necessarily delayed the completion of the wharf-house, and would entail a heavy penalty of $300 per day as liquidated damages upon plaintiff, as provided in the contract.
Before the plaintiff took charge of one half of this work, and sublet the other half to Doullut & Williams, the plaintiff during the month of September, 1915, made frequent complaints, verbally and in writing, to the subcontractor and to the surety company, that the work of driving these piles was not progressing in accordance with the terms of the contract, and on September 20, 1915, Messrs. Carey & Boettner having failed to comply with the demand made upon them, plaintiff through its attorneys addressed to the bonding company a letter reading as follows :
“September 20th, 1915.
“United States Fidelity & Guaranty Company, Whitney Central Building, New Orleans, La. — Gentlemen: We inclose herewith copies of our letters of September 16, directed to Messrs. Carey & Boettner and to yourselves. In connection therewith we now beg to advise you that Messrs. Carey & Boettner have failed to make , any efforts to comply with the specifications embraced in the contract. In consequence, by virtue of section 15 of the contract to which you have subscribed, by reason of the bond which you have written, we beg to eall upon you to do the work for the rest. We regret to state that, in default of a strict compliance on your part, within forty-eight hours, Messrs. Zimmerman & Son will find it necessary, either to annul their contract with Messrs. Carey & Boettner, with an attendant forfeiture on their part of any payments of moneys which may be due to the latter, or owing to them on the work already executed, or in the alternative to employ additional force or to relet the said work without advertisement, and to have the said-work completed for the account of, and at the expense of the subcontractor and his bondsman.”
The defendant surety company failed within the time limit provided for in the contract to effect a compliance with the provisions of the contract by tbe subcontractor, and plaintiff, through its attorneys, addressed to said company, under date of September 28, 1915, tbe following letter:
“September 28, 1915.
“The U. S. Fidelity & Guaranty Co., Whitney Bank Bldg., City — Gentlemen: Zimmerman, Inc., v. Carey & Boettner. Referring to our earlier written apd verbal notice in this matter, we beg to advise that Jacob A. Zimmerman, Inc., have been compelled to relet one-half of the work to be done by Carey & Boettner to Doullut & Williams at 7% cents per foot and to undertake themselves to do the rest of the work. This was the most advantageous arrangement they were able to make, after due notice to you as you are aware, and they will in due course, upon completion of the work, make claim against you for the amount of the loss and extra cost of the work.”
In pursuing this course, plaintiff was acting clearly within the provisions of section 15 of the contract, which is the law governing this case.
The contract required the work of driving these piles to be completed on October 10, 1915. Tbe subcontractor was notified to begin work on August 11, 1915. On September 27, 1915, the date on which plaintiff took over the work, or more than 30 days after the beginning of tbe work, when it should have been more than half finished, Carey & Boett-ner had actually driven 44,480 out of the total aggregate of 400,000 feet which had to be driven, or, in other words, had completed only about 10 per cent, of the work.
It is not, therefore, surprising that the engineers complained very often to plaintiff, the contractor, of the lack of progress on this
This disposes of the contention of defendants that the plaintiff had no right to take over the work and arrange to complete it, no matter how clearly Carey & Boettner were in default, unless Ford, Bacon & Davis, the engineers, made complaint; especially as article 15 of the contract provides that, “if the subcontractor shall persist in any course violative of the provisions of the contract,” the contractor may proceed at once to put him in default, and, after due notice to the suretjr, take over the contract.
Under these circumstances, neither the subcontractor nor his surety have any just ground to complain that there was any delay caused by failure to remove these obstructions.
The defendant bonding company signed the contract, which contains in.article XIY the following provisions:
“Neither the subcontractor nor Ms sureties shall be released from, the whole or any part of the obligation hereby assumed by reason of any change in the amount, nature, scope, character or extent of the work, or in any plan of specification, or in the mode or time of payment, or by the consent to any subcontract, or by any extension of time or indulgence granted to the subcontractor, even though any or- all of said acts be without the knowledge and consent of the subcontractor or his sureties, unless such release be expressly made in writing by said contractor.”
This provision is a complete answer to respondent’s' contention. The drivers were placed on barges both by plaintiff and by Doullut & Williams in completing the contract, after it was taken out of the hands of the subcontractor.
The record shows that this was the proper method of driving the piles In order to expedite the work, and that “followers” were essential, while driving piles in the water.
The record fails to disclose that the cost of completing the work was excessive, but, on the contrary, shows that the work was finished to the best advantage possible under the circumstances.
No contention was made by either Carey & Boettner or by the bonding company that they had been delayed in any of the ways set up in the answer, when the work was finally taken out of the hands of Carey & Boettner by plaintiff, after repeated notices to Carey & Boettner and the bonding compa
The judgment appealed from is therefore affirmed.