194 Ind. 130 | Ind. | 1924
This was an action on the bond of a firm of contractors to recover damages because of their failure to complete a free gravel road in Huntington county that was ordered constructed under the “three mile act”, as then in force (§7719 Bums 1908, Acts 1907 p. 68, §1). The greater part of the length to be improved was north of the Salamonie River, and was comparatively level, while the short distance south of the river was laid out to pass through a hill in a deep cut, that would require five times as much excavation as the longer distance at the north end. All of the highway, after being properly graded, was to be metaled with gravel to a depth as stated. That part north of the river was completed according to contract, and the contractors had received more than half of the agreed price, when they quit work, in July, 1913, -stating that they could not finish until a proposed bridge across the Salamonie River should be completed.
Of the six defendants, the record does not disclose that any but the two contractors, who were the principals in the bond, filed answers to the complaint. What purports by its recitals to be an answer of denial by “the defendants and each of them” is set out on page forty-two of the transcript, but the order-book entry which precedes it and under which it purports tó be incorporated in the transcript states only that “the defendants Jackson and Gordon now file a reply of general denial to the answer in two paragraphs to cross-complaint of said defendants Jackson and Gordon herein in these words”: This entry follows other entries showing that an answer and cross-complaint had been filed by Jackson and Gordon, and that a reply to the answer and an answer to the cross-complaint had been filed by the plaintiff. Recitals in a pleading filed by two defendants as a reply to the-answer to their cross-complaint, after the issue on their answer to the complaint had been closed by a reply thereto, could not give effect to such pleading as an answer to the complaint on behalf of all six of the defendants. Appellants seem to rely on a docket entry, copied on page twenty-six of the transcript, stating that “the defendants Amos L. Jackson and James O. Gordon now file second paragraph of answer herein in these words. Not on file in this office, Kent Sweet, Clerk”, and on the fact that the pleading set out sixteen pages later, under the record entry stating that Jackson and Gordon filed a reply, as stated above, purports also to
The only pleadings presented for our consideration are the three paragraphs of the complaint, the third paragraph of affirmative answer by the contractors, who are the principals in the bond sued on, the reply thereto of denial and estoppel, and the cross-complaint, answer and reply.
On proper request by the defendants (appellants), the trial court made a special finding of facts, on which it stated conclusions of law to.the effect: (1) that the law was with the relator; and (2) that the relator was entitled to recover damages in the sum of $7,401, as being the difference between the price at which the work-of completing the road had been relet, and $5,099, the. balance remaining unpaid of the original contract price; and each defendant excepted separately to each of the conclusions of law. Appellants have waived all assignments of error except the assignment that the trial court erred in each of its conclusions of law, to which, alone, the points and authorities and arguments in their brief are addressed.
But appellants insist that the measure of damages was the reasonable cost of completing the work, and not necessarily the actual cost of doing so. However, if the board of commissioners, after the contractors had abandoned the work and refused to complete it, relet the work to the lowest bidder after due advertisement, and entered into a contract with him at a price fixed by such bid, and took a bond from him to secure the performance of his contract, in conformity with the provisions of the statute in such cases, an inference that the price at which it was so let was the reasonable cost would necessarily follow, in the absence of any showing that the advertisement and letting of the new contract was not fairly and honestly done. Being limited by statute to the single method of advertising and reletting the contract, the result of such reletting is necessarily conclusive as to the reasonable cost of getting the work completed by that method, unless impeached for fraud or illegality. Donaldson v.
Neither was it necessary to show that the work actually had been completed, and the price at which it was relet actually paid, in order to make out a cause of action for the recovery of the damages claimed. Donaldson v. State, ex rel., supra.
The facts found show clearly that appellants bound themselves to complete the work for $11,999; that they received all of that price but $5,099; that the lowest bid for completing it was $12,500; and that a contract to complete it was let at that price, in full compliance with the statute. These facts, with the conclusion which follows, clearly established relator’s right to recover the sum of $7,401, for which the judgment was rendered in its favor. Where it is obvious on the face of the record that the parties were given a full opportunity to present the case and that a right result was reached, the judgment will not be reversed because of technical irregularities of procedure.
The judgment is affirmed.