This case is before the Court for review of the decision of the First District Court of Appeal in Shakespeare Foundation, Inc. v. Jackson,
FACTS
In 2006, George Jackson, Kerry Jackson, and the Jackson Realty Team, Inc. (“the Jacksons”) decided to sell the real property that is the subject of the contract which forms the basis of this dispute. They posted the following advertisement in the Bay County Multiple Listing Service:
This is a Great affordable housing project. Estimate from North Bay Engineering is $17,500 to get you to Dev order stage. Topography and boundary survey completed recently by Dragon Surveying to be included in price.*590 Property is 165' on Everitt Avenue and 396' deep, totally cleared and filled except for 10' around fence line. Zoning per City of PC is MU2, Mixed Use 2, Multi Family duplex, triplex or quadra-plex be built on the property. Recently tapped into Panama City Water and Sewer, with new commercial grade pump/lift station on site. Local Engineering company has platted 10 duplexes could fit 6 4 plexes. Zoned 20 units per acre or 30 units total. Wetlands study verifies No Wetlands. One of Sellers is Licensed Fl. Realtor.
(Emphasis added.) When the Jacksons posted this advertisement, they had in their possession a Property Report Land Use Planning Analysis, which established, contrary to the advertisement, that 25% of the subject property constituted wetlands.
The Jacksons and the Respondents — the Shakespeare Foundation, Inc., and the Herd Community Development Corp. (collectively the “Shakespeare Foundation” or the “Foundation”) — entered into negotiations for the purchase of the real property. During the negotiations, the Shakespeare Foundation advised the Jacksons that they intended to develop the property into a twenty-seven unit low-income housing development. The Shakespeare Foundation relied on the representations set forth in the advertisement and entered into a contract with the Jacksons for the purchase of the real property.
In July 2007, after the Shakespeare Foundation tendered full payment to the Jacksons for the property, the Foundation held an onsite meeting with a builder and engineer. The builder reported that the property might contain wetlands. The Shakespeare Foundation hired an engineering firm to perform a wetlands delineation
The Shakespeare Foundation thereafter filed an action against the Jacksons for fraudulent misrepresentation. In the complaint, it was alleged that in the advertisement for the sale of the property, the Jacksons knowingly and falsely misrepresented that the property had no wetlands and that the property was suitable for the construction of thirty units, and the Shakespeare Foundation relied on these misrepresentations when entering into the contract. The Shakespeare Foundation contended that if it had been known that 26% of the property constituted wetlands, the property would have never been purchased because that percentage of wetlands made use of the property “economically unfeasible.” The Shakespeare Foundation also asserted that the existence of the wetlands led to a delay in project development. It was alleged that this delay of time caused the Foundation to miss a favorable real estate market in which the subject property could have been sold, and placed them in one of the worst real estate markets in the modern era.
The Jacksons moved to dismiss the Shakespeare Foundation’s action. They asserted that the fraud claim arose out of, and was related to, the contract and, therefore, fell within the arbitration provi
14. DISPUTE RESOLUTION: This Contract will be construed under Florida law. All controversies, claims, and other matters in question arising out of or relating to this transaction or this Contract or its breach will be settled as follows:
(a) Disputes concerning entitlement to deposits made and agreed to be made: Buyer and Seller will have 30 days from the date conflicting demands are made to attempt to resolve the dispute through mediation. If that fails, Escrow Agent will submit the dispute, if so required by Florida law, to Escrow Agent’s choice of arbitration, a Florida court or the Florida Real Estate Commission. Buyer and Seller will be bound by any resulting award, judgment, or order.
(b) All other disputes: Buyer and Seller will have 30 days from the date a dispute arises between them to attempt to resolve the matter through mediation, failing which the parties will resolve the dispute through neutral binding arbitration in the county where the Property is located. The arbitrator may not alter the Contract terms or award any remedy not provided for in this Contract. ... This clause will survive closing.
(Emphasis added.) The Jacksons contended that the contractual provisions required the Shakespeare Foundation to submit the fraud claim to binding arbitration. It was asserted that this provision required binding arbitration of the fraud claim because the scope of the contractual provision included all claims “arising out of or relating to this transaction or this Contract.” (Emphasis added.)
The trial court subsequently granted the Jacksons’ motion to dismiss, concluding that the arbitration provision in the contract required that the parties submit the fraud claim to arbitration. The Shakespeare Foundation appealed the judgment of dismissal to the First District Court of Appeal. See Shakespeare Found.,
Decision of the First District
On appeal, the First District examined whether the trial court erred in dismissing the action. See id. at 1197-98. The crux of the appellate court’s review was whether the fraud claim of the Shakespeare Foundation was within the scope of the arbitration provision of the contract. See id. at 1198.
The district court below concluded that the arbitration provision of the subject contract was broad in scope because its terms were to apply to all claims or controversies “arising out of or relating to” the contract. See id. (concluding that the “or relating to” language rendered the arbitration provision broad in scope). The district court then held that a claim falls within a broad arbitration provision if a “significant relationship” — i.e., a “contractual nexus” — exists between the contract and the claim. See id.
The district court, however, determined that the fraud claim here did not come within the broad scope of the arbitration provision because the fraud claim arose from a general duty established under the common law; not from an obligation arising under the contract. See id. at 1199. More specifically, the district court concluded that the fraud claim did not significantly relate to the contract because determination of this claim required neither reference to nor construction of the contract. See id. Rather, the district court held that the claim rested on the alleged false statements in the published adver
The First District ultimately held that the action based on fraud was not a dispute subject to arbitration under the contract, reversed the trial court’s order, and certified conflict with the decision of the Fifth District in Maguire. See id. at 1201.
Conflict Case
In Maguire, a buyer entered into a contract to purchase real property from the sellers. See
On appeal, the Fifth District reversed and remanded, directing the trial court to compel arbitration of the fraud and misrepresentation claims. See id. at 268. The appellate court held that a contractual nexus existed between the misrepresentation claims and the contract because the contract contained a broad arbitration provision, and the buyer based the misrepresentation claims on duties created by the contractual relationship between the parties. See id. at 266 (“[T]he tort claims are nonsensical when divorced from the contractual obligation to deliver approximately two acres of drainage rights.”). According to the appellate court, the fraudulent misrepresentation and fraud in the inducement claims arose from conduct pertaining to the agreement — i.e., the misrepresentation regarding the drainage rights which had been specifically incorporated into the written contract. See id. at 267.
ANALYSIS
Standard of Review
This Court reviews de novo a trial court’s ruling on a motion to dismiss. See Execu-Tech Bus. Sys., Inc. v. New Oji Paper Co. Ltd.,
Applicable Rules of Law
Generally, the three fundamental elements that must be considered when determining whether a dispute is required to proceed to arbitration are: (1) whether a valid written agreement to arbitrate exists; (2) whether an arbitrable issue exists; and (3) whether the right to arbitration was waived. See Seifert v. U.S. Home Corp.,
Two basic types of arbitration provisions have emerged: (1) provisions with language and application narrow in scope, and (2) provisions with language and application broad in scope. See Seifert,
A “significant relationship” between a claim and an arbitration provision does not necessarily exist merely because the parties in the dispute have a contractual relationship. See id. Rather, a significant relationship is described to exist between an arbitration provision and a claim if there is a “contractual nexus” between the claim and the contract. See id. at 638. A contractual nexus exists between a claim and a contract if the claim presents circumstances in which the resolution of the disputed issue requires either reference to, or construction of, a portion of the contract. See id. More specifically, a claim has a nexus to a contract and arises from the terms of the contract if it emanates from an inimitable duty created by the parties’ unique contractual relationship. See id. at 639. In contrast, a claim does not have a nexus to a contract if it pertains to the breach of a duty otherwise imposed by law or in recognition of public policy, such as a duty under the general common law owed not only to the contracting parties but also to third parties and the public. See id.
For example, in Seifert, this Court examined whether a negligence claim in a
The wrongful death action in that case arose after a wife and husband purchased a home. See id. at 635. After the couple moved into the home, the husband died inside the home due to the inhalation of carbon monoxide. See id. at 635. This death occurred because an air conditioner located in the garage area captured carbon monoxide emissions from a running car engine in the garage and transmitted the toxic emissions into the living area of the home. See id. The wife, as personal representative of her husband’s estate, filed a wrongful death action against the sellers of the home for strict liability, negligence, and breach of express and implied warranties. See id. The sellers moved to compel arbitration with regard to the negligence-type claims, arguing that although the claims were founded in tort law, all of the claims were within the scope of the arbitration provision in the purchase contract:
13. ARBITRATION. Any controversy or claim arising under or related to this Agreement or to the Property (with the exception of “consumer products” as defined by the Magnuson-Moss Warranty-Federal Trade Commission Improvement Act, 15 U.S.C. Section 2301 et seq., and the regulations promulgated under the Act) or with respect to any claim arising by virtue of any representations alleged to have been made by the Seller or Seller’s representative, shall be settled and finally determined by mediation or binding arbitration as provided by the Federal Arbitration Act (9 U.S.C. Section 1 — 14) and similar state statutes and not by a court of law.
Id. (emphasis added).
This Court disagreed with the sellers. See id. at 640-42. We held that the negligence-type claims did not have a significant relationship to the contract because they were founded in the tort of common law negligence and were unrelated to any unique legal duties imposed under the contract, i.e., the actions were predicated on the sellers’ breach of general common law duties of care owed to the injured parties; not on a breach of a unique duty imposed under the contract. See id. The holding was supported by reference to the total absence of any mention of rights regarding personal injury or negligence actions in the contract. See id. We concluded that the absence of such language further signified that the parties did not intend for the arbitration provision to apply to the negligence-type claims. See id. at 641-42.
Instant Case
We hold that the action here based on fraud is within the scope of the arbitration provision because it has a clear contractual nexus with, and thus a significant relationship to, the contract. This relationship exists because: (1) the fraud claim is inextricably intertwined with both the circumstances that surrounded the transaction from which the contract emanated and the contract itself; and (2) resolution of the fraud claim requires the construction and consideration of duties arising under the contract.
In this case, as in Seifert, the contract at issue has a broad arbitration provision because it subjects “[a]ll controversies, claims, and other matters in question arising out of or relating to this transaction or this Contract or its breach” to binding arbitration. (Emphasis added.) See Seifert,
In contrast to Seifert, here, although the fraud claim is based on common law fraud,
Therefore, unlike the negligence-type claims in Seifert, the fraud claim at issue here is inextricably intertwined with both the transaction from which the contract arose and the contract itself — the reliance element of the claim emanates from the transaction from which the contract arose, and the damages element of the claim arises from the execution and existence of the contract itself. Accordingly, the fraud claim has a significant relationship to the contract and is within the scope of the contract’s broad arbitration provision.
Furthermore, the resolution of the fraud claim requires reference to and construction of both the contract’s arbitration provision and its “as is” provision.
This limitation of remedies in the arbitration provision may have an impact on the contract and the arbitration provision. See Hialeah Auto., LLC v. Basulto,
The adjudication of the fraud action may also require reference to and the construction of the “as is” provision of the contract. More specifically, the resolution of the fraud claim may require a determination as to whether that claim is negated due to an election of the “Feasibility Study” option under the “as is” provision of the contract. By electing this option, the Shakespeare Foundation may have accepted the property “as is” for the intended use and waived any claims. See Gilman v. Butzloff,
The decision in Maguire is also consistent with our holding. There, the parties entered into a contract for the sale of real property that contained an arbitration provision identical to the provision we consider in this case. There, as here, the aggrieved party filed an action for fraud. In relying on Seifert, the Fifth District in Maguire held that a contractual nexus existed between the fraud claims and the contract because the contract contained a broad arbitration provision, and the buyer based the fraud claims on misrepresentations regarding the property that was the subject of the contract, which were relied upon by the buyer in executing the contract. See Maguire,
Lastly, decisions from the United States Supreme Court and other state courts support the conclusion that the fraud claim here is within the scope of the broad language of the arbitration provision at issue. See Prima Paint Corp. v. Flood & Conklin Mfg. Co.,
CONCLUSION
Accordingly, we conclude that the fraud action here filed by the Shakespeare Foundation has a contractual nexus with, and a significant relationship to, the contract between the Shakespeare Foundation and the Jacksons and is, as a general principle, within the scope of the contract’s broad arbitration provision. We do not determine nor do we address any other issue beyond this threshold determination. We, therefore, quash the decision below, remand for further consideration, and approve the decision in Maguire to the extent that it is consistent with this opinion.
It is so ordered.
Notes
. A "wetlands delineation” is "the act of establishing the boundary between wetlands and uplands (or non-wetlands).” The Wetlands Regulation Center, Wetlands Delineation Under the Clean Water Act, http://www. wetlands.com/regs/tlpge02h.htm (last visited January 15, 2013).
. An aggrieved party proves common law fraud by establishing that: (1) the opposing party made a misrepresentation of a material fact, (2) the opposing party knew or should have known the falsity of the statement, (3) the opposing party intended to induce the aggrieved party to rely on the false statement and act on it, and (4) the aggrieved party relied on that statement to his or her detriment. See, e.g., Butler v. Yusem,
. In the contract, the Shakespeare Foundation elected the following provision:
(1) Feasibility Study: Buyer will, at Buyer's expense and within 30 days from Effective Date ("Feasibility Study Period”) determine whether the Property is suitable, in Buyer’s sole and absolute discretion, for use. Buyer will deliver written notice to Seller prior to the expiration of the Feasibility Study Period of Buyer’s determination of whether or not the Property is acceptable. Buyer’s failure to comply with this notice requirement will constitute acceptance of the Property as suitable for Buyer’s intended use in its "as is " condition.
(Emphasis added.)