delivered the opinion of the- court.
The declaration sets up that in July, 1897, the city of 'Jackson, on a contract with an association of persons, required a deposit of $1,500, to be forfeited to the city in case of failure to build and put in operation an electric light plant and street railroad ; that the forfeiture became complete by а failure; that in August, 1898, the city contracted with appellant, granting it franchises in consideration that it would construсt the plants; that in'August, 1899, the city passed a resolution accepting the work of the appellant as а compliance with the contract, which resolution ordered the $1,500, in its possession as forfeit from the former contract to be paid over to appellant, which was done, and the action is to reсover this money from the city. In this attitude the case was here before on demurrer to the declaration, and we held (
It should be noted and borne in mind that there appears nothing in the ordinances or resolutions of the board, or in the written contract between it and Carnes & Corson, all made a part of the plea, by which Carnes & Corson are under any sort of obligation to make any deposit whatevеr. This cannot be supplied by the averments of a plea at law of contemporaneous or рrevious parol understandings or agreements. Those who deal with a municipality in matters of the nature shown
Affirmed.