In consolidated actions, inter alia, to recover damages for breach of certain construction contracts, the County of Westchester (hereinafter the County) appeals from (1) an order of the Supreme Court, Nassau County (Murphy, J.), dated April 3, 1984, which granted the motion of J. R. Stevenson Corp. (hereinafter Stevenson) and its sureties for partial summary judgment dismissing its third counterclaim and cross claim in action No. 1, (2) an order of the same court, also dated April 3, 1984 which granted the motion of Stevenson and its sureties for partial summary judgment dismissing the County’s third-party complaints against Stevenson for contribution or indemnity in action Nos. 2 and 3, instituted by Luna Industries, Inc. (hereinafter Luna) and Martin Mechanical Corp. (hereinafter Martin), respectively, (3) stated portions of an order of the same court dated April 12, 1984 which, inter alia, denied its motion for leave to amend its answer to Martin’s complaint in action No. 2 and granted, to a certain extent, Martin’s cross motion for partial summary judgment on certain of its claims, in that action, and (4) stated portions of an order of the same court dated June 11, 1984 which, inter alia, granted Luna’s cross motion to limit the County’s second counterclaim in action No. 3 for liquidated damages, insofar as asserted against it, to the sum of $8,700 (29 days X $300 per day). Martin cross-appeals from stated portions of the order dated April 12, 1984 which, inter alia, granted the County’s motion for partial summary judgment dismissing certain of Martin’s claims in action No. 2.
Orders dated April 3, 1984 affirmed, without costs or disbursements.
Order dated April 12, 1984 modified, on the law, by (1)
Order dated June 11, 1984 affirmed, insofar as appealed from, without costs or disbursements, and without prejudice to a motion by the County, if it be so advised, to amend the ad damnum clause of its first counterclaim asserted in action No. 3 to set forth an increased amount demanded as damages for incomplete or defective work.
Three of the prime contractors involved in the construction of the Westchester County Courthouse Complex, J. R. Stevenson Corp., the general contractor; Martin Mechanical Corp., the heating, ventilation and air-conditioning contractor; and Luna Industries, Inc., the electrical contractor, brought separate actions against the County seeking damages for delay, extras and their contract retainage. The County asserted counterclaims for its delay damage, both liquidated and actual, and the costs of defective and incomplete work. In each action the County also asserted third-party claims against the other two contractors seeking indemnity or contribution on the theory that any liability on its part to the respective plaintiffs was attributable to them.
The contract form used with each contractor included a "no-damage-for-delay clause”, prohibiting the contractors from recovering delay damages from the County for its acts, a hold-harmless clause, and a liquidated damages clause fixing a
The contractors sought dismissal of both the County’s third-party reimbursement claims and its actual delay damages counterclaims on the ground that they were barred by the liquidated damages clause of the contract. The County sought dismissal of the bulk of the contractors’ actual delay damages claims on the ground that they were barred by the no-damage-for-delay clause.
Special Term dismissed the County’s third-party claims and its actual delay damage clause. Leave to amend the County’s answer to include additional counterclaims against Martin was, in large part, denied. Summary judgment was granted to Martin on the bulk of its retainage and extra claims, and the County’s liquidated damages were limited. Certain of Martin’s claims were dismissed.
The County argues here, as it did before Special Term, that the liquidated damages clause does not serve to indemnify the County and is thus not enforceable. We disagree.
It has been noted that: "Parties to a contract may provide for anticipatory damages in the event of failure to complete performance within the time specified, as long as such agreement is neither unconscionable nor contrary to public policy. (Mosler Safe Co. v Maiden Lane Safe Deposit Co.,
Thus, a liquidated damages clause which is reasonable precludes any recovery of actual damages (General Supply & Constr. Co. v Goelet,
In the case at bar, we must reject the County’s contentions that the liquidated figure of $300 per day is inequitable or that it bears no rational relationship to the actual damages anticipated at the time the contracts in question were executed. After all, the County drafted the terms of the agreement and imposed it upon all the contractors, and the County was certainly in the best position to estimate the amount which would recompense it for the harm caused by a delay (see, X.L.O. Concrete Corp. v Brady & Co., supra). Neither can the County argue that the provision constituted a penalty designed to induce its performance rather than a means of providing just compensation for loss (see, Truck Rent-A-Center v Puritan Farms 2nd,
The County further argues that if the liquidated damages clause is enforceable, recovery of actual damages is appropriate if it should be found that both the owner and contractors contributed to the delay. As a general rule, where the delays are caused by the mutual fault of the parties, a liquidated damage clause is abrogated and each party must resort to an action to recover its actual damages (Mosler Safe Co. v Maiden Lane Safe Deposit Co.,
We also agree with Special Term’s determination that under the circumstances of this case, the liquidated damages clause in the contracts in question bars the third-party claims of the County to recover contribution or indemnity upon the theory that any liability it might have to one contractor was caused by the wrongs of others (see, General Supply & Constr. Co. v Goelet,
The County further contends that Special Term erred in denying its motion for summary judgment dismissing the contractors’ delay claims. The County asserts that these claims are barred by the no-damages-for-delay clauses in the three contracts.
Such a clause will not bar an action based on delays or obstructions which were not within the contemplation of the parties when the contract was executed (Cauldwell-Wingate Co. v State of New York,
We further note that Special Term properly limited any recovery by the County on its second counterclaim for liquidated damages as against Martin and Luna to the 29-day period attributed to those parties in the County’s answer to Luna’s interrogatory number 10.
In action No. 3, brought against the County by Luna, we find that Special Term properly dismissed the County’s third
In action No. 2, brought against the County by Martin, the County did move, inter alia, to amend the ad damnum clause of its first counterclaim which sought to recover damages for incomplete or defective work. That portion of the County’s motion which sought leave to amend its answer in that regard should have been granted to the extent indicated above. Given that amendment, the granting of partial summary judgment on Martin’s first cause of action against the County for recovery of the contract balance would be improvident, as Martin’s counterclaims on closely related matters seek sums in excess of this figure (see, Illinois McGraw Elec. Co. v John J. Walters, Inc.,
