97 Mich. App. 295 | Mich. Ct. App. | 1980
This is an appeal from the consolidated trial of four cases in which mechanics’ liens were asserted against the Thunderbird Hilton Inn by five subcontractors and the general contractor, DeWitt-Newton, defendant-appellee. The lower court entered judgment in favor of all of the lienors against IDS, defendant-appellant, the present owner of the Inn. IDS appeals. Subsequent to judgment and the filing of this appeal, the five subcontractors reached a settlement with defendant IDS. Therefore, DeWitt-Newton is the sole appellee.
This case arose out of a construction project known as the Thunderbird Hilton Inn (hereinafter the Inn). On November 18, 1971, Thunderbird Investment Corporation entered into a construction contract with DeWitt-Newton whereby De
Subsequently, Thunderbird Investment Corporation obtained a mortgage loan from IDS Mortgage Corporation in the initial amount of $4,100,000. That amount was increased to $4,300,000 and the mortgage was recorded on April 11, 1972.
As work progressed, it became apparent that the cost of completing the structure was greater than initially planned. In the spring of 1973, there were unpaid claims amounting to $203,000 for extra work authorized by the general contractor and Thunderbird Investment Corporation, as owner, but which were not included in or provided for by the construction loan with IDS.
In April or May of 1973, Thunderbird Investment Company applied to IDS for an increase in the amount of the mortgage loan to cover these bills. This request was refused. Work began to slow down on the project after May of 1973. The general contractor secured the project for the winter and, for such purposes, IDS authorized three construction draws, the last of which was made on or about September 14, 1973.
In the fall of 1973, DeWitt-Newton contracted with A & A Electrical Services. A & A performed work and provided materials until on or about January 2, 1974, at which time DeWitt-Newton was billed approximately $20,000 for these services. In March of 1974, DeWitt-Newton requested that A & A perform assorted electrical services in the bathrooms and on exit signs and to do general clean-up work on the project. The work was done on March 23, 1974, and DeWitt-Newton was billed $328.
On or about May 23, 1974, DeWitt-Newton
The Inn property was purchased April 4, 1974, through the foreclosure sale of the IDS Construction mortgage, at a sheriffs sale. The sheriffs deed to IDS was recorded on April 5, 1974, in the office of the Wayne County Register of Deeds.
Following a hearing, Judge John D. O’Hair entered a very thorough and well written opinion in favor of DeWitt-Newton Corporation and the five subcontractors. IDS appeals from two of the trial court’s findings. We first address Judge O’Hair’s finding that DeWitt-Newton substantially complied with the recording and notice requirements of the mechanics’ lien act.
IDS asserts that the trial court’s finding was erroneous on two grounds. First, IDS argues that DeWitt-Newton did not comply with MCL 570.5; MSA 26.285
The work done on March 23, 1974, consisted of repair work on the exit lighting and in the second floor bathrooms. This work was done at the request of DeWitt-Newton and was part of A & A’s October, 1973, contract. A & A billed DeWitt-Newton $21,889.05 for work done from October, 1973, to January 2, 1974. The bill for the March 23rd work was $328. Although IDS alleges that the work performed after September, 1973, was for the purpose of sale or to avoid bond liability, this allegation is not supported by the record. Rather it appears the work was done to attract additional financiers for the project. Admittedly, the work on the project was slowing down due to lack of money. However, it appears that the Thunderbird
"The Court is satisfied that the work done at the project in the latter part of March, 1974, was intended to further the project and the construction contract, and was not simply a device to afford DeWitt-Newton the opportunity to record its statement of account and lien within the time period prescribed by MCLA 570.5. Though the amount of work done at the project was relatively small in comparison to the entire project, it was beneficial and necessary.”
We decline to disturb this conclusion since it was clearly supported by the proofs. Tuttle v Dep’t of State Highways, 397 Mich 44, 46; 243 NW2d 244 (1976), Smith v Michigan State Accident Fund, 403 Mich 201, 204; 267 NW2d 909 (1978).
IDS next asserts that DeWitt-Newton’s failure to serve its statement of account and lien upon IDS and to name IDS as an owner on same renders DeWitt-Newton’s lien ineffective in light of MCL 570.5; MSA 26.285,
For the reasons stated we conclude that there was substantial compliance with the various requirements of the mechanic’s lien act in the present case.
IDS’s final argument is that the trial court erred in finding that DeWitt-Newton’s mechanics’ lien was superior to IDS’s construction mortgage. We disagree.
It is clear that all properly perfected mechanics’ liens based upon projects commenced before the filing of a construction mortgage take priority over that mortgage. MCL 570.9; MSA 26.289 provides in pertinent part:_
*303 "The several liens herein provided for shall continue for 1 year after such statement or account is recorded in the office of the register of deeds, and no longer unless proceedings are begun to enforce the same as hereinafter provided, and such liens shall take priority as follows:
"Third, They shall be preferred to all other titles, liens or incumbrances which may attach to or upon such building, machinery, structure or improvement, or to or upon the land upon which they are situated, which shall either be given or recorded subsequent to the commencement of said building or buildings, erection, structure or improvement”.
Williams & Works, Inc v Springfield Corp, 76 Mich App 541; 257 NW2d 160 (1977), Wallich Lumber Co v Golds, 375 Mich 323; 134 NW2d 722 (1965).
In this case the parties do not dispute that the general contractor entered into a contract with Thunderbird Investment Corporation to construct the Inn on November 18, 1971, that work on the Inn began in November, 1971, and that defendant IDS’s construction mortgage was not recorded until April 11, 1972. Based on these facts, DeWittNewton’s mechanics’ lien should take priority over IDS’s construction mortgage.
IDS argues, however, that since DeWitt-Newton owned 20% of the outstanding stock of Thunderbird Investment Company, owner of the Thunderbird Inn, DeWitt-Newton was in effect a partial owner of the Inn. As such, IDS contends, DeWittNewton is precluded by Heide v Societatea Romana, 262 Mich 394; 247 NW 702 (1933), from claiming that its mechanics’ lien has priority over IDS’s construction mortgage. We decline to read Heide as broadly as IDS urges.
In Heide, plaintiffs undertook in October, 1928, to construct an assembly hall for the defendant
Finding that plaintiffs took an active part in inducing the lender to take the mortgage and presented its own sworn statement of the amount due under the contract to the lender, the Supreme Court held that "loss of otherwise priority may arise where contractors, in effect, by affirmative action, induce or procure a mortgage to be given for their benefit and participate in the proceeds”. Id., 400. (Emphasis added.)
We agree with DeWitt-Newton’s analysis that the basis of the Heide decision is the agreement between the owner and the contractor, the active
While the general contractor in Heide was also an owner of the project, this fact was incidental to the issue considered by that Court. We do not read Heide as stating that simply by virtue of being an owner of the project the general contractor-owner loses the priority of his mechanics’ lien to a construction mortgagee. Nor do we find IDS’s argument that since DeWitt-Newton did not include $203,000 worth of "extras” due the subcontractors in the sworn statements or certificates of the contract-buyer submitted to IDS, DeWitt-Newton is now estopped from asserting its mechanics’ lien as superior to the mortgage lien. This $203,000 arose in the spring of 1973 and represented unpaid claims for extra work authorized by DeWitt-Newton and the owner, Thunderbird Investment Corporation, but were not included in or provided for by the construction loan with IDS. Although Thunderbird Investment Company applied to IDS for an increase in the amount of the mortgage loan to cover these bills, IDS refused the request: Clearly, IDS was not prejudiced by this statement since it not only refused to grant the requested increase, but both the owner and IDS admitted knowledge of the $203,000 extras prior to presentation of the sworn statement. Additionally, we note that since the statement only covered sums paid out under the mortgage, the inclusion of the $203,000 would have served no purpose.
Aside from the argument made as to the $203,000, there is no allegation that DeWitt-Newton affirmatively induced or procured IDS to give a
Affirmed. Costs to be paid by appellant.
MCL 570.5; MSA 26.285 provides in pertinent part:
"Every person, or his agent or attorney, whether contractor, subcontractor, material man or laborer, who wishes to avail himself of the provisions of this statute, shall make and record in the office of the register of deeds, in the county or counties in which said real estate, house, swimming pool, building, structure or improvement to be charged with the lien is situated, a just and true statement or account of the demand due him, over and above all legal setoffs, setting forth the time when such materials were furnished or labor performed, and for whom, and containing a correct description of the property to be charged with the lien, and the name of the owner, part owner or lessee, if known, which statement shall be verified by affidavit. Such verified statement or account shall be recorded within 90 days from the date on which the last of the materials shall have been furnished or the last of the labor or the last of the designing, engineering or surveying services shall have been performed or the*300 last day of use of any rented or leased equipment by the person claiming the lien.”
See footnote 1.
MCL 570.6; MSA 26.286 provides in pertinent part:
"Every person recording such statement or account as provided in the preceding section, except those persons contracting or dealing directly with the owner, part owner or lessee of such premises, shall within 10 days after the recording thereof, serve on the owner, part owner or lessee of such premises, if he can be found within the county or in case of his absence from the county, on his agent having charge of such premises, within the county wherein the property situated, a copy of such statement or claim; * * * before any subsequent proceedings shall be taken for the enforcement of such lien.”
MCL 570.29; MSA 26.309 defines owner as follows:
"For the purpose of this act the words 'owner, part owner or lessee’ shall be construed to include all the interest, either legal or equitable, which such person may have in the real estate upon which the improvements contemplated by this act are made, including the interest held by any person under contracts of purchase, whether in writing or otherwise.”
See footnote 3.