9 Conn. App. 481 | Conn. App. Ct. | 1987
This is an appeal from a judgment rendered in an action by the plaintiff to recover liquidated dam
The referee found numerous facts. In July, 1971, Cahn Engineers, Inc., entered into a contract with the defendants to provide engineering services in connection with the installation of sewers on State Street in New Haven. Cahn prepared specifications for the job which stipulated that the sewer trench would be protected by “sheeting-in-place.” Thereafter, the plaintiff submitted the lowest bid and was awarded the job. Work was to commence on May 31, 1973, and to be completed within 270 days. The contract between the plaintiff and the defendants provided for liquidated damages of $100 per day beyond the 270 day limit. A dispute arose and work stopped when the plaintiff, in an attempt to reduce his costs, refused to use the “sheeting-in-place” method of trench protection as required in the contract. Eventually, the parties reached a compromise and work resumed. The project was behind schedule, however, and final inspection did not take place until 873 days had elapsed from the date of the order to proceed. The plaintiff was paid $24,185, and the defendants retained $62,000 in liquidated damages for the 620 days beyond the contract limit taken to complete the job.
The trial referee concluded that the liquidated damages on the State Street job should have been limited to $57,500 and that, therefore, the plaintiff was entitled to $4500 plus interest. The referee also concluded that the plaintiff was not entitled to any additional compensation for the Dwight Street project since there were 437 unexcused delay days. The referee’s report was filed on September 25, 1984.
On October 17, 1984, the plaintiff filed an objection to judgment being rendered on the report. On October 18, 1984, the defendants filed a motion requesting judgment on the report. Both motions were assigned for hearing on October 29, 1984. At that hearing, the plaintiff requested a continuance of the arguments so that the attorney who tried the case could argue the motions. The trial court denied the continuance, and overruled the plaintiff’s objection because it was not timely filed. On the same day, the court accepted the referee’s report and rendered judgment thereon.
The plaintiff claims the trial court erred (1) in refusing to grant a continuance, (2) in refusing to consider the plaintiff’s objection to the referee’s report, and (3) in rendering judgment on the referee’s report. We find no error.
The rules of practice require that objections to the acceptance of a referee’s report be filed within two weeks of the filing of the report. Practice Book § 441. Clearly, the plaintiff did not comply with this rule since
In the absence of a timely objection to the report, our review is strictly limited to “ ‘determining whether the subordinate facts found by the attorney referee were sufficient to support the referee’s ultimate factual conclusions.’ ” Ross v. Renzulli, 9 Conn. App. 87, 90, 516 A.2d 149 (1986), quoting Blessings Corporation v. Carolton Chronic & Convalescent Hospital, Inc., 7 Conn. App. 364, 367, 508 A.2d 829 (1986). We conclude that the referee’s subordinate factual findings in this case sufficiently support the ultimate factual conclusions. The plaintiff’s final claim of error is without merit.
There is no error.
In this opinion the other judges concurred.
The city of New Haven is a codefendant in this appeal.