J. L. White Furnace Co. v. C. W. Miller Transfer Co.

115 N.Y.S. 625 | N.Y. App. Div. | 1909

Kruse, J.:

The defendant challenges the right of the plaintiff to prosecute this action, because the plaintiff is a foreign stock Corporation other *561than a moneyed corporation, and had no certificate, as provided by section 15 of the General Corporation Law,* authorizing it to do business in this State, but we think the plaintiff was not doing business in this State within the meaning of that section.

The contract was in the form of a written proposition submitted by the president of the plaintiff at Buffalo, in this State, to the president of the defendant, and accepted by the latter in writing and approved by the secretary of the plaintiff in the city of Milwaukee, in the State of Wisconsin, as was usual, by the plaintiff. So far as the evidence discloses, the plaintiff had no office and did no business in this State other than that of furnishing and installing the furnaces and doing the work under the contract. We think the plaintiff was not doing business in this State within the contemplation of the section referred to. (Ozark Cooperage Co. v. Quaker City Cooperage Co. 112 App. Div. 62; Union Trust Co. v. Sickels, 125 id. 105; Penn Collieries Co. v. McKeever, 183 N. Y. 98.)

The other question raised by the defendant is more serious. If the defendant’s only remedy for the breach of warranty is to remove the material and hold it subject to the order of the plaintiff, manifestly the defendant cannot recover upon its counterclaim, since it has not availed itself of the provision-by removing the material as is therein provided. It is undoubtedly true, as contended by the plaintiff and held by the trial court, that it was entirely competent for the parties to contract for the specific remedy of removing the furnaces and material for a failure of the furnaces to meet the requirements of the contract, and éven make the remedy exclusive. But such a special remedy is not exclusive unless it is apparent that such was the intention of the contracting parties.

In order to determine the intention of the parties in that regard, it may be well now to refer to another provision of the contract and the surrounding circumstances. The contract required the defendant to build the foundations for the furnaces. This and the other changes which the defendant would have to make to use the furnaces in connection with the boilers would require the expenditure *562of a ■ considerable amount; and taking out and removing the fur-maces in case they were not successful and up to the requirements of the contract would require a further expenditure.

The contract was made in October, 1906. The work was done in November and December, 1906, being completed on or about December twenty-first. The contract price was $1,500. Five hundred dollars was paid thereon at the plaintiff’s request on that day, which was before the furnaces had been operated. On January 28, 1907, the defendant made a further payment of $100 at the plaintiff’s request. On J anuary 30,1907, the board, of health of the city warned the defendant of the offensive odors being emitted by the burning of the manure. Various interviews occurred between the presidents of the respective companies, a demand being made on behalf of the plaintiff for the balance of the contract price, and a refusal upon the part of the defendant to pay the same, upon the ground that the furnaces were not up to the requirements of the contract. There is a dispute in the evidence as to just what was said about taking out the furnaces. It is, however, a conceded fact that the furnacds were not taken out. »

It appears that even before the $100 was paid, the furnaces had been operated and that odor from the burning manure was detected, but, as the defendant’s president testified, he was assured by the plaintiff’s representative that it would be better, and he was assured that the furnaces would meet the requirements of the contract, and requested that the furnaces be left there for a while. . .

On March 21, 1907, notice of lien was filed. The action, was commenced April 18, 1907. After the action had been commenced and between June 7 and July 14, 1907, an agreement was made between the parties that the furnaces should be further tested, the claim being made on behalf of the plaintiff that the defendant’s Workmen engaged in firing the furnaces did not properly do that work. Thereupon a further test was made by a person who was satisfactory to the defendant, with the same result as before — offensive odors were still emitted from the stack, caused by the burning of the manure. In short, the trial judge finds that at no time did' these furnaces burn all the manure, or burn it without emitting offensive odors from the stack.

We deem it unnecessary to enter into an extended argument *563upon the facts, or an analysis of the various’ cases cited by counsel for the respective parties. In view of the positive guaranty of the plaintiff,,the large expenditure to be made by the defendant before the test could be made to determine the efficiency of the furnaces, the loss to the defendant in taking them out and the conduct of the parties after making the contract, we think it. should not be held that it was the intention of the parties that the only remedy which the defendant should have for the- failure of the furnaces to meet the requirements of the contract, was to take them out and hold them subject to the order of the plaintiff. But even if such was the intention when the contract was entered into, the payment of a part of the purchase price by the defendant upon the assurance that the furnaces would do the work as required by the contract, and the request by the plaintiff to ’ leave the furnaces after they had been tested and found wanting, and the other circumstances in the case, to which I have alluded, modified the contract in that regard, and the plaintiff waived the right to require the defendant to remove the furnaces, and rely solely upon that remedy for the non-fulfillment of the contract upon the part of the plaintiff. In either view the conclusion follows that the defendant is not limited in its remedy, as is contended by the plaintiff, but may recover such damages as it has sustained from the failure of the plaintiff to furnish and install furnaces to meet the requirements of the contract.

The judgment should be reversed and a new trial granted, with costs to the appellant to abide the event.

All concurred.

Judgment reversed and new trial ordered, with costs to appellant to abide event, upon questions of law and fact.

See Laws of 1892, chap. 687, § 15, as amd. by Laws of 1904, chap. 490.— [Rep.

midpage