delivered the opinion of the court:
Defendant-appellant, Montalbano Builders, Inc. (Montalbano), appeals from an order of the circuit court of Du Page County denying his motion to stay all proceedings and to compel arbitration. Montalbano and defendants-appellees Joseph and Mary Falbo (the Falbos) entered into a written contract which included an arbitration clause on October 29, 1980, for the construction of a home. The Falbos agreed to pay Montalbano $360,000 for the construction work. Montalbano entered into various contracts with subcontractors to perform the work, none of which contained an arbitration clause.
To date, the Falbos have paid $208,236.00 to Montalbano on the contract. During construction, a dispute arose between the Falbos and Montalbano, and the Falbos have refused to pay any additional sums to Montalbano until certain corrections are made. Prior to litigation, 15 subcontractors and Montalbano had filed lien claims with the office of recorder of deeds of Du Page County. Two subcontractors filed separate suits to foreclose on mechanics’ lien claims against the Falbos’ real property. The cases were consolidated on July 21,1982.
The Falbos filed their answer and countercomplaint against Montalbano, alleging (1) breach of contract; (2) breach of an implied warranty of habitability; (3) precontract fraud; (4) unfair and deceptive trade practices; (5) negligence, and also petitioned the court for a general settlement under section 30 of the Mechanics’ Liens Act (Ill. Rev. Stat. 1981, ch. 82, par. 30). As its responsive pleading to all complaints, Montalbano filed on September 29, 1982, a motion to stay all proceedings and for an order compelling arbitration between the Falbos and Montalbano. Prior to this motion, eight subcontractors joined the lawsuit in addition to those who had initiated the proceedings. After five more subcontractors joined this litigation, the court on November 17, 1982, denied Montalbano’s motion, who then filed a timely interlocutory appeal.
After oral argument in this case, Montalbano filed on May 24, 1983, a motion to realign the parties on appeal and to suggest the mootness of objections to Montalbano’s motion to compel arbitration. In his appellate motion, Montalbano asserted that it had settled and compromised the claims of nine subcontractors and was assigned their lien rights. Additionally, Montalbano stated that seven more subcontractors had withdrawn any objections to and joined in its motion to compel arbitration. On May 31, 1983, the Falbos filed their answer and supporting memorandum wherein they asserted that Montalbano’s motion lacked certain procedural requisites, and did not render any issue moot. On July 20, 1983, this court granted Montalbano’s motion to file a reply to the Falbos’ answer and ordered that the reply be taken with this case.
Although the order appealed from in the instant case is interlocutory, we nonetheless have jurisdiction for the trial court’s denial of the requested relief is analogous to the denial of an injunction. (Kelso-Burnett Co. v. Zeus Development Corp. (1982),
In Illinois, contractual arbitration provisions are construed in light of the Illinois Uniform Arbitration Act. (Ill. Rev. Stat. 1981, ch. 10, par. 101 et seq.) Illinois adopted the provisions of the Uniform Arbitration Act with minor modifications in 1961. (School District No. 46 v. Del Bianco (1966),
“One of the fundamental objectives of the act was to encourage and facilitate the arbitration of disputes by providing a speedy, informal, and relatively inexpensive procedure for resolving controversies arising out of commercial transactions, including the labor-management field. The language of the act emphasizes an intention to change the common-law policy of judicial hostility toward arbitration to one favoring arbitration. Contrary to decisions found in many states, it specifically makes a written agreement to arbitrate effective whether relating to existing or future disputes.” Layne-Minnesota Co. v. Regents of the University of Minnesota (1963),266 Minn. 284 , 287-88,123 N.W.2d 371 , 374. See School District No. 16 v. Del Bianco (1966),68 Ill. App. 2d 145 ,154,215 N.E.2d 25 , 29.
Both the Uniform Arbitration Act and the Federal Arbitration Act (9 U.S.C. sec. 1 et seq. (1976)), enacted in 1925 are patterned after the New York arbitration statute enacted in 1920. (Sonderby, Commercial Arbitration: Enforcement of An Agreement to Arbitrate Future Disputes, 5 J. Mar. J. Prac. & Proc. 72, 75-76 (1971), citing 1920 N.Y. Laws, ch. 275, originally in N.Y. Civ. Prac. Act sec. 1448-69, now in N.Y. Civ. Prac. Law & Rules sec. 7501 — 14 (McKinney 1963); see also Greenfield, The Contract to Arbitrate Future Disputes: A Comparison of the New Mexico Act With the New York and Federal Acts, 9 N.M.L. Rev. 71, 71-72 (1978-79).) Given the common origins of the Federal and uniform statutes, courts interpreting State arbitration statutes patterned after the Uniform Arbitration Act look for guidance to Federal court decisions interpreting similar provision of the Federal Arbitration Act. (See Charles J. Frank, Inc. v. Associated Jewish Charities of Baltimore, Inc. (1982),
Section 2(a) of the Illinois Uniform Arbitration Act (Ill. Rev. Stat. 1981, ch. 10, par. 102(a)) provides: At a hearing to stay a judicial proceeding and to compel arbitration, the trial court should concern itself solely with whether an agreement exists to arbitrate the dispute in question. Farris v. Hedgepeth (1978),
“On application of a party showing an [arbitration] agreement ***, and the opposing party’s refusal to arbitrate, the court shall order the parties to proceed with arbitration, but if the opposing party denies the existence of the agreement to arbitrate, the court shall proceed summarily to the determination of the issue so raised and shall order arbitration if found for the moving party, otherwise, the application shall be denied.”
The trial court did not make a finding with respect to the existence of an agreement to arbitrate which was error. (KelsoBurnett Co. v. Zeus Development Corp. (1982),
On the other hand, the Falbos contend that the parties’ written agreement actually contained an additional arbitration clause with a different set of governing rules, and thus, the parties could not have reached agreement on a specific arbitration procedure. The contract does refer to two arbitration clauses. While these two clauses appear to conflict, the language of the second clause contained in AIA Form No. A107 and incorporated by reference into the general conditions of the parties’ contract states that it becomes operative only if the parties do not establish an alternative procedure. Here, the parties established with the inclusion of paragraph 22 an alternative arbitration procedure and thus, the parties did agree to one form of dispute resolution.
In addition to ascertaining the existence of an agreement to arbitrate, a court should order arbitration only if the dispute is arbitrable. In resisting arbitration, the Falbos argue that the issues of breach of implied warranty of habitability, precontract fraud, unfair and deceptive trade practices, negligence, and general settlement under the Mechanics’ Liens Act are not subject to arbitration, but cite no authority for their position. Arbitration contracts are interpreted in the same manner and according to the same rules as are all other contracts. (See Flood v. Country Mutual Insurance Co. (1968),
Whether a dispute is within the scope of an arbitration clause “ ‘should be determined at the earliest possible moment and should be controlled by judicial guidelines.’ ” (Farris v. Hedgepeth (1978),
We believe that the parties’ arbitration clause is sufficiently broad to encompass each of the Falbos’ counts. In the instant case, the written contract contains a “generic” arbitration clause which does not enumerate which disputes are arbitrable. (Roosevelt University v. Mayfair Construction Co. (1975),
Our conclusion that each count in the Falbos’ counterclaim is arbitrable is buttressed by the drafting of the counterclaim itself. In count I, the Falbos alleged Montalbano breached his contract with the Falbos. The first 13 paragraphs of count I allege facts relating to the discussions between the parties preceding their signing of the contract, payments made by the Falbos to Montalbano and the fulfillment by the Falbos of all of their obligations under the contract. Counts II-VI reallege these identical paragraphs in support of the separate bases for liability alleged in each of these counts. Very few additional facts other than those alleged in count I are alleged in the subsequent counts of the Falbos’ counterclaim. Since the facts which underlie the breach of contract count also underlie the other counts, we conclude that these counts arise out of or relate to the contract or its breach.
Examination of the counts themselves also leads to the conclusion that the counts are arbitrable. Count II is based upon Montalbano’s alleged breach of an implied warranty of habitability. The Falbos allege no facts in addition to those alleged in their breach of contract count to support count II. Our supreme court in Petersen v. Hubschman Construction Co. (1979),
We likewise believe that count III based upon precontract fraud is arbitrable. The Falbos in count III do not allege that Montalbano’s fraudulent actions relate specifically to the parties’ agreement to arbitrate. Rather, the Falbos assert they were denied the performance to which they were entitled based upon the representations made to them prior to entering into the contract. The majority of courts considering a claim of fraud concerning the contract as a whole as opposed to a fraudulent inducement to enter into an arbitration agreement has concluded that the fraud claim is within the scope of a broad arbitration clause. (E.g., Prima Paint Corp. v. Flood & Conklin Manufacturing Co. (1967),
Similarly, count IV alleging unfair and deceptive trade practices in violation of the Illinois Consumer Fraud and Deceptive Business Practices Act (Ill. Rev. Stat. 1981, ch. 121½, par. 261 et seq.) (consumer fraud act) states no facts in addition to those alleged in count I. Count IV merely recites conclusory allegations that the facts comprising the breach of contract and fraud counts also constitute unfair and deceptive acts violative of the consumer fraud act. Our reading of count IV discloses no allegations based upon any aspect of the strong public policy embodied in the consumer fraud act, but rather the allegations “appear to be an attempt to bolster and supplement clearly private claims.” (Greenleaf Engineering & Construction Co. v. Teradyne, Inc. (1983), 15 Mass. App. 571,_,
Count V based on negligence alleges that Montalbano breached its duty to construct the home in a good and workmanlike manner. Therefore, the Falbos used the negligence term to describe a breach of a duty owed to the Falbos by virtue of the parties’ contract and not from a duty based in tort. To support this count, the Falbos alleged the identical defects in construction .contained in count I. Therefore, this count is also arbitrable. See Premier Electrical Construction Co. v. Ragnar Benson, Inc. (1982),
Count VI, seeking a general settlement under section 30 of the Mechanics’ Liens Act (Ill. Rev. Stat. 1981, ch. 82, par. 30), realleges the first 18 paragraphs of count I. Mechanics’ liens exist only by virtue of the statute creating them (Robinette v. Servite Fathers (1977),
Montalbano argues that since a valid arbitration clause exists, the court must enforce the arbitration agreement even though the general contractor and the homeowner are parties to a multiparty lawsuit concerning the identical construction project. The Falbos respond that where an arbitration agreement involves some, but not all of the parties to a multiparty dispute, the policy favoring arbitration must be balanced against that favoring joinder of claims. The Falbos contend that the claims of the parties to the instant dispute arise from the same project and involve common issues and evidence and thus, arbitration is not appropriate in this case. The Falbos rely heavily on J.F. Inc. v. Vicik (1981),
“The claims of the four subcontractors, who are not subject to arbitration, all arose from the same construction project which is the basis of the disputes between the general contractor and the homeowners. The claims which the subcontractors pressed in their legal actions did not arise from direct disputes between the subcontractors and either the general contractor or the homeowners but only as subsidiary claims resulting from the basic dispute between general contractor and homeowners. Therefore, all claims involve common issues and evidence.” J.F. Inc. v. Vicik (1981),99 Ill. App. 3d 815 , 820,426 N.E.2d 257 , 261.
In reaching its conclusion, the appellate court, fifth district, in Vicik discussed this court’s earlier decision in Iser Electric Co. v. Fossier Builders, Ltd. (1980),
While recognizing the general rule, the court in J.F. Inc. v. Vicik (1981),
Subsequent to Vicik, this court in Kelso-Burnett Co. v. Zeus Development Corp. (1982),
We believe that the policy in Illinois favoring arbitration requires the conclusion that the trial court erred in refusing Montalbano’s motion to compel arbitration. In so holding, we find unpersuasive the arguments advanced by courts in this and other States for denying arbitration and for consolidating all parties’ claims in the judicial forum.
Courts advance several reasons for refusing to compel arbitration and for consolidating the parties and issues subject to arbitration with the court proceedings. The first reason is that allowing arbitration between two of the parties in multiparty proceedings while litigation involving some of these same parties proceeds frustrates the goal of judicial economy. (J.F. Inc. v. Vicik (1981),
“Where arbitration would increase rather than decrease delay, complexity and costs, it should not receive favored treatment.”
Closely related to this concern for judicial economy is the argument that joinder should be favored over arbitration when the issues in the arbitration and court proceeding are closely intermingled involving common issues and evidence, thereby resulting in the duplication of proof. (J.F. Inc. v. Vicik (1981),
We believe none of these reasons warrants our refusal to enforce the arbitration clause in the instant case. Requiring the parties here to arbitrate will not result in judicial inefficiency. Were all parties and issues joined in the lien foreclosure action, at least an equivalent amount of judicial resources would be utilized in the consolidated proceeding. More effort may be required of the Falbos and Montalbano in resolving the disputes between them in arbitration and the disputes with the subcontractors in the judicial forum, but this result is not unfair to either Montalbano or the Falbos because they specifically agreed in writing to resolve their disputes in arbitration. Since the issues raised by the Falbos in their counterclaim were subject to arbitration, fewer judicial resources will be expended by forcing the parties to resolve their disputes privately than if the entire counterclaim were resolved in the judicial proceeding. Even if more judicial resources are expended as a result of our decision to compel arbitration, we do not believe that judicial economy is a . sufficient basis for denying arbitration. See Dickinson v. Heinhold Securities, Inc. (7th Cir. 1981),
The subsidiary nature of the subcontractors’ claims similarly does not warrant denial of Montalbano’s motion to compel arbitration. In J.F. Inc. v. Vicik (1981),
Certain factors militate toward the conclusion that the subcontractors’ claims here are not subsidiary to the dispute between Montalbano and the Falbos. The rights between the Falbos and Montalbano are defined by the contract between them. The rights of the subcontractors are defined by their separate contracts with the general contractor. The distinct nature of the contractual rights of the subcontractors is recognized by the Mechanics’ Liens Act. A subcontractor has five remedies to enforce his rights: (1) an action at law against the original contractor alone; (2) an action at law against the original contractor and the owner jointly; (3) an action at law upon the original contractor’s completion bond; (4) an action in equity to enforce the subcontractor’s lien; and (5) intervention in a pending action of the original contractor against the owner. (Ill. Rev. Stat. 1981, ch. 82, par. 1 et seq.; see Illinois Mechanics’ Lien 5 — 54 (Ill. Inst. Cont. Legal Educ. 1981).) The remedies of a subcontractor are cumulative and may be pursued consecutively or concurrently. (Culver v. Elwell (1874),
Even if the subcontractors’ claims are viewed as subsidiary, we disagree with the Vicik court’s conclusion that the subsidiary nature of the claims justifies consolidation of the arbitration hearing with the court proceedings. Rather, we conclude that arbitration of the primary dispute between the Falbos and Montalbano will determine the amount owed Montalbano. After Montalbano receives payment, funds should be available to satisfy the claims of his subcontractors, thereby possibly alleviating the need for the subcontractors to foreclose on their mechanics’ liens. (See Kelso-Burnett Co. v. Zeus Development Corp. (1982),
Neither do we believe that duplication of proof will result because the two proceedings involve common issues and evidence. The dispute between Montalbano and the Falbos which is subject to arbitration involves proofs which are not necessary or even relevant to the subcontractors’ lien action. The Falbos’ counterclaim is directed at Montalbano exclusively except for count VI seeking a general settlement. The Falbos alleged that Montalbano misrepresented to the Falbos that “the specifications contained in the Customer Building Proposal for the construction of the home were the same specifications contained in the plans drawn by the architect” except for items the parties had agreed to change. Evidence necessary to prove this assertion would not be germane in the lien foreclosure action. The arbitrator also will have to rule on the counts based upon an implied warranty of habitability, precontract fraud and unfair and deceptive trade practices, none of which should require proof duplicative of that offered in the lien foreclosure action. The multitude of construction defects alleged in the Falbos’ counterclaim suggest that the arbitration hearing will be broader in scope than the lien foreclosure action. Since only eight subcontractors still hold lien claims against the property, that proceeding will not cover many of the construction defects alleged in the Falbos’ counterclaim.
In contrast to arbitration which is designed to resolve the disputes arising out of or relating to the contract between the Falbos and Montabano, the purpose of a lien foreclosure action is for the subcontractor to obtain a legal hold on the owner’s property as security for a debt. (See Moulding-Brownell Corp. v. E.C. Delfosse Construction Co. (1937),
Nor do we believe that the potential for inconsistent results from the judicial and arbitration forums warrants nonenforcement of the arbitration clause. Neither party has demonstrated to us how inconsistent results can obtain from staying the judicial action while arbitration proceeds. Rather than producing inconsistent results, this procedure will likely result in payment to Montalbano of a sum of money which can then be used to satisfy Montalbano’s obligations to his subcontractors. We believe that we should adhere to the general rule in Illinois that arbitration agreements in multiparty litigations should be enforced despite the existence of claims by third parties which create the potential for duplicative proceedings. Iser Electric Co. v. Fossier Builders, Ltd. (1980),
We also reject two additional arguments raised by the Falbos. Based upon Kelso-Burnett Co. v. Zeus Development Corp. (1982),
In contrast to Kelso-Burnett, no party to the arbitration agreement here caused the multiplicity problem. The multiplicity difficulties arose when the two subcontractors who were not parties to the contract containing the arbitration clause filed suit to foreclose on their mechanic’s lien. Montalbano no more caused the multiplicity problem than did the Falbos. While it may have been more prudent for Montalbano to have included arbitration clauses in his subcontracts, he was not required to do so. Nothing prevented the Falbos from insisting that Montalbano only employ subcontractors who would agree to arbitrate disputes in a consolidated hearing. The Falbos were fully aware that work would be performed by subcontractors with which they would have no direct contractual relationship. The inability to require the subcontractors’ participation in the arbitration hearing, therefore, is as much the Falbos’ fault as Montalbano’s. The Falbos should not be relieved of the contractual obligation to arbitrate simply' because the subcontractors are not subject to arbitration, thereby forcing the Falbos to protect their interests in two different forums. Were we to deny Montalbano’s demand for arbitration, arbitration clauses in multiparty construction contracts could be rendered meaningless solely because one or several of the subcontractors did not agree to arbitrate their disputes with the general contractor. We do not believe that the policy in this State favoring arbitration should be frustrated so easily.
Concern of the trial judge and the Falbos about the Falbos’ exposure to liability during arbitration similarly does not warrant denial of Montalbano’s motion to compel arbitration. While both state that under the liens act, the Falbos’ home would be exposed to liability during arbitration proceedings, Montalbano persuasively argued at the hearing on his motion that the Falbos’ home would be subject to the same liability during consolidated trial proceedings. If this cause proceeded to court on the lien foreclosure suit, and Montalbano were awarded less than the total amount of the mechanic’s lien claims, and Montalbano did not satisfy his additional debt, then the subcontractors could proceed against the Falbos and their home. Thus, the Falbos’ potential liability is not altered by use of the judicial as opposed to the arbitration forum. The trial court also expressed concern that the resolution of the dispute between the Falbos and Montalbano by arbitration will impair the subcontractors’ rights to obtain full satisfaction of their debts. The parties have failed to cite and we have not found any authority that states that the subcontractors’ recovery is dependent upon the arbitrator’s findings concerning the contract between the homeowners and the general contractor.
In addition to rejecting the reasons advanced by the Falbos and other courts for denying arbitration in multiparty litigation, we believe there exists several persuasive arguments supporting our decision to compel arbitration in this case. In Charles J. Frank v. Associated Jewish Charities of Baltimore, Inc. (1982),
“ ‘If a claim of right to arbitration could be foreclosed whenever a dispute between the parties to the contract derives from another person’s claim against one of the parties, the utility of broad arbitration agreements would be undermined.’ ” 12 Mass. App. 160, _,422 N.E.2d 782 , 785, quoting Acevedo Maldonado v. P.T.G. Industries, Inc. (1st Cir. 1975),514 F.2d 614 , 617.
In addition to frustration of the policy favoring arbitration, the Frank court stated as a second rationale for compelling arbitration that “the enactment of the Uniform Arbitration Act evidences a legislative intent that arbitration not be enjoined to prevent multiplicity of actions.” (Charles J. Frank, Inc. v. Associated Jewish Charities of Baltimore, Inc. (1982),
“Section 2(d) of the Illinois Act shows that the Legislature contemplated a multiplicity of actions. In enacting the Uniform Arbitration Act, the Legislature has not eradicated a chancellor’s inherent powers, but the Legislature has determined in Section 2 that it is no longer equitable to enjoin arbitration to prevent multiplicity of actions.”376 F. 2d 711 , 716.
We find these rationales persuasive. Courts in this State have recognized consistently the public policy favoring arbitration. (Board of Trustees v. Cook County College Teachers Union, Local 1600 (1981),
In addition to granting Montalbano’s motion to compel arbitration, we believe that the subcontractors’ lien foreclosure action should be stayed pending the outcome of the arbitration hearing. Section 2(d) of the Uniform Arbitration Act states:
“Any action or proceeding involving an issue subject to arbitration shall be stayed if an order for arbitration or an application therefor has been made under this Section or, if the issue is severable, the stay may be with respect thereto only. When the application is made in such action or proceeding, the order for arbitration shall include such stay.” (111. Rev. Stat. 1981, ch. 10, par. 102(d).)
The Falbos’ counterclaim challenging the construction of their home is arbitrable. The eight subcontractors have filed their lien foreclosure action seeking security to ensure satisfaction of the debt owed to them by Montalbano. Since the result of the arbitration may eliminate the necessity for pursuing the court action, we order that the entire lien action be stayed pending arbitration. While the subcontractors are not parties to the contract containing the arbitration clause, both Federal and State courts have stayed court proceedings involving parties who are not bound by the arbitration clause. See Kelso-Burnett Co. v. Zeus Development Corp. (1982),
The Falbos’ last basis for avoiding arbitration is that fundamental fairness notions would be violated if this court were to allow the Northern Illinois Home Builders Association (Association) to decide this dispute between Montalbano, one of its members, and the Falbos. While not alleging that the arbitration forum is actually biased or prejudiced, the Falbos argue the appearance of bias is sufficient to require nonenforcement of the arbitration clause. In response, Montalbano contends that the Association is the proper forum for resolution of this dispute.
The merits of Falbos’ public policy argument do not, we believe, require us to declare the arbitration forum here inimical to notions of fairness. Where a contract is in fundamental conflict with public policy, the contract will not be enforced. (People ex rel. Callahan v. Marshall Field & Co. (1980),
The Falbos cite no provision of our constitution or any statutes supporting their position that arbitration here violates public policy. Examination of the practice of government officials is not relevant to the instant inquiry, and the judicial precedents cited by the Falbos do not require the conclusion that this clause should be invalidated. The Falbos cite two decisions from foreign jurisdictions as support for their position that the appearance of bias warrants nonenforcement of the arbitration clause. This court is not bound in determining its public policy by the decisions of other States, however, and the Falbos cite no Illinois cases concluding that similar arbitration clauses violate public policy.
The only Illinois decisions cited by the Falbos, Freeport Construction Co. v. Star Forge, Inc. (1978),
The arbitration clause in the case at bar is conspicuous and the Falbos do not contend that they were not aware of this provision when they signed the contract. In addition, on the same page as the arbitration clause was a fully capitalized sentence which states: “SECTION 22 [the arbitration clause] OF THIS CONTRACT IS NULL AND VOID IF AT THE TIME OF ITS EXECUTION, THE CONTRACTOR REFERRED TO ABOVE IS NOT A MEMBER IN GOOD STANDING OF NIHBA.” Thus, the Falbos were expressly aware that Montalbano was a member of the Association when they signed the contract. The absence of persuasive Illinois precedent and the clarity of the contract language suggest that this arbitration clause does not violate public policy.
In light of our disposition of this case, we need not address Montalbano’s motion to realign the parties and to suggest the mootness of certain objections to its trial court motion to compel arbitration.
Accordingly, we reverse the order of the circuit court of Du Page County and grant Montalbano’s motion to compel arbitration and to stay the judicial proceedings pending completion of the arbitration hearing.
Reversed and remanded with directions.
SEIDENFELD, P.J., and NASH, J., concur.
