112 Wis. 532 | Wis. | 1902
One important stipulation in the written ■contract was that no alterations should be made in the work shown or described by the drawings and specifications except upon the written order of the architect. It seems to have been assumed on the trial that this stipulation was sufficiently broad to cover extra work, and was of such a character as that the architect might waive its provisions. There is no dispute but that extra work was performed, and the amount thereof was determined by the architect and included in the final certificate. It is not claimed that such work was done upon the written order of the architect, but it is claimed that defendants waived that provision of the ■contract. Whether the architect had any power to waive contract provisions of that kind is very doubtful; but, defendants having consented that the court should answer question 4 of the verdict without submission of the fact to the jury, that question is not now before us for decision. Permitting the court to answer that finding in the affirmative precludes the defendant from raising any objection to the finding at this time.
A much more serious question arises regarding the answer to the sixth question. There is absolutely no evidence in the case that the defendants have personally done anything
The importance of this stipulation, as well as its purpose, is manifest. The very contest that has arisen in this case demonstrates the necessity of some such cautious provision. Disputes frequently arise between different pon tractors, or the owner and the architect, as to responsibility for delays in the work. Owners are very much in the power of contractors and architects. To avoid the uncertainty of verbal disputes, and to prevent the contractors from making claims
As we have already said, the purpose of this stipulation was to protect the defendants from stale claims for delay, which might be based upon oral understandings, and made when it might be difficult to prove the facts in relation thereto. The giving of the notice was a condition precedent to any authority on the part of the architect to act. The latter was not a general agent of defendants. He had only such authority as was given him under the contract. Thus, in California an architect, without special authority conferred by the written contract, was not authorized to receive notice of an assignment ‘of a building contract. Renton, H. & Co. v. Monnier, 77 Cal. 449. He has no power to bind the owner for extra work unless it is done as the contract prescribes. Baltimore C. Co. v. Coburn, 7 Md. 202; Starkweather v. Goodman, 48 Conn. 101. See Condon v. Jersey City, 43 N. J. Law, 452; Sutherland v. Morris, 45 Hun, 259; Fitzgerald v. Moran, 141 N. Y. 419. Where the contract provided that no claim for extra work should be allowed “ unless the same should he done in pursuance of a written order from the engineer in charge, and the claim made at the first settlement after the work was executed,” it was held that the engineer had no power to alter or change the contract, and no allowance for extra work could be made without proof of performance of the conditions precedent in the contract. Woodruff v. R. & P. R. Co. 108 N. Y. 39. In
“No one could for a moment be led into any misapprehension as to the extent of the engineer’s authority to ■charge the company by varying the existing conditions or making new ones. The engineers were there for no such purpose, and they had no such agency, except under specific limitations and restrictions, and they did not, as to this item, assume to do any such thing.”
See, also, Vanderwerker v. V. C. R. Co. 27 Vt. 130; Lewis v. Slack, 27 Mo. App. 119. In Dodge v. McDonnell, 14 Wis. 553, where one had employed an architect to make plans for a house and do such other acts as architects usually do as such, and had engaged a contractor to do the work and furnish the materials, and had placed money in the architect’s hands to be paid on the contractor’s order, it was held that this did not warrant a finding that the architect was the general agent of his employer, and he had no authority to bind him by new contracts for materials with other persons. See Campbell v. Day, 90 Ill. 363. In Starkweather v. Goodman, 48 Conn. 101, a builder made a written contract to furnish the materials and build a house for defendant according to definite plans and specifications and for a fixed sum, all the materials and work to be accepted by an architect named, who Avas to superintend the construction. The builder, under the direction of the architect, did certain work variant from, and in addition to, the specifications, which increased the cost and value of the house. Held that
“ An architect or engineer has no general authority to-dispense with, waive, vary, or alter the conditions of a building contract. His duty is to see that it is faithfully fulfilled according to its terms; but it may be varied by the parties themselves, who are entitled to strict compliance therewith, or by the architect under special authority given-him on that behalf.”
This rule was applied in Canada in Jones v. Reg. 7 Can. Sup. Ct. 570, which contains a careful discussion of both the-English and American decisions.
The decisions cited indicate the. almost unvarying rule-that, without express authority, the architect cannot waive important conditions in his employer’s contract. The parties, themselves have that power, and the courts have frequently recognized it. Bannister v. Patty's Ex'rs, 35 Wis. 215; McPherson v. Rockwell, 37 Wis. 159; Boden v. Maher, 105 Wis. 539, and Wambold v. Gehring, 109 Wis. 122,—are cases in. this court. A proper construction of the contract makes the-giving of the notice to the architect a condition precedent, to the right of plaintiff to claim an extension of the time for the completion of the building. It was a condition the-architect had no power to waive. There is no claim that, the defendants have done anything to waive it.
It being admitted that the work was not finished within the time limited by the contract, the defendants were entitled to damages for the delay. The contract stipulated $50 per day as liquidated damages. We are unable to say from the evidence whether that sum is so disproportionate to the actual injury suffered as that it should be construed to be a mere penalty, or as damages fully liquidated. Seeman v. Biemann, 108 Wis. 365. The trial court seems to-have treated it as liquidated damages and denied defendants, the right of showing the rental value of the building, be
The jury found that plaintiff completed the building on November 27th, a delay of twelve days. The defendants claim a delay of thirty-two days. Plaintiff’s testimony is quite inconclusive on the subject. The manager testified the building was completed on the day mentioned; yet there appears in the record a letter written by him on that day asking the architect for an estimate on account, in which he says:
“ We figure that five hundred dollars will complete all the work left to do under our contract, and expect to get an estimate for the baLance due, less that amount and the retain age.”
These two statements do not harmonize. If there was yet work of the value of $500 to be done, it could not be well said that the building was finished. In view of the testimony of defendants that the building was not completed until some time afterwards, the finding of the jury as to date of completion had very little to rest upon. It was clearly against the evidence.
The evidence offered to impeach the certificate of the architect was not of the character demanded in this class of cases. In Hudson v. McCartney, 33 Wis. 331, this court laid
We see no error in the other assignments raised and discussed.
By the Oowrt.— The judgment is reversed, and the cause is remanded for a new trial.