124 Minn. 251 | Minn. | 1914
The complaint alleged that on August 16, 1911, defendant and plaintiff entered into a written contract, by the terms of which defendant ordered from plaintiff one 300-gallon Jensen cream ripener, and agreed to pay therefor the sum of $260, by giving his note for that sum payable six months after the receipt of the ripener, with six per cent interest; that plaintiff delivered the ripener to defendant August 19, 1911, and that it was duly received and accepted by defendant on the twentieth; that plaintiff thereupon demanded of defendant that he execute and deliver the note, but that defendant has refused and still refuses to do so, or to pay the agreed price of the ripener, “all to the damage of this plaintiff in the sum of $260, together with interest * * * at the rate of six per cent per annum” from August 20, 1911. Judgment was demanded for such sum and interest.
The answer admitted that on August 16, 1911, plaintiff and defendant entered into a written contract, which was in the following words: “The undersigned purchaser hereby contracts for and orders of J. G. Cherry Company * * * one 300-gallon Jensen cream ripener, guaranteed first class, for which purchaser agrees to pay * * * the sum of $260, payable as follows: J. E. Larson
The complaint does not in terms ask to recover the purchase price of the ripener, but is for damages caused by the refusal of defendant to give his note as agreed. The answer claims a breach of warranty and a rescission on account thereof. The trial, which was to a jury, proceeded upon the theory that the burden of proof was upon plaintiff to show that the ripener was “first class,” as guaranteed; that plaintiff was entitled to recover if it sustained this burden, or if defendant did not return the ripener within a reasonable time after discovering that it was not as guaranteed; that otherwise defendant was entitled to a verdict. The instructions were along this line, and the jury returned a verdict for the defendant. This appeal is from an order denying a new trial.
The assignments of error are: (1) That the court erred in denying plaintiff’s motion to direct a verdict in its favor for the agreed price of the ripener; (2) that the court erred in denying plaintiff’s motion for a new trial. The second assignment of error raises no question for our decision, as the motion was made on several grounds, and the assignment does not specify the particular error relied on. 1 Dunnell, Minn. Dig. § 363. We therefore have not before us the question whether the verdict is sustained by the evidence, or the cor
The sole ground upon which it is claimed that plaintiff was entitled to a directed verdict is that defendant delayed an unreasonable time after discovery that the ripener did not fulfil the guaranty before rescinding the contract. As we have stated, this issue was submitted to the jury and decided in defendant’s favor. The question here is whether it should be held as a matter of law that defendant was not entitled to rescind. There are strong suggestions in the evidence that after experimenting with and using the ripener, and finding that it splashed and roiled the cream, defendant did not promptly disaffirm the contract, but sought rather to obtain a reduction in the price. However, considering that under the contract the title remained in plaintiff, and the fact that some time was spent in experimenting and endeavoring, with the assistance of a representative of plaintiff, to make the ripener do its work properly, and in trying to make a settlement with plaintiff, we are not prepared to say as a matter of law that defendant waived his right to rescind.
Order affirmed.