40 Mass. App. Ct. 937 | Mass. App. Ct. | 1996
Here, White incurred costs for allowance items which were roughly six times the estimates provided by the MBTA in its bid documents. The MBTA reimbursed White for all of the costs that White paid relating to the allowance items. White claimed that it was entitled to reimbursement for its overhead costs associated with the allowance items, because it did not expect that the actual costs White incurred for the allowance items would so greatly exceed the estimates furnished by the MBTA. The MBTA, however, relying on the language contained in the contract, refused to pay White for its overhead costs associated with administering the allowance item costs. White’s action against the MBTA followed, and subsequently, summary judgment was granted in favor of the MBTA.
On appeal, White claims that the granting of summary judgment was error because (1) the estimates by the MBTA of the allowance item costs were intended to be relied upon by the contractor; (2) the estimates constituted an implied warranty that they were “approximately” correct; (3) White was entitled to equitable relief under the doctrine of fraud at law or mutual mistake; and (4) the decision violated sound contract principles. We affirm the granting of summary judgment.
All of the contracts contained clear and unambiguous language that the contractor would not be entitled to reimbursement for overhead associated with the administration of allowance item costs. “It is . . . elementary that an unambiguous agreement must be enforced according to its terms.” Schwanbeck v. Federal-Mogul Corp., 412 Mass. 703, 706 (1992).
White’s argument that the estimates provided by the MBTA of allowance item costs were intended to be relied upon by the contractor is without merit. The clear terms of the contracts provided that the actual costs incurred by the contractor for the allowance items could exceed the estimates furnished by the MBTA for such work, and that the contractor would be reimbursed for all valid allowance item costs, even those beyond the MBTA’s estimates. Therefore, the contracts’ terms precluded any reliance by White on the furnished estimates. Further, such language also eliminated any possibility of an implied warranty that they were even approximately correct. See D. Federico Co. v. Commonwealth, 11 Mass. App. Ct. 248, 252 (1981). Compare Richardson Elec. Co. v. Peter Francese &
There is nothing in the record before the motion judge that supports White’s claim that it was entitled to equitable relief under the doctrines of fraud or mutual mistake. Further, any equitable relief is entirely inappropriate in this matter because the contracts unambiguously prohibit the contractor from recovering overhead costs associated with administration of allowance items.
Contrary to White’s argument, sound contract principles dictated the results here. The language, we repeat, was clear and unambiguous. White entered into the contracts “without compulsion and of [itsj own choice.” Crimmins & Pierce Co. v. Kidder Peabody Acceptance Corp., 282 Mass. 367, 378 (1933). We recognize that White had to pay a considerable amount of money in overhead in administering allowance item costs. But, when the language in a contract is as unambiguous as it was in the contracts under scrutiny here, enforcement of such contracts “will not be denied because of hardship to one of the parties.” Hiller v. Submarine Signal Co., 325 Mass. 546, 550 (1950).
Judgment affirmed.