304 Mass. 130 | Mass. | 1939
By contract dated December 14, 1936, the petitioner agreed to construct an earth dam and a reservoir, and to lay a pipe line for the respondent as an addition to its plant and equipment in the conduct of its business as a water company. The compensation to be paid the petitioner was set forth in a schedule of prices which, in nearly every instance, was based upon a unit measurement of quantity and, in a few instances, upon a lump sum for doing a particular portion of the work. The quantities shown in this schedule of prices were expressly stated to be only approximate, and, as to the items for which a unit price was stated, the compensation was to be computed in accordance with the actual amount of work done at the rate fixed for the unit of measurement. One of the principal portions of the work to be performed was the erection of an earth embankment for the dam. The contract provided that the petitioner should secure the material from borrow pits upon the respondent’s property. The estimated amount of material required was set forth in the contract as fifty-two thousand cubic yards and the compensation at the rate of forty cents a cubic yard. The final estimate of the engineer showed that only forty-two thousand four hundred twenty
Upon the completion of the contract, the petitioner, under date of September 17, 1937, wrote the respondent that the appearance of the borrow pits indicated that the material to be excavated would be gravel, but that it had encountered a very heavy excavation consisting in large percentage of boulders and rock'which had increased the cost of doing the work, and that “we maintain that such excess cost was caused by reason of the extreme divergence in the character of the material to be excavated from that which we were justifiably led to expect by reason of the data furnished and the appearance of the test pits indicated, together with the discrepancies in conditions along pipe line and in pay quantities.” The letter also directed the respondent’s attention to article 13 of the contract and requested that, in accordance with this article, an adjustment of prices be made, “in order that we may receive a fair and equitable reward for our labors.” The respondent did not make any changes in the contract prices. The petitioner, on October 8, 1937, submitted a bill for “additional costs beyond our control as described” in its letter of September 17, 1937. The bill set forth a claim in ten items amounting to $37,451.76. The first item was for “Additional cost constructing earth embankment due to conditions of borrow pits $18,564.22,” and another item was for “Added cost laying water pipe — conditions not shown $9,943.24.”
The contract in article 3 provided that the engineer was in the first instance to be the interpreter of the contract, and
The engineer refused to make any adjustment and the petitioner, purporting to act under article 16, presented its claim to a board of arbitration, which made an award of $18,575. The arbitrators refused to specify the items that were included in this award, but it is apparent from the items submitted to the board that the award included compensation under both or either of the claims arising from building the embankment and laying the pipe line. Upon petition this award was accepted and confirmed in the Superior Court and judgment was ordered to be entered for the petitioner. The respondent excepted to the denial of its motion to set aside the award and to the refusal to grant certain requests for rulings. The respondent urged before the board, before the Superior Court and before this court that the items upon which the award was made were not arbitrable under the contract or under the statute, G. L. (Ter, Ed.)
If the parties of their own accord and outside of court saw fit to submit to arbitration, without restriction or condition, the whole matter in dispute, including all questions of law and of fact, then the decision of the arbitrators upon the subject matter, in the absence of fraud, is binding and conclusive upon the parties, even though the arbitrators may have committed an error of law in reaching their conclusion. Jones v. Boston Mill Corp. 6 Pick. 148. Smith v. Boston & Maine Railroad, 16 Gray, 521. Rundell v. La Fleur, 6 Allen, 480. Norcross v. Wyman, 187 Mass. 25. Phaneuf v. Corey, 190 Mass. 237. Darrow v. Braman, 201 Mass. 469.
The validity of the award is challenged not merely on the ground that the.arbitrators have made an erroneous decision but upon the ground that they had no right to make any decision at all. In other words, the respondent’s contention is that the board was not empowered to hear and determine' the matter. That point is open. If authority was lacking, then the award is void. Mickles v. Thayer, 14 Allen, 114, 121. Boyden v. Lamb, 152 Mass. 416. Colombia v. Cauca Co. 190 U. S. 524. The Atlanten, 252 U. S. 313. Marchant v. Mead-Morrison Manuf. Co. 252 N. Y. 284. The authority of the arbitrators depends upon the terms of the agreement of submission. Towne v. Jaquith, 6 Mass. 46. Phippen v. Stickney, 3 Met. 384. Haven v. Winnisimmet Co. 11 Allen, 377. Washburn v. White, 197 Mass. 540. The burden was upon the petitioner to show that the contract provided for the settlement of this particular claim by arbitration. Norcross v. Wyman, 187 Mass. 25. Morgan v. Murdough, 216 Mass. 502. Marchant v. Mead-Morrison Manuf. Co. 252 N. Y. 284. Lehman v. Ostrovsky, 264 N. Y. 130.
The petitioner sought compensation in excess of that fixed by the contract because of changes in the contract prices, which it requested should be effected under article 13. Upon the failure of the respondent to make such changes,
An examination of the three articles shows that the engineer was required to make prompt and impartial decisions upon all the matters specified in article 3; that all of these decisions were to be final excepting only “as to the element of time and as to financial considerations involved,” which, in case the parties did not agree, were to be submitted to arbitration under article 16. This last article prescribed the procedure to be adopted in case of arbitration. It did not extend the field of arbitrable controversies. That was fixed by article 3. Both together by express reference comprised every provision of the contract
We are confirmed in this view not only by a comparison of these three articles but also by other provisions of the contract. The petitioner expressly agreed that it had informed itself fully in regard to all conditions pertaining to the place where the work was to be done; that it had obtained all information necessary to enable it fully and fairly to estimate the costs of the work; that it would at its own cost and expense provide and do everything necessary to perform fully the contract; that it would not make claim on account of any error in the soundings or borings; that it would bear and sustain all damages of whatever nature or cause resulting from the work; and that it would “bear all losses resulting to . . . [it], including but not
The arbitrators refused to specify the items contained in their award. We think it clear that they could not have arrived at their conclusion without including a part of the petitioner’s claim for additional compensation in building the embankment or in laying the water pipe. The award was for an indivisible lump sum and, as part of it was beyond the power of the arbitrators to make, the whole award must be set aside. The respondent’s motion to set aside the award should have been granted. In view of the conclusion we reach, it is not necessary to consider the requests for rulings. Barrows v. Capen, 11 Cush. 37. Brown v. Evans, 6 Allen, 333. Yeamans v. Yeamans, 99 Mass. 585. Camp v. Sessions, 105 Mass. 236. Kabatchnick v. Hoffman, 226 Mass. 221.
Exceptions sustained.