J.E.T. Development and other property owners sued a contractor, Gary Carpenter, and his firm, Dorsey Construction Co., Inc., for failure to complete the construction of a restaurant. The contractor cross-claimed against the owners to foreclose a labor and materialmen’s lien. After trial, the court denied relief on the owners’ complaint and entered judgment for the contractor. The owners have appealed. We affirm.
We are asked to decide three questions: (1) Did the trial court err in finding that the parties had entered into a “cost-plus” contract and that the total charge against the owners under the contract were reasonable? (2) Did the trial court err in limiting rebuttal testimony? (3) Was the contractor entitled to a statutory attorney fee on his successful cross-claim?
I
The parties did not put their contract in writing. The owners have contended that they orally agreed to a $90,000 “target figure” for construction of the basic restaurant structure, and that they entered into a separate “cost-plus” oral agreement for additions to the building. During construction, the contractor regularly billed and received progress payments from the owners. When the billings exceeded $90,000, the owners stopped paying and the contractor left the site after substantially completing the work.
Sharply conflicting evidence was presented at trial concerning the original understanding of the parties. The trial court found that the parties had agreed to a “cost plus 15%” contract. The court further found that the costs incurred by the contractor were reasonable, and that the total charge to the owners was reasonable.
We will not reverse a trial court’s findings of fact unless they are clearly erroneous. I.R.C.P. 52(a). The trial court’s findings of fact will not be disturbed on appeal when they are supported by substantial and competent, though conflicting, evidence. E.g., First Realty & Investment Co., Inc. v. Rubert,
The owners argue that even if there was a “cost-plus” contract, the contractor’s recovery should not have exceeded the reasonable value of his services. A contractor under a “cost-plus” contract must reasonably control his costs. Westendorf v. Dininny,
II
The owners contend that the trial court erred in denying their request to call the contractor as a rebuttal witness. The contractor had previously taken the stand twice, first as an adverse witness called by the owners during their case-in-chief, and
The initial examination of the contractor covered the bids received and the contractor’s billing process. The owners later cross-examined the contractor on the “cost-plus” contract. We have examined this testimony and the testimony of the other witnesses. It does not appear that the trial court deprived the owners of an opportunity to develop their side of the case regarding the existence or administration of the “cost-plus” contract. The permissible scope of rebuttal rests in the sound discretion of the trial court. Absent abuse of such discretion, the ruling of the trial court will be affirmed. Cargill v. Hancock,
The owners urge us to apply Loftin v. Morgenstern,
Ill
The owners argue that the trial court erred in awarding attorney fees and costs to the contractor under I.C. § 45-513. This statute relates to foreclosure of labor and materialmen’s liens. It mandates inclusion of a reasonable attorney fee in a judgment of foreclosure. The contractor’s cross-claim sought a determination of the amount due under the contract and foreclosure of a lien on the subject property to satisfy the obligation. Prior to trial, as an accommodation to the owners, the contractor stipulated to release of the lien upon condition that a sufficient sum of money would be held in a special account to pay any balance due the contractor. After trial, the court ruled that the relief sought by the cross-claim was “of the nature of a lien foreclosure.” The court also noted that, but for the stipulation, the contractor would be entitled to foreclose directly against the property. He concluded that the stipulation did not displace the contractor’s right to an attorney fee. We agree. The cross-claim, seeking to recover from the special account fund, was the functional equivalent of an action to foreclose the lien. We hold that I.C. § 45-513 was applicable to the cross-claim.
The owners next contend that the contractor should not recover a statutory attorney fee because the amount determined to be due under the contract was less than the amount claimed by the contractor in its notice of lien. However, the Idaho Supreme Court has held that a reasonable attorney fee is an incident of foreclosure of the lien. The lien itself is not rendered invalid merely because a claimant fails to prove the full amount of his original claim. Guyman v. Anderson,
The judgment of the district court is affirmed. Costs to respondents.
