Althоugh the parties were insistent at oral argument that the question they pose regarding the application of G. L. c. 30, § 39M, perplexes and concerns the construction industry and public bidding authorities, we think there is less to the problem than meets the eye. The failurе of the appellant, A. Amorello & Sons, Inc. (Amorello), as a bidder for a general contract to build a sewer interceрtor, to make a bid deposit “in an amount not less than five percent of the value of the *113 proposed, work, as estimated by the awarding authority'' 2 was a material deviation from bidding procedures which rеquired the city of Worcester to reject Amorello’s bid as nonresponsive. Undeniably, there was considerable confusion among bidders as to the proper amount of the bid deposit, but that confusion says more about assumptions which the bidders made than it dоes about any mystery inherent in the statute.
The city received thirteen bids from prospective general contractors for сonstruction of the Northwest Interceptor, Contract No. 18A (the Project). Methuen Construction Co., the lowest bidder, was permitted tо withdraw for the reason that it had made a clerical error, leaving Amorello, the defendant-appellant, as the low biddеr at $2,369,670. The runner up was J. D’Amico, Inc. (D’Amico), the plaintiff-appellee, at $2,395,995. Amorello furnished a bid deposit of $118,483.50, which was five perсent of the value of its bid, but lower by $71,516.50 than five percent of the value of the work as estimated by the city. The city’s estimate of the vаlue of the Project was $3,800,000, although the Dodge Report, a trade journal in the construction industry, had published an early city estimate (corrected in a later issue) of $2,000,000. According to Amorello, and the other parties do not dispute it, eight bidders submitted bid deposits that were five percent of their respective bids; five bidders posted bid deposits that were five percent of the estimatе cost of the Project by the city’s engineer.
Those who made the smaller bid deposits apparently were accustomed to bidding on public
building
projects, as to which the bidding process is governed by G. L. c. 149, §§ 44A through 441, inclusive, as appearing in St. 1980, c. 579, § 55. The amount of thе bid deposit called for in G. L. c. 149, § 44B(2), is “five percent of the value of the bid.” Bidding for public works projects, e.g., projects involving roads, bridges, or sewerage facilities, but not
buildings,
is governed byG. L. c. 30, § 39M. The distinction between public building
*114
projects and public works which are not buildings must be recognized to reconcile G. L. c. 30, § 39M, and G. L. c. 149, §§ 44A-44I, and has been acknowledged in the cases. See
James Constr. Co.
v.
Commissioner of Pub. Health,
All parties acknowledge that the Wоrcester Northwest Interceptor job was a nonbuilding public work governed by G. L. c. 30, § 39M. D’Amico, the second lowest bidder, demanded that the bid of Amorello be set aside as not in compliance with § 39M, and protested to the Department of Labor and Industries (DOLI). That agеncy has power to investigate if there has been a violation of § 39M and to institute proceedings in Superior Court to enjoin the award of a contract, if it finds noncompliance. See G. L. c. 149, § 44H, and
Department of Labor & Indus.
v.
Boston Water & Sewer Commn.,
However aрpealing an award to Amorello might be as a matter of practical sense, the judge was plainly right. The “minor or formal deviation” exception to compliance with competitive bidding statutes does not generally apply to failure by a bidder to comply with a statutory requirement. See
Phipps Prod. Corp.
v.
Massachusetts Bay Transp. Authy.,
As to the argument that Amorello’s deviation should be overlooked because the city inadequately informed (we do not so decide) bidders as to its engineer’s estimate of the cost of the work, the answer appears in
Phipps Prod. Corp.
v.
Massachusetts Bay Transp. Authy.,
Judgment affirmed.
Notes
The quoted material is from the third sentence of G. L. c. 30, § 39M(a), as appearing in St. 1976, c. 506, § 2. The italics have been added.
The Modem Continental case noted the establishment, by St. 1980, c. 579, of the division of Capital Planning and Operations to oversee certain planning and building prоjects within the Commonwealth. The same act of the Legislature reflected a comprehensive revision of G. L. c. 149, §§ 44A-44I. That 1980 legislation did nothing to eradicate the public building - public works distinction, one which presents a problem, when, as in Modem Continental, the public work includes buildings. The court’s opinion, at 834 n.8, discusses criteria suggested by the Division and the Attorney General for determining whether public works or public buildings prоcedures should apply.
DOLI's reasoning in this regard was that G. L. c. 149, § 44B(3), required the forfeiture from the deposit of only the amount between the bid withdrawn *115 and the next lowest bid. The difference between Amorello’s bid and D’Amico’s bid was $26,325, so, facially, Amorello’s bid deposit of $118,483.50 was ample. Whether § 44B(3) governs forfeiture of a bid deposit made under G. L. c. 30, § 39M, is not obvious. Section 39M has nothing to say on the subject.
An exception to the general rule has been countenanced in a narrow category of cases of apparent clerical oversight. See e.g.,
Chick’s Constr. Co.
v.
Wachusett Reg. High Sch. Dist. Comm.,
