J & A Bayly Construction Co. v. Village of Castleton-on-HudsonJ & A Bayly Construction Co. v. Village of Castleton-on-Hudson
Appeals (1) from an order of the Supreme Court (Ceresia Jr., J.), entered June 29, 1996 in Rensselaer County, which granted a motion by defendant Village of Castleton-on-Hudson for summary judgment dismissing the complaint against it, and (2) from an order of said court, entered March 26, 1997 in Rensselaer County, which denied plaintiffs motion for reconsideration.
In June 1990, defendant Village of Castleton-on-Hudson awarded a contract to plaintiff for the erection of á ground water storage tank that was to be constructed of steel reinforced concrete that could not contain fly ash and had to include a certain air entraining admixture. Construction commenced immediately; however, in October 1990 it was discovered that the concrete contained fly ash and had less air entrainment than required. The Village directed plaintiff to remove the storage tank and, in March 1991, issued a notice of default to plaintiff which it rescinded in May 1991 when plaintiff agreed to demolish and reconstruct the storage tank. Plaintiff advised the Village that the cost for this extra work would be determined in accordance with the contract’s provisions regarding the change order method of payment.
Plaintiff completed the extra work in early July and on July 23, 1991 submitted to the Village payment request No. 5, which did not include any charges for the extra work but was limited to the $52,443.07 balance due on the original contract. On August 9, 1991, Anna Bayly, plaintiffs president, executed an affidavit received from the Village that was similar to ones she had previously executed before receiving sequential contract payments wherein plaintiff agreed to shield the Village from any claims or liens arising out of the contract. After deducting $3,000 for work not completed, the Village issued a check to plaintiff for $49,443.07, which plaintiff negotiated. Thereafter,
Plaintiff then commenced this action seeking damages for the extra work it performed.
A release is a contract that, unless its language is ambiguous, must be interpreted to give effect to the intent of parties as indicated by the language they utilized (see, Loitta v Real Seal Constr.,
The contract provides that upon acceptance of all work, the engineer prepares a semifinal application for payment in an amount equal to 100% of the contract price less all previous payments and other deductions. The application is presented to the contractor who signs it and submits it to the Village for payment. It is undisputed that this procedure was not followed here nor was plaintiff advised by the Village that its payment request No. 5 was being treated as a semifinal payment application. The Village nevertheless argues that summary judgment in its favor was warranted since plaintiff knew or should have known that the submission of its payment request No. 5 would constitute a semifinal payment as it was in an amount equal to 100% of the contract price.
Plaintiff maintains that this inference cannot be drawn since
Plaintiff’s appeal from Supreme Court’s order denying its motion for reargument is dismissed since no appeal lies from such order (see, Spa Realty Assocs. v Springs Assocs.,
Ordered that the appeal from the order entered March 26, 1997 is dismissed. Ordered that the order entered June 29, 1996 is reversed, on the law, with costs, and motion denied.
Notes
The supplier of the concrete, defendant Clemente Latham Concrete Corporation, is not involved in this appeal.