349 Mass. 172 | Mass. | 1965
The plaintiff sought a declaration that its low subhid for the electrical work on the new city hall in the Government Center in Boston was valid and that the rejection of the bid by the Government Center Commission, as the awarding authority, in favor of a bid by Morris Vigoda, doing business as Norfolk Electric Co. (Norfolk), was erroneous. The judge in the Superior Court found that the plaintiff’s bid was incomplete, that the deviation was not minor, and that the awarding authority was justified in rejecting the plaintiff’s subbid. The evidence is reported.
The form for subbid furnished by the awarding authority had typed thereon the following: “B. This sub-bid includes addenda numbered 1, 2, 3, 4, 5, 6.” Three additional addenda had been issued as a basis for bidding; the plaintiff had received these additional items; it was incumbent upon the plaintiff, if it intended to make a bid for the entire electrical work, to insert the numbers of the additional addenda, or at least the two (8 and 9) that referred to such work. Through the plaintiff’s inadvertence these numbers were omitted from its subbid form.
The plaintiff’s bid was in the amount of $1,519,000; Norfolk’s bid, next lowest, was for $1,545,000. The plaintiff’s bid was included in the list of subbids mailed to the general bidders, and was used by the successful general bidder. Norfolk, however, protested to the awarding authority and to the Department of Labor and Industries of the Commonwealth. After a hearing, the department’s general counsel rendered a decision that the plaintiff’s subbid should be rejected.
The two omitted addenda that related to the electrical work contained over twenty references thereto. The testimony tended to show that the figured cost of doing the work without the addenda would be altered somewhat by the in-
General Laws c. 149, § 44H, as amended by St. 1963, c. 445, § 2, provides in part, “Every sub-bid . . . shall be for the complete work of the sub-trade as specified. . . . [The awarding authority] shall reject every sub-bid . . . which is on a form not completely filled in, or which is incomplete, conditional or obscure.”
The awarding authority was justified in rejecting the plaintiff’s subbid; it was not a submission that entitled the plaintiff to the award. Grande & Son, Inc. v. School Housing Comm. of No. Reading, 334 Mass. 252, 256. Chick’s Constr. Co. Inc. v. Wachusett Regional High Sch. Dist. Sch. Comm. 343 Mass. 38, 41. Fred C. McClean Heating Supplies, Inc. v. Westfield Trade High Sch. Bldg. Comm. of Westfield, 345 Mass. 267, 272. Builders Realty Corp. v. Newton, 348 Mass. 64, 67. The issue is not whether the deficiencies were of such a nature that the awarding authority would have been justified in overlooking them. Loranger v. Martha’s Vineyard Regional High Sch. Dist. Sch. Comm. 338 Mass. 450, 456. John D. Ahern Co. Inc. v. Acton-Boxborough Regional Sch. Dist. 340 Mass. 355, 357, 358. Fred C. McClean Heating Supplies, Inc. v. School Bldg. Comm. of Springfield, 341 Mass. 322. Chick’s Constr. Co. Inc. case, supra. We need not decide whether
Decree affirmed,.
See St. 1963, c. 445, § 2, amending (G. L. c. 149, § 44H, to permit rejection after the two day period specified.
The only sure monetary difference appears to be that admitted by the plaintiff, that is: change in size of an exhaust silencer, add $40; plywood backboard changed to steel, add $228; eliminate two spray pumps, deduct $40. A plaintiff’s witness, who had testified that none of the changes was material, testified on cross-examination as to the possibility of additional cost as a result of a provision in addendum 8 which had made specific the type of clock face to be used. The original specifications had listed this as a decision for the architect, and conceivably an overall bid with this item open would have varied from such a bid with this item certain. The witness accepted as "possible” the examiner’s suggestion that the variation might be as much as $20 a clock face. There was testimony that there were 178 clocks. Norfolk and the Commission also rely on the testimony that there would have been a saving of over $10,000 to the subcontractor had the architect permitted the use of the substitute material which the plaintiff had sought to use and had inquired about, rather than ruling against the use of such material in addendum No. 8. The argument is that the plaintiff’s omission of the reference to addendum 8 suggests the possibility of an intent to be a subcontractor only if the ambiguity of the specifications, apart from addendum 8, remained in the contract. The futility of such a course by an earnest bidder is, of course, apparent.