121 P. 1061 | Mont. | 1912
delivered the opinion of the court. In his original complaint, the plaintiff attempted to state three separate causes of. action, the first of which alleged that on or about the nineteenth day of June, 1908, he entered into an agreement with the defendants, whereby they leased and let to him a certain piece of ground under and within the Lexington quartz lode mining claim, upon the following terms: He was to clean out an old drift, retimber the same, extend it twenty-five feet or more, if necessary, and cut an upraise to a point where ore would be encountered. After striking ore, he was to have all he could take out for the succeeding thirty days. It was further agreed “that at the termination of thirty days after plaintiff had cut the ore, if defendants desired to discontinue the lease they could do so by paying him day’s wages for the work already performed by him.” He alleged that he began work on the nineteenth day of June, 1908, cleaned out and retimbered the drift, and, after running an upraise for about fifteen feet, eut the lead on August 7, 1908, and encountered ore; up to the thirteenth day of August, 1908, he knocked down forty tons of ore, whereupon the defendants, without cause, ousted him from the premises, refused to allow‘d him to go on with the work, and “kept and shipped all the ore, and refused to settle with him for the same. ’ ’ He demanded general damages in the sum of $1,000 for breach of the agreement of the lease. The second cause of action was based upon the allegation “that, by reason of the acts of the defendants
At the trial, before the court sitting with a jury, the plaintiff testified that Mr. Frank, who was in charge of the mine for the defendants, told him orally that if he would do the work, as above indicated, he could have the ore, after striking the same, for thirty days without royalty. He said: “Mr. Frank told me, ‘Now, if you strike that ore, we will give you, after doing this work, thirty days clear of royalty for doing this work.’ I was never allowed to take that ore out there. I never got any of the benefits of that ore. Any point I struck ore, I had thirty days to take it out. ’ ’ After testifying, in effect, that Mr. Frank ordered him out of the mine, and that he had performed all the dead work mentioned in the contract, he continued: “The work and labor we performed in cleaning out the drift, retimbering the same, extending the drift and cutting the upraise, was reasonably worth $448. I went to Mr. Frank once and asked him, ‘What are you going to do about it?’ and he said, ‘Nothing.’ I said that I had forty or forty-five tons of ore there, and, ‘What are you going to do about it?’ and he said, ‘What is your costs for doing the work?’ and I told him $448. ‘Well,’ he said, ‘I’ll pay you wages for that work done, and I want to keep that ore,’ and I said: ‘No, you don’t keep that ore.’ The arrangement we had there was that he was to pay me day’s wages, provided my lease was canceled after thirty days; and I told him the wages was $448.” In cross-examination of the plaintiff, the defendants produced a cheek for $120.91, the net value of the ore retained by them; but Ivey declared that the check had not been tendered to him.
When plaintiff rested his case, the defendants moved for a nonsuit. Thereupon plaintiff asked and was granted leave to file
1. It is contended that the so-called lease, not being in writing, was void under the statute of frauds. This position is taken on the authority of Clark v. Wall, 32 Mont. 219, 79 Pac. 1052, and the point seems to be conceded by counsel for the respondent. But it is not necessary to determine whether or not the facts in this case bring it within the rule laid down in Clark v. Wall. After experiencing some difficulty in establishing a cause of action, other than that relating to the forty tons of ore, the plaintiff practically abandoned the cause of action for breach of the so-called lease agreement in itself by testifying that Mr. Frank reserved the right to terminate the agreement by paying day’s wages for the dead work. The court is presumed to have correctly charged the jury that plaintiff could not recover for failure of the defendants to allow him to continue the work of getting
2. It is contended that the amended complaint contains three
3. But it is said that the two last causes of action are improperly joined, for the reason that the second claim, or cause of action, is founded in tort, and the third is founded in contract. It was
The judgment and order are affirmed.
Affirmed.