171 N.E. 757 | NY | 1930
The plaintiff's consolidated mortgage is subordinate to the lien of the defendant Hurwitz for advances made pursuant to the building loan agreement and mortgage for $54,000, executed and filed before the plaintiff's mortgage. The building loan agreement provides that the first advance of $8,640 shall be made at the time of the execution of the agreement. Other advances were to become due at later stages of the progress of the work, but the lender might at his option make any advances before they were due. At the time of the execution of the instruments the lender delivered checks to the order of the borrower aggregating the sum of $8,900. The largest check, for the sum of $6,840, was immediately indorsed and delivered to the lender and retained by the lender as a bonus for the agreement to make the building loan.
The lender stipulated for the payment of that bonus. The borrower agreed, as it had a right to do. Part of the moneys secured by the mortgage were used for the payment of the bonus. Nothing in the building loan agreement or mortgage forbade, expressly or by implication, such use of the moneys advanced. The lien for advances made in accordance with its terms is superior to the lien of a subsequent mortgagee, who takes with notice of the prior mortgage and building loan agreement. (Hyman v.Hauff,
The Appellate Division erroneously found that an additional sum of $3,500 was also advanced pursuant to the mortgage. That sum was never advanced pursuant to the mortgage. It had been loaned by Hurwitz long before the mortgage was executed. When the mortgage was thereafter assigned to Hurwitz it did not cover any moneys previously loaned by the assignee, and the owner of the premises could not at that time agree to extend its protection to cover a prior unsecured loan.
The judgment should be modified in accordance with this opinion and as modified affirmed, without costs.
CARDOZO, Ch. J., POUND, CRANE, KELLOGG, O'BRIEN and HUBBS, JJ., concur.
Judgment accordingly.