Interstate Natural Gas Ass'n of America v. Federal Energy Regulatory CommissionInterstate Natural Gas Ass'n of America v. Federal Energy Regulatory Commission
Opinion for the Court filed by Circuit Judge BROWN.
The Federal Energy Regulatory Commission (“FERC” or “the Commission”) issued an Accounting Order, instructing natural gas pipeline companies to expense certain costs associated with the Pipeline Safety Improvement Act of 2002, Pub.L. No. 107-855, 116 Stat. 2985 (“PSIA”). After FERC denied a request for rehearing, the Interstate Natural Gas Association of America (“INGAA”) petitioned for review in this court. Finding FERC’s explanation for its Accounting Order reasonable and its responses to INGAA’s comments sufficient, we deny the petition.
I
Section 14 of PSIA, 49 U.S.C. § 60109(c)-(d), requires each operator of natural gas pipelines to adopt and implement a written integrity management program (“IMP”) to monitor and reduce the risks associated with pipeline segments located in areas of high population density (“High Consequence Areas,” or “HCAs”). Each IMP includes a testing regime with two components. First, companies are to conduct baseline integrity assessments of their HCA segments by December 2012. Id. § 60109(c)(3)(A). Second, going forward, they are to retest each HCA segment at least once every seven years unless granted a waiver by the Secretary of Transportation. Id. § 60109(c)(3)(B), (5).
Under the Natural Gas Act, FERC has jurisdiction to regulate the transportation and sale of natural gas in interstate commerce. 15 U.S.C. § 717(a)-(b). This includes the power to issue rules and regulations governing pipeline companies’ accounting practices. Id. §§ 717g(a), 717o. Pursuant to that authority, FERC issued a Notice of Proposed Accounting Release (“PAR”) describing its planned accounting rules for PSIA testing and inviting comments. 69 Fed.Reg. 67,727 (Nov. 5, 2004). Under the proposal, testing costs under PSIA would be expensed, not capitalized.
The PAR acknowledged FERC had occasionally permitted capitalization of testing costs in the past, citing in particular Northwest Pipeline Corp., Docket No. AC94-149-000 (FERC Apr. 30, 1996) (“NPC”). FERC distinguished NPC on the ground that NPC’s testing costs were incurred “in connection with [a] major pipeline rehabilitation project! ] involving significant replacements and modifications of facilities” that “extended the overall pipeline system’s useful life and serviceability,” while PSIA required testing as part of “on-going maintenance programs.”
INGAA advocated capitalization of testing costs in comments submitted in response to the PAR. FERC subsequently issued an Accounting Order, 111 F.E.R.C. ¶ 61,501 (June 30, 2005), responding to comments and establishing definitive IMP accounting rules for pipeline companies. The Order repeated FERC’s earlier instruction to expense PSIA testing costs and also set accounting rules for other IMP obligations. These rules were to take effect on January 1, 2006, with no restrictions placed on the accounting treatment of earlier expenditures.
The Accounting Order instructed pipeline companies to expense the costs of writing IMP implementation plans, identi-
II
To establish standing as an association, INGAA must show (1) at least one of its members has standing in its own right, (2)the interests INGAA seeks to protect are germane to its purpose, and (3) neither the claim asserted nor the relief requested requires the participation of an individual INGAA member in the suit.
Am. Library Ass’n v. FCC,
Individual pipeline companies (which constitute INGAA’s membership) are harmed by the Accounting Order’s ex-pensing requirements in at least two ways. First, expensing these costs rather than capitalizing them reduces the companies’ “rate bases,” thereby decreasing their maximum allowable revenues.
See Williston Basin Interstate Pipeline Co. v. FERC,
We review FERC’s actions under 15 U.S.C. § 717r(b).
See CNG Transmission Corp. v. FERC,
On the merits, INGAA suggests two grounds on which we should set aside the Accounting Order. We address these in turn.
A
First, INGAA contends FERC deviated from its precedent in
NPC
without providing a reasoned explanation.
See Motor Vehicle Mfrs. Ass’n of the U.S. v. State Farm Mut. Auto. Ins. Co.,
FERC interpreted
NPC
as permitting capitalization of testing that (1) “was done in connection with major pipeline rehabilitation projects involving significant replacements and modifications of facilities”; (2) “extended the overall pipeline system’s useful life and serviceability” or otherwise benefited future accounting periods; and (3) was not “associated with any on-going maintenance programs.” This is a reasonable reading of NPC’s terse ruling, and we defer to it.
See Williams Gas Processing,
B
Second, INGAA argues FERC failed to respond reasonably to its comments on the PAR and the Accounting Order. When FERC issues accounting rules pursuant to 15 U.S.C. §§ 717g and 717o, it must abide by the Administrative Procedure Act (“APA”) strictures at 5 U.S.C. § 553.
Mobil Oil Corp. v. FPC,
Assuming without deciding that FERC had the same obligation to respond to IN-GAA’s arguments regarding the Accounting Order as it had with respect to comments it received on the original PAR, we find FERC responded sufficiently to all of INGAA’s arguments from its petition for rehearing. See 15 U.S.C. § 717r(b) (limiting review to arguments raised on rehearing).
INGAA generally complains the Commission ignored its own regulations and departed from precedent without explanation. Examined closely, however, IN-GAA’s complaint is more accurately that the Commission’s interpretation of both regulations and precedent differed from INGAA’s. For example, INGAA argued Abstract No. 89-13 from the Emerging Issues Task Force of the Financial Accounting Standards Board (“EITF 89-13”) provided the proper framework for setting IMP accounting rules. But, in FERC’s view, EITF 90-8, Capitalization of Costs to Treat Environmental Contamination, more fully described which costs should be capitalized and which expensed. See Rehearing Order ¶ 14. Contrary to INGAA’s analysis, FERC determined that under EITF 90-8, baseline assessment costs should be expensed, as they would not “increase or extend the life, capacity, safety, or efficiency of a pipeline beyond its original construction or acquisition state.” Id.; see EITF 90-8 at 2. While such baseline assessments could arguably increase a pipeline’s certified capacity, it was reasonable for FERC to read EITF 90-8 to require increases in actual physical capacity.
FERC likewise rejected INGAA’s attempted analogy between PSIA testing costs and prepaid expenses, as the testing costs secured no future service or resource. Rehearing Order ¶ 10. Equally appropriate was FERC’s response to IN-GAA’s argument that costs required to avoid loss of an asset ought to be capitalized, a theory FERC noted would require capitalization of even ordinary maintenance costs.
Id.
And while INGAA’s assertion that PSIA expenses should be rec
INGAA argued the initial costs of constructing databases and composing IMP implementation plans would be incurred only once and ought therefore to be capitalized. However, by statute such projects were to be complete by January 1, 2006, and the Accounting Order did not apply to expenditures prior to that date. Thus, this comment was not “significant,” and FERC had no duty to respond to it.
See Portland Cement Ass’n,
INGAA also maintained NPC controlled. As described above, FERC reasonably distinguished the rule from NPC. See Accounting Order ¶¶ 21-22.
INGAA noted the PSIA regulations were contained in Subpart O of 49 C.F.R. Part 192 (§§ 192.901 et seq.), while pre-PSIA maintenance requirements appeared in Subpart M (§§ 192.701 et seq.). From this, INGAA inferred the new regulations could not mandate maintenance expenditures, contrary to FERC’s reasoning in the Accounting Order. But we are aware of no authority making Subpart M the sole repository for maintenance regulations in Part 192, and as FERC reasonably argued, “an increase in the required level of maintenance does not change the fact that the work remains a maintenance activity,” Rehearing Order ¶ 12. We thus deem FERC’s response sufficient.
Finally, INGAA argued early PSIA expenditures served to produce a “knowledge base” and improve “the original Integrity Plan 'asset,’ ” so they should be capitalized. FERC again rejected INGAA’s proposal, noting “[t]he activities incurred during the baseline period[ ] are not materially different, if different at all, from the same category of costs that INGAA does not object to expensing after the baseline period.” Rehearing Order ¶ 13. In essence, IN-GAA wanted the first iteration of certain periodic expenditures to be deemed nonrecurring precisely because they were first; FERC’s response rejecting this theory was reasonable.
■ III
As described above, FERC provided a reasoned explanation for its decision not to treat NPC as governing, and it responded sufficiently to all of INGAA’s arguments. Therefore, INGAA’s petition for review is
Denied.