357 Mass. 282 | Mass. | 1970
The plaintiff (I T & T), a Maryland corporation, by corporate merger succeeded to the assets, claims and choses in action of Nesbitt, Inc. (Nesbitt), a Delaware corporation, engaged in the business of supplying ventilating, heating and plumbing materials. Under G, L. c. 149, § 29, I T & T seeks to enforce Nesbitt’s right to payment for materials furnished by Nesbitt for use in the construction of an addition to a public school in the town of Holliston (the town).
The general contractor for the construction of the school addition was Donatelli Building Company, Inc. (Donatelli), a Rhode Island corporation. The surety on Donatelli’s bond to the town was the defendant Hartford Accident and Indemnity Company (Indemnity). Kahn Heating Corporation (Kahn), a Massachusetts corporation, subcontracted with Donatelli to do the heating and ventilating work at the school. Nesbitt supplied certain materials required by Kahn in the performance of its subcontract with Donatelli.
Kahn is not a party to the suit. No relief is sought against the town.
On April 9, 1964, Kahn was adjudicated bankrupt. On May 18, 1964, Nesbitt filed with the town clerk a sworn statement of its claim for $8,353.10 for heating and ventilating equipment supplied to Kahn for the school from October 7, 1963, to May 7, 1964.
No payment whatever has been made to Nesbitt for the materials furnished at the school job.
The case was referred to a master, who, subject to some vague reservations of law, found for Indemnity and Donatelli. By interlocutory decrees the plaintiff’s motion to recommit was denied, its exceptions to the report were overruled, and the report was confirmed. A final decree was entered dismissing the plaintiff’s bill. From all of the decrees the plaintiff has appealed.
The master correctly stated “To obtain the benefit of a sworn statement filed within ‘ninety days after the claimant ceases to . . . furnish . . . materials, appliances . . . as aforesaid’ the plaintiff must rely upon the March 13, 1964 shipment,” since the last previous shipment was clearly more than ninety days before the filing of the sworn statement.
The master found “Nesbitt made all shipments in good faith and with no express intention to extend the time prescribed by G. L. c. 149, § 29, for filing its lien.”
He made an alternate finding, based in part on a stipula
We feel obliged to comment on the master’s report. Notwithstanding the fact that on its face the report conforms to Rule 86B of the Superior Court (1954) in that it has captions reading “Subsidiary Findings of Fact” and “General Findings of Fact” it lacks the coherence and ■unity which are essential to a statement of facts upon which a judgment is to be made. It has been necessary for us to cull, draw together and correlate facts scattered among eighty-five numbered paragraphs. This kind of burden should not fall upon a reviewing court, whether it be the Superior Court or this court. We have criticized this kind of report before. State Line Contractors, Inc. v. Commonwealth, 356 Mass. 306, 324. The present effort represents a new high in the flourishing art of expository confusion.
The master’s finding in favor of Indemnity was based on his conclusion that the claim filed by Nesbitt on May 18, 1964, under G. L. c. 149, § 29, was ineffective. It was ineffective, says the master, because it was late; and it was late because the shipment by Nesbitt to Kahn on March 13, 1964, was a nullity under G. L. c. 149, § 29.
We have studied the report and shall state the result as to facts found, issues presented and the rationale apparently controlling the conclusions of the master.
The master’s report shows that the shipment of March 13, 1964, was a single shipment. Although the report does not expressly so state, we think it is desirable for purposes of presentation and discussion to divide the shipment into three components. We must treat each of the three components separately.
1. The first component consisted of items shipped to Kahn as the result of a change order in Donatelli’s original contract with the town. There is no question about the authenticity of the change order. The town’s architect directed Donatelli to furnish and install a two foot section
2. The second component of the March 13,1964, shipment consisted of two so called W.O.L. wall sleeves. These items the master found had been called for by the original purchase order of July, 1963, and should have been included by Nesbitt in the October shipments of that year. By inadvertence, however, these items were not included among the more than 650 items in the October, 1963, shipments, although the charge for them was included in the October invoices. The value of the two W.O.L. wall sleeves was $6. To make up for the inadvertent omission in October 1963, Nesbitt included them at Kahn’s request in the March 13, 1964, shipment. No charge was made by Nesbitt for these two W.O.L. wall sleeves. The master fomid that the original Kahn-Donatelli agreement called for only two Nesbitt W.O.L. sleeves in the new building. He found that the job, as completed on May 22, 1964, had two Nesbitt W.O.L. sleeves incorporated in it. He declined to find, however, that the two Nesbitt W.O.L. sleeves actually used were those shipped on March 13, 1964, “[s]ince there is a possibility that the sleeves, so seen on the job were sleeves which had been in the old school area.”
3. The third component of the March 13, 1964, shipment
"[W]here the master in his report sets forth all of the subsidiary findings upon which he bases an ultimate conclusion, it is the duty of the trial court, and of this court, to draw its own inferences from those findings.” Corrigan v. O’Brien, 353 Mass. 341, 346. McOuatt v. McOuatt, 320 Mass. 410, 411. Samia v. Central Oil Co. of Worcester, 339 Mass. 101, 122. See LiDonni, Inc. v. Hart, 355 Mass. 580, 583.
It seems to us that the master’s conclusions and the method used to reach them, as shown by the words used in his report, demonstrate, at least as to components 1 and 2, that he imposed upon the plaintiff a severe and unduly rigorous standard of proof in its effort to show compliance with G. L. c. 149, § 29. He seems to have considered it his duty to deny to the plaintiff the benefit of a reasonable inference from proved facts unless the inference is a required one. For example the master said as to component 2 £<I cannot find who actually installed these sleeves or they were, in fact, the two (2) wall sleeves shipped on March 13, 1964. Since there is a possibility that the sleeves, so seen on the job were sleeves which had been in the old school area and which were relocated, I cannot infer from the existence of Nesbitt wall sleeves at the school, that they were those furnished by Nesbitt on March 13, 1964” (emphasis supplied).
The master likewise seems to have required the plaintiff to prove that Kahn and no one else installed the materials
We think it is plain on the face of the master’s report that he imposed upon the plaintiff a burden of proof that is greater than the law requires and that he applied rules of evidence which precluded consideration of material facts and thus unduly restricted his own field of deliberation as the trier of fact. For these reasons recommitment of the report would be required.
It is our further view, however, that recommitment is unnecessary because the master’s conclusion on the third component of the shipment is plainly wrong and requires a different decree.
The facts found are: The items of component 3 were not on the job site when Kahn wanted to use them. Kahn reported to Nesbitt that they were not included in the October, 1963, shipments. Nesbitt shipped these items (with components 1 and 2) to Kahn on March 13, 1964, without charge. The job was completed by May 22, 1964.
With respect to component 3, unlike components 1 and 2, the master raises no doubt that the items were used in the building. Indeed the items of component 3 must have been used in the building since on March 13, 1964, they were needed to do the job, they became available on that day to do the job, and before May 22, 1964, the job was done. The master’s finding that the shipment by Nesbitt was made in good faith must be taken to include the concept that the shipment was in fulfilment of the contract with Kahn and with the expectation that payment for the entire job would in due course be forthcoming. On the foregoing facts Nesbitt had done all that was needed to be done to perfect its lien under G. L. c. 149, § 29.
It follows from the facts found that Nesbitt, as matter of law, has complied with the statutory requirements of G. L. c. 149, § 29, and that the plaintiff as its legal successor is entitled to recover from Indemnity, as stipulated, the sum of $8,280 with interest from May 18, 1964. The final decree
So ordered.
The figure $8,353.10 is made up of the $8,280 for the October, 1963, shipments plus the $23.60 for a component of the March 13, 1964, shipment plus $49.50 for special cabinets and grilles shipped on May 7, 1964. At the hearing before the master Nesbitt withdrew its claim to the $49.50 and it plays no part in the case.