INTERNATIONAL RISK CONTROL, LLC, Aрpellant, v. SEASCAPE OWNERS ASSOCIATION, INC., Appellee.
No. 14-12-00016-CV.
Court of Appeals of Texas, Houston (14th Dist.).
Feb. 14, 2013.
Cris A. Rasco, Texas City, George William Vie, III, Galveston, for Appellee.
Panel consists of Chief Justice HEDGES and Justices BROWN and BUSBY.
SUBSTITUTE OPINION
ADELE HEDGES, Chief Justice.
We issued an opinion in this case on January 8, 2013, reversing the trial court’s summary judgment and remanding for additional proceedings. Appellee subsequently filed a motion for rehearing. Without changing our previous disposition, we deny the motion for rehearing, withdraw оur earlier opinion, and issue this substitute opinion in its place.
BACKGROUND
Seascape Owners Association, Inc. (“Seascape”) is the managing corporation of a large condominium complex on Galveston Island. In September 2008, following the torrent of Hurricane Ike, many units on the property sustained extensive damage from water and wind. Seascape tried to assess the damage in the aftermath of the storm and collect the sums that it believed were due under its various insurance policies. When Seascape encountered difficulties in the collection process, it engaged the services of International Risk Control, LLC (“IRC”), a firm of licensed public insurance adjusters. The parties executed a written contract, providing for IRC’s assistance in the preparatiоn and presentation of Seascape’s multiple insurance claims. In return for these services, Seascape agreed to pay IRC an eight percent commission on any amounts received or collected in settlement.
Pursuant to their agreement, IRC assessed the damaged properties, estimated the costs of repairs, and presented several insurance clаims on Seascape’s behalf. The claims were only partially paid by Seascape’s carrier, the Texas Windstorm Insurance Association (“TWIA”). Of the amounts that were received, Seascape timely paid IRC its bargained-for commission. Seascape’s remaining share was still too low, however, for it to cover the projected costs of reconstruction. Seascape decided that more claims needed to be pursued, so it retained a local law firm in the hopes of maximizing any additional recovery.
After severing ties with IRC, Seascape filed an original petition against TWIA, asserting numerous causes of action, including fraud, breach of contract, and violations of the DTPA and Texas Insurance Code. TWIA agreed to settle the dispute outside of court for a substantial sum of money. Believing that the settlement was achieved as a result of its own work product, IRC demanded its fair share of the proceeds. IRC addressed a letter to TWIA requesting to be named as an additional payee on any amounts tendered in payment of Seascape’s insurance claims. IRC also threatened to hold TWIA liable if it failed to include IRC on any payments to Seascape.
Hoping to end this dispute, Seascape filed an original petition against IRC, seeking declaratory relief that IRC was not entitled to any additional compensation under the contract. IRC filed a counterclaim, asserting damages for breach of contract. Seascape moved for summary judgment, arguing on three separate grounds that the contract was unenforceable because it failed to comply with statutory requirements, because it illegally provided for the unauthorized practice of law, and because it violated public policy. Seascape also argued that IRC was not entitled to any share of the settlеment proceeds because, by law, the scope of IRC’s commission could not extend to the types of claims covered by the settlement.
The trial court granted summary judgment in Seascape’s favor. In its final modified order, the court concluded that the contract between the parties was unenforceable, agreeing with the first and third bases of Seascape’s motion, but exprеssing no opinion on the contract’s illegality. The court ordered that IRC take nothing on its counterclaims, concluding that the settlement proceeds did not constitute a “claim” for which it could legally recover. The court also ordered IRC to pay Seascape reasonable attorney’s fees. IRC timely filed an appeal, challenging every basis for summary judgment that was argued in Seascape’s motion, including the award of attorney’s fees.
SUMMARY JUDGMENT
Our standard of review is well-established. We review a trial court’s summary judgment de novo. Ferguson v. Bldg. Materials Corp. of Am., 295 S.W.3d 642, 644 (Tex. 2009) (per curiam); Tex. Mun. Power Agency v. Pub. Util. Comm’n of Tex., 253 S.W.3d 184, 192 (Tex. 2007). With a traditional motion for summary judgment, the movant has the burden of showing that there is no genuine issue of material fact and that she is entitled to judgment as a matter of law.
With these principles in mind, we now turn to the theories that Seascape presented below.
A. Statutory Noncompliance
Seascape’s first argument is that the contract is unenforceable because it fails to comply with
The contract here was negotiated by Barry McGonigal, the president of IRC. McGonigal represented that he was a public insurance adjuster licensed in the state of Texas. Thе contract denotes his name and business address, but it does not list his license number, as required by the regulations. Seascape contends that, without the license number, the contract is invalid and unenforceable.
Seascape has not cited to any direct authority for its proposition. No case law was provided in its motion for summary judgment, and in its appellate brief, Seascape hаs only discussed authority stating that a court must give effect to the plain language of a statute. This authority merely provides a rule of construction, however. It offers little guidance when deciding the enforceability of a contract.
We are guided instead by the rule described in American National Insurance Co. v. Tabor, 111 Tex. 155, 230 S.W. 397 (1921). In that case, the supreme court held that, unless a contract is declared by law to be void or unenforceable, a court should not refuse to enforce a contract simply because it is in contravention of a statute. See id. at 160, 230 S.W. at 399; accord Borger v. Brand, 131 Tex. 614, 619, 118 S.W.2d 303, 306 (1938); Davis v. Hendrick Autoguard, Inc., 294 S.W.3d 835, 840 (Tex. App.—Dallas 2009, no pet.); New Boston Gen. Hosp., Inc. v. Tex. Workforce Comm’n, 47 S.W.3d 34, 40 (Tex. App.—Texarkana 2001, no pet.). The court explained that if the legislature has expressly provided that other consequences may arise from violation of the statute, a reviewing court should reasonably infer that those consequences were adjudged to be adequate to secure the statute’s observance, and that only those rеmedies should be applied. Tabor, 111 Tex. at 160, 230 S.W. at 399.
Following Tabor, we note first that there is no legal provision, either statutory or regulatory, declaring a contract void or unenforceable because the contract fails to adhere to the requirements of
The correctness of our approach is confirmed by
Seascape has not argued that its contract should be avoided because McGonigal was not licensed. Indeed, in its own motion for summary judgment, Seascape acknowledged that “McGonigal is a licensed Public Adjuster under
Seascape’s effort to void its contract does not comport with our precedent. Though the contract may be in contravention of the regulations, its technical deficiency is one that should be addressed administratively, rather than by avoidanсe. Seascape has not shown its entitlement to judgment as a matter of law on the basis of regulatory noncompliance.
B. Illegality and Public Policy
The trial court did not address Seascape’s argument regarding the legality of the contract, but because the argument is so closely tied to Seascape’s contention that the contract violates public policy, we consider them both together. Seascape argued in its motion that the contract was illegal, and therefore unenforceable, because its performance required IRC to engage in the unauthorized practice of law, which is prohibited by both statute and regulation.
The legislature has defined the “practice of law” to mean “the preparation of a pleading or other document incident to an action or special proceeding or the management of the action or proceeding on behalf of a client before a judge in court as well as a service rendered out of court.”
Seascape contends that this example applies because the contract assigned IRC an eight percent commission on any amount received from Seascape’s insurancе claims. But a fee arrangement is common to many adjuster contracts, and even contemplated by statute.
Seascape has also suggested that the contract is illegal on its face because its performance required IRC to engage in the unauthorized practice of law. Based on a plain reading of the contract, we cannot say that it does. The contract is short, only two pages in length, and worded simply. In addition to several boilerplate provisions, it consists of just the following clauses:
Seascape Condominium Association [sic] (hereinafter “insured”) hereby engages International Risk Control, LLC (hereinafter “IRC”) to assist with the preparation and presentation of their insurance claims arising from loss аnd damages occurring on or about: September 13th and arising from Hurricane Ike (hereinafter “Claim”).
Insured agrees to pay IRC for its claim services and hereby assigns eight (8%) percent of the amount received for Claim. The amount of IRC fee to insured can never exceed the eight percent of the amount of the Claim settlement.
The contract essentially contemplates that IRC would provide estimates of the property damage and present the necessary paperwork and data to Seascape’s insurance company. This court has previously held that such activities do not constitute the practice of law. See Unauthorized Practice of Law Comm. v. Jansen, 816 S.W.2d 813, 816 (Tex. App.—Houston [14th Dist.] 1991, writ denied). As we explained in Jansen, these procedures are required in every adjuster contract before the insured can colleсt on an insurance policy. Id. IRC could not have engaged in the unauthorized practice of law by agreeing to perform the very duties that are endorsed by the Texas Insurance Code.
Seascape also observes that even if a contract is not illegal on its face, it may still be unenforceable if facts showing its illegality are presented to the trial court. See Lewis v. Davis, 145 Tex. 468, 472, 199 S.W.2d 146, 148-49 (1947) (“A contract to do a thing which cannot be performed without a violation of the law is void. But where the illegality does not appear on the face of the contract it will not be held void unless the facts showing its illegality
IRC disputed that any of these activities was illegal. In his affidavit, McGonigal attested that he was not a lawyer and that all of the advice he gave was based solely on his skill and experience as a public insurance adjuster. McGonigal also attested that “[a]ny demand letters sent by Seascape [were] the product of past and present attorney involvement, and are activities in which IRC does not engage.” This evidence raises a fact issue. Accordingly, we cannot conclude as a matter of law that the contract was illegal, against public policy, or otherwise unenforceable.
C. Not a Claim
Seascape’s final argument is that IRC is barred as a matter of law from receiving any share of the settlement proceeds. Seascape essentially contends that IRC is limited in the types of “claims” from which it can recover, and the settlement is not one of them.
Seascape cites to
To prevail on this argument that IRC was not entitled to any share of the settlement proceeds, Seascape had to establish as a matter of law that the proceeds exclusively represented damages from its legal causes of action. Seascape has not satisfied this burden.
Attached to Seascape’s motion for summary judgment is the final settlement agreement negotiated between Seascape and TWIA. The agreement makes clear that the settlement sum represents a release of both Seascape’s insurance claims and its legal causes of action. The agreement recites extensive facts about Hurricane Ike and the ensuing efforts by Seascape to collect on its insurance policy. It also reflects that policy disputes arose, and that Seascape pursued multiple causes of action when its claim was not paid. TWIA agreed to pay the settlement sum not because it was admitting its liability—it continued tо deny liability, in fact—but “to avoid further costs and risks associated with continued litigation.” The agreement plainly states that the sum is being paid “in full and final settlement of all claims and causes of action” (emphasis added). Seascape’s insurance claims are necessarily included in that release.
Whether IRC is entitled to a share of the settlement proceeds is a factual determination we need not consider here. We merely decide that Seascape has not car-ried
CONCLUSION
After reviewing the movant’s motion for summary judgment, we conclude that none of the grounds presented is meritorious. We therefore reverse the trial court’s summary judgment. In light of this disposition, we do not address the issue pertaining to attorney’s fees. See
