146 N.Y.S. 371 | N.Y. App. Div. | 1914
The action is brought to recover damages on account of the . failure of the defendant to deliver pulp wood as agreed. The agreement between the parties, dated July 5, 1899, “ Witnesseth: That Whereas, William Gr. Rockefeller'has entered into a contract with the Kingsley Lumber Company, dated June 9, 1899, for the purchase of certain timber lands and property in Franklin County, Hew York, therein more particularly described, and has assigned the same to the party of the first part.
“And Whereas, the party of the second part is desirous of purchasing wood now on the said lands from the party of the first part, which the latter is willing to sell if he acquires the title to the said lands under the said contract.
It then provides that if the defendant acquires the land he agrees to sell and deliver on the cars, at the mills of the plaintiff at Cadyville, during the year 1899, 6,000 cords of wood, and during each of the next five years from January 1, 1900, to January 1, 1905, not less than 10,000 cords of wood per year, with the right to the plaintiff to require an additional amount in any year, not to exceed 2,000 cords, by giving the notice required. The wood was to be cut from live spruce trees. Deliveries for the year 1889 were to commence not earlier than October first and continue on an average of about 1,000 cords a month “ after connection has been established by the Chateaugay Railroad Company.” In the successive five years deliveries were to be on the average about 800 to 1,000 cords of wood a month, commencing January 1, 1900. The plaintiff agreed “ to purchase and accept the said wood as hereinbefore provided, and to pay for the same ” five dollars and fifty cents per cord.
The defendant did not in any year deliver the amount of wood stated. In 1899 no wood was delivered. In 1900 there was a deficiency of 4,956.75 cords; in 1901 of .5,679.86 cords; in 1902 of 5,597.75 cords; in 1903 of 7,999.01 cords; in 1904, giving credit for the deliveries after that year, the deficiency was 3,511.87 cords. The defendant has in fact delivered not quite one-half the amount of wood required. In the year 1903, the particular time of year not appearing, more than one-half of the lands referred to in the contract, the part not cut, was burned over and substantially all the spruce killed by fire. Aside from the wood delivered to the plaintiff there remains about 550 cords upon the top of the high mountain which could have been cut and furnished as pulp wood, but the expense of obtaining and delivering it would have been about twenty dollars a cord.
The contract having been executed under seal, the plaintiff’s remedy is not barred by the Statute of Limitations. The defendant having defaulted in delivering the wood at Cadyville, the measure of damages was the difference between the
The difficulty arises with reference to the contention of the defendant that the destruction of the green spruce by fire excused him from making deliveries thereafter. Clearly he is liable for all deficiencies occurring prior to the fire. The contract was made under the following circumstances: In 1899 the De Bar mountain tract, containing about 16,000 acres, belonging to the Kingsley Lumber Company was for sale. It was woodland, with a large quantity of growing spruce. It was connected by a spur with the New York Central railroad, a broad-gauge road, and near the Central railroad at that point was the Chateaugay railroad, a narrow-gauge road. From the lands to the Oadyville mill by the Central road was along and circuitous route; by the Chateaugay road it was substantially a direct line. The accessibility of woodland to a railroad connection, and the freight charges, are an important element in furnishing pulp wood to a given mill. The defendant owned other spruce lands in Franklin county,, upon which no lumbering was being done except the cutting and marketing of wood which had been killed by fires. These lands were about 30 miles away in an air line, about 100 miles by rail, and lumbering from them for the Oadyville mill would make necessary the transfer of. pulp wood from a broad-gauge to a narrow-gauge car in order to use the Chateau-gay road; otherwise it would be necessary to carry it a much greater distance.
One Hibbard applied to the plaintiff in 1899, informing it
The contract by its terms is conditional upon the defendant’s acquiring the Kingsley lands, but the plaintiff contends it is a reasonable inference that if the defendant acquired the Kingsley lands he was then willing to contract absolutely for the delivery of the wood and that the contract does not show that the wood was to be taken from those lands.
While not free from doubt, it seems to me that it was contemplated that the wood to be furnished was to be cut on the Kingsley lands. The statement that the plaintiff was desirous of purchasing the wood now on the lands and that the defendant was willing to sell it if he acquired the lands; the fact that the contract was conditional upon the purchase and that the first deliveries in 1899 were dependent upon the connection with the Ohateaugay road which came within a very short distance but would not immediately serve any other wood lands, and the fact that Hibbard was the moving spirit in the matter, was
In an undated letter from Hibbard to the defendant, which was apparently received about December 26, 1899, he refers to the contract as one “for wood from the De Bar Mountain tract for the Cadyville Mill.” On October 22, 1901, the plaintiff wrote to the defendant complaining that some spruce logs had been sold from the lands, and continued: “We entered into the agreement with Mr. Hibbard with the understanding that we were to have all the spruce wood on this land, although it was not specifically stated that he should not take a small quantity of same for timber purposes. To the best of my judgment, you will not have on this land any more spruce wood than the contract calls for. I simply call this matter to your attention thinking possibly you do not really understand the conditions of the contract as they are being carried out by your representative.”
Under all the circumstances it must be considered that the deliveries of the pulp wood from time to time were conditional upon the continued existence of the green spruce upon the lands not cut over. (Buffalo & L. Land Co. v. Bellevue L. & I. Co., 165 N. Y. 247; Dexter v. Norton, 47 id. 62; Dolan v. Rodgers, 149 id. 489; Herter v. Mullen, 159 id. 28.)
We do not know what time in 1903 the fire occurred, nor
The judgment and orders are reversed upon the law and the facts and a new trial granted, with costs to the appellant to abide the event.
All concurred.
Judgment and orders reversed on law and facts and new trial granted, with costs to appellant to abide event. The findings that'the defendant agreed unconditionally to deliver all the pulp wood mentioned in the contract, and that the plaintiff has suffered damages in the amount of $48,000, are reversed as against the evidence, and the findings are made that considering the circumstances under which the contract was made the deliveries of wood from time to "time were conditional upon the continued existence of the green spruce upon the Kingsley lands not cut over, and that in 1903 the spruce growing upon said lands was substantially destroyed by fire, and that the evidence does not show that the destruction of said spruce was caused by the negligence or fault of the defendant.