70 Wash. 504 | Wash. | 1912
This is an action for a writ of mandate, to require the proper officers of the city of Seattle to allow and pay certain items as extras under a contract of relator with the city. The cause was tried to the court without a jury. After a full hearing upon the evidence, the court dismissed the action at the relator’s costs. The relator has appealed.
On September 24, 1909, the respondent, pursuant to certain ordinances duly passed, entered into a contract with the appellant for the construction of a concrete lining for the Green Lake low service reservoir, called the “lower reservoir,” and for the Green Lake intermediate service reservoir, called the “upper reservoir.” • The earthwork for both reservoirs had previously been performed by other
“Excavation: The contractor shall make such excavation as may be necessary to bring the surface on which the concrete lining is to be placed to a true form and grade to receive the lining. Material necessarily excavated for this purpose shall be removed from the reservoir basin and deposited on the adjacent grounds at such locations as ordered by the engineer in charge. The price bid for excavation per cubic yard shall include excavating, loading, hauling, and dumping as above specified. Particular attention is called to the necessity of accurately finishing the surface to be concreted, and no extra yardage in concrete will be allowed for filling areas excavated below grade, unless such excavation below grade is ordered by the engineer in charge.
“Concrete Filling: When so ordered by the city engineer, channels or depressions eroded in the sides and bottoms of the reservoir basins shall be refilled with concrete which shall be mixed in the proportions of one part of cement to four parts of sand and eight parts of gravel. Concrete filling will be paid for at the rate bid therefor per cubic yard in place.
“Redressing Slopes: When it is necessary in the opinion of the city engineer to redress or repair the surface of the slopes of the reservoir it shall be done by the contractor before the concrete lining is placed thereon. Such redressing or repairing of slopes will be paid for at the rate bid therefor per square yard, such payment to be in full for performing*507 the work and maintaining it in condition until the concrete is placed thereon. Redressed or repaired slopes shall be in all respects as firm and true to grade as the original.”
The contract also provided:
“Contractors must base their proposals on the basis of the quantities hereinafter given, but as these quantities are only approximate and not guaranteed to be correct, and intended only as a basis for the comparison of bids, payment will be made only for actual amount of work done and material furnished, whether it be more or less than the estimated amount.”
The contract was let to the appellant at rates and on approximate estimates as follows: Lower reservoir concrete filling, 9,500 cubic yards, $9.08 per cubic yard; redressing slopes, 2,000 square yards, one dollar per square yard; excavation, 800 cubic yards, fifty cents per cubic yard. Upper reservoir concrete lining, 9,500 cubic yards, $9.18 per cubic yard; redressing slopes, 200 square yards, one dollar per square yard; excavation, 800 cubic yards, fifty cents per cubic yard. The appellant seeks to recover for four items of labor and material furnished in the work claimed as extras, which the respondent has refused to allow.
(1) The first item was for redressing the bottom of the upper reservoir to the extent of 28,248 square yards. The appellant claims that this was extra work for which fifteen cents a square yard was a reasonable price, at which rate this work would amount to $8,487.20. The respondent claims that this was covered by the contract as excavation. Computed as such, there were 259 cubic yards. The city paid for this at the contract rate for excavation of fifty cents per cubic yard, amounting to $129.50. The appellant, therefore, claims a balance for this item of $8,857.70. The contract must be construed with reference to the condition of the subject-matter at the time it was let. It is admitted that the contract, plans, and specifications contain no provision for redressing the bottom of either reservoir. The reason for this, as is clearly shown by the evidence, was that, at the
“The contractor is to sustain, without claim against the city, all losses or damages to the work to be done under these specifications, arising from the action of the elements, ,or from any unforeseen obstruction or incumbrances on the line of work, which may be encountered in the prosecution of the same.”
“We will put this filling in, free of cost to the city, and assume responsibility for future washing out, on the basis of the following concessions to be made us: that all the base shall be put in on the slopes and bottom in the proportion of 1-3-6, assuming a barrel of cement to be 3.5 cubic feet, as stated in the specifications, and the concrete to be proportionate in the ratio of 1.03 barrels of cement, 10.8 cubic feet of sand, and 21.6 cubic feet of gravel, the top to be in the proportion of 1-1% or 11.9 cubic feet of cement to 17.8 cubic feet of sand. The above is also made with the understanding that the grade on the bottom and on the sides will be lowered an inch or more in order that the flat surfaces will not require more than six inches of base. This will, of course, save the city the expense of paying us for back filling, and place the concrete on solid instead of tamped earth. The ribs are to be put in exactly the same size as before, with the*511 proportion of 1-3-6, as above, you to pay us for excavation and yardage of these. Should you wish to change the size of the ribs, kindly let us know at once.”
The city engineer answered, accepting this offer with the understanding “that the quantities for which payment is to be made are to be computed as though the lining were seven inches thick over the surface of the reservoir, and that no account is to be taken of the concrete which is necessarily used to fill the gullies eroded in the sides of the reservoir basin; that the ribs are to be measured as though they were é" x 8" in cross-section; that the earth which has washed from the slopes is to be removed by you without cost to the city.” This supplemental agreement cheapened both the base and the mortar surface, by requiring less cement, as the evidence shows, to the extent of 2-10 of a barrel to each cubic yard of concrete. The very purpose of the agreement was to avoid the necessity and consequent delay to the appellant of redressing the slopes on the one hand, and the expense to the city of redressing the slopes on the other. The contract, it will be remembered, provided for redressing only when necessary in the opinion of the city engineer.
While there was much testimony that the slopes were redressed to the extent claimed, there was no sufficient proof that this was ordered by the city engineer. Both the president of the appellant and its foreman testified that they were required (the inference being by some one representing the city) to remove the surface of the slopes with pick and shovel from an inch to in some places four or five inches. On the other hand, the city engineer testified that, under the supplemental agreement, “they were to proceed with the work and to fill the gullies, which had eroded, with concrete at a given price, and no instructions were given and no requirements made that they should dress the slopes.” The engineer in direct charge of the work for the city, and who reported directly to the city engineer, also testified that neither he nor any of his assistants that he knew of ever gave any order
“This can in no way be interpreted to be covered by our figure for excavation, and you would doubtless feel injured if we tried to apply our figure of one dollar per square yard which was intended to cover the resurfacing of the slopes in the lower reservoir. We would therefore ask that we be allowed fifteen cents per square yard for this resurfacing from the time we began work this spring, which will amount to about 9,000 yards on the slopes and about 20,000 yards on the bottom.”
The city engineer, as he testified, after looking over the work, answered this letter on May 12, as follows:
“As to the slopes, the work you are doing is certainly covered by the agreement entered into under the date of March 22, in my letter accepting your proposition of March 21; as you know, you were granted a concession in the amount of cement used, which amounts to about 2-10 of a barrel to each cubic yard of concrete, and this concession is being applied to the bottom as well as the slopes of the reservoir.”
In view of these facts, it is evident that both parties recognized that they were then proceeding under the supplemental agreement which had superseded the original contract as to this resurfacing. In fact, the appellant seems to concede that the contract price of one dollar per square yard was originally intended to apply only to the slopes of the lower reservoir. This is further supported by the testimony of the appellant’s president that the bid was unbalanced, in that it was higher for the redressing and lower for the concrete in the lower reservoir. The contractor, having received the benefit of the supplemental agreement by a cheapening of the mixture throughout, cannot dispute this. Having received the consideration moving to it in the cheapening of the mixture, the defendant cannot question the right of the city
(3) The third item was for 585.5 cubic yards of concrete which it is claimed was used upon the sides and bottom of the upper reservoir in excess of the seven inches agreed upon in the contract. This, at the contract rate of $9.18 per cubic yard, amounts to $5,374.89. It is clear that, under the supplemental agreement, there can be no recovery for excess concrete used on the slopes. The only specific estimate which we have been able to find relating to the bottom of the reservoir alone is one made by the engineer of the appellant from condemned slabs removed from the bottom. He placed the amount of excess concrete used in the bottom at 504.5 cubic yards. Since the respondent offered no evidence in contradiction of this, we will assume that it is approximately correct. The respondent claims that, under the supplemental agreement, the appellant was not entitled to pay for excess concrete, whether placed on the slopes or on the bottom. A reading of the correspondence which we have quoted constituting this agreement is a sufficient answer to this contention. That agreement was manifestly intended to apply only to the excess concrete used on the slopes. The appellant is entitled to recover for 504.5 cubic yards of concrete at the contract price, amounting to $4,631.31.
(4) The appellant sought also to recover for 830.7 cubic yards of concrete placed in the bottom of the lower reservoir, which it is claimed was in excess of 7.5 inches thickness agreed
“ ‘5. In lieu of your changing the base concrete to 1-3-6 and the surface to 1 to 1%, we agree to make the base of an average thickness of 6% inches, as stated above for the slopes, and the same average of thickness on the bottom.’ This is accepted. ‘6. The bottom is to be prepared for the concrete by simply rolling with a steam roller, to within twenty feet of the foot of the slopes, from which point to the foot of the slopes the surface is to be finished in excavating the talus.’ ‘7. We are to be allowed the cost of doing the rolling, you to stand the cost of loading and unloading the roller on the cars, and we to pay for transportation of the same.’ These paragraphs are accepted. ‘8. We presume you will desire to go over the entire bottom with a street-surfacing machine to remove the clover and weeds before the rolling is done, which will not be of any considerable expense, but will, we assume, be included within the cost of rolling.’ It is my opinion you should remove this clover at your own expense, as it has all grown since the contract was awarded you, and would not have required removing if you had laid the lining sooner. ‘9. A new grade is to be agreed upon by your Mr. Alexander and our Mr. Rollins, so that the thickness of the base will average 6% inches with an allowed variation of from 5 inches to 8 inches.’ This proposition is accepted, with the understanding that the base of each slab is to*515 average 6% inches, with a maximum thickness of 8 inches, and a minimum thickness of 5 inches.”
Item 6 as to steam rolling was afterward waived by the respondent. It is thus apparent that the changes contemplated were change of grade to avoid redressing the bottom, change of thickness of lining to compensate for unevenness of the bottom, and change of proportions of the concrete aggregate. The evidence shows that there was a delay in Rollins and Alexander, engineers for the contractor and city respectively, getting together to agree upon the new grade. Rollins, however, made an estimate that a raise of grade of 0.15 of a foot would give an average thickness of base of from 6% to 6% inches, which would make the average thickness of lining 7% to 7% inches. He estimated that the added thickness of base over 6% inches average would not require over 100 cubic yards of additional concrete, and Alexander told him the city would pay for that amount. Accordingly, on June 20, the president of the appellant company wrote the city engineer, offering to proceed on that basis. This, letter was not answered at once, and the president of the appellant, on June 24, wrote another letter, stating that the appellant would clean the grass and weeds from the bottom, take off high points amounting to ten or twelve per cent at the “newly established grade so that no part of the base will be less than five inches thick, and make no extra charge for any excess concrete in the bottom, on the basis that we are to make the base 6% inches instead of 6% inches on the slopes. We have instructed our Mr. Davis to go ahead at once on this basis, as we can think of absolutely nothing else but what is fully agreed upon.” On June 28 the city engineer in answer to these letters, after quoting the last one, continued:
“I understand this to mean that the grade of the finished surface of the bottom of the reservoir is to be raised 0.15 feet above the original levels shown on our plan for the entire area; that the minimum thickness of the base of the slabs*516 in the bottom of the basin is to be 5 inches and the minimum finished thickness 6 inches, including the mortar surface; that you will do such grading and surfacing as may be necessary to secure such minimum thickness; that you will make no charge for grading or surfacing the bottom of the basin or for removing clover or weeds; that the thickness of the base of the slab on the slopes is to be 6% inches or 7% inches, including the mortar surface, and that the concreting in the lining of the reservoir on both sides and bottom is to be computed as though it were 7 inches thick, including the mortar surface, and paid for at the rate of $9.08 per cubic yard based on this measurement. Should it prove that raising the grade of the bottom 0.15 feet and grading off such area as may be necessary to secure such minimum thickness produces slabs having an average thickness of more than 7% inches, including the mortar surface, that you are to make no claim for extra yardage in concrete. This letter is intended to fulfill and confirm the terms of your letter of June 7th, referred to as paragraph 9 in my letter of June 14th, in which you say ‘a new grade is to be agreed upon by your Mr. Alexander and our Mr. Rollins, so that the thickness of the base will average 6% inches, with an allowed variation of from 5 inches to 8 inches’; and to explain and render definite this agreement as to the position of the grade and thickness of the concrete lining. With this understanding, your proposal is accepted.”
To this the appellant answered:
“Replying to yours of the 28th, you are correct in all the statements contained therein, and also in your understanding that no charge will be made for grading or surfacing the bottom, or for removing the clover and weeds, éxcept the compensation of % inch reduction in the thickness of the concrete base on the slopes, making it 6% inches instead of 6% inches.”
It transpired that the raise of grade of the bottom of the reservoir 0.15 feet increased the amount of concrete by making the thickness of the lining greater than the appellant’s engineer had estimated. It is for this excess concrete that the claim is made. There can be no question that there was a meeting of the minds on the grade as fixed. While there
The judgment is reversed, with directions that the writ issue for the allowance and payment of $4,631.31, which we have found due for the third item claimed.
Mount, C. J., Morris, and Fullerton, JJ., concur.