Opinion for the Court filed by Circuit Judge HARRY T. EDWARDS.
In 1981, the Interstate Commerce Commission (“ICC” or “the Commission”) authorized Chicago and North Western Transportation Company (“CNW”) to abandon two rail lines. Under the terms of the authorization, CNW was required to apply employee protective conditions on behalf of workers adversely affected by the planned abandonments. When a dispute arose over the implementation of the employee protective conditions, the matter was properly submitted to arbitration for resolution. Following arbitration, however, the ICC asserted authority to review the arbitrator’s decision. The petitioner, International Brotherhood of Electrical Workers (“IBEW” or “union”),
The question posed for this court is one of first impression. Although the ICC has required the use of arbitration for a number of years to resolve disputes over labor protective conditions, neither the agency nor the courts heretofore have had occasion to decide whether the ICC may assert jurisdiction to review an arbitrator’s decision. In our view, the ICC’s determination that it may review arbitration awards under the Interstate Commerce Act, 49 U.S.C. § 10903 (1982) (“ICA”), is permissible and not contrary to precedent. We further find that the ICC has provided a rational basis for asserting jurisdiction to review arbitration awards in select cases. Accordingly, we deny the petition for review.
I. Background
In 1981, acting pursuant to 49 U.S.C. § 10903 (1982), the ICC authorized CNW to abandon two rail lines.
11. Arbitration of disputes — (a) In the event the railroad and its employees or their authorized representatives cannot settle any dispute or controversy with respect to the interpretation, application or enforcement of any provision of this appendix ... within 20 days after the*106 dispute arises, it may be referred by either party to an arbitration committee.'
* * * * * *
(c) The decision, by majority vote, of the arbitration committee shall be final, binding, and conclusive and shall be rendered within 45 days after the hearing of the dispute or controversy has been concluded and the record closed.
Following the ICC’s authorization of the CNW abandonments, a dispute arose over payments due to Daniel Scheele, a CNW electrician. IBEW presented claims to CNW for the employee’s moving expenses and the losses incurred in selling Scheele’s home in Oelwein.
In March 1986, CNW filed a petition for administrative review of the Board’s decision.
On April 28, 1987, the Commission held that it had jurisdiction to review arbitration decisions; upon review of the merits of the case, the ICC upheld the Board's award of benefits to Scheele. The Commission stated, however, that in this and in future cases it would limit its review to “recurring or otherwise significant issues of general importance regarding the interpretation of our labor protective conditions.”
In its decision, the Commission first noted that “there is no specific Commission precedent to rely on in resolving this [jurisdictional] issue.” Id. at 732. Previous ICC “cases [did] not address the question presented here: what happens after an issue has been submitted to arbitration.” Id. at 735 (emphasis in original). Pointing to precedent involving the former Civil Aeronautics Board (“CAB”), the Commission found that “proper implementation of the statute may compel our review when. an arbitration decision raises issues concerning our statutory responsibility to impose labor protection.” Id. at 733. The Commission also looked to earlier instances in which the Commission had to answer questions raised “as to whether collective bargaining agreements ... conformed] with statutory requirements for protection, and questions defining the scope or coverage of imposed conditions.” Id. (footnotes omitted). While expressing the “continue[d] belie[f] that mandatory arbitration is appropriate for the final resolution of causation issues,” the Commission concluded that “nothing in the mandatory arbitration requirement forecloses us from considering whether our abandonment decisions (and labor protection conditions) have been properly interpreted or carried out as we intended.” Id. at 735 (footnote omitted).
II. Analysis
A. Justiciability
This case comes to us in a somewhat unusual posture, because the ICC upheld the union’s position on the merits of the arbitration award. Given this state of the record, it might be claimed that there is no justiciable controversy before the court. However, at oral argument, counsel for both the ICC and the petitioner asserted that IBEW has standing to pursue this, appeal, that the case is not moot and that the appeal is ripe for review. We agree.
First, with respect to IBEW’s standing to maintain this appeal, the union’s interest in resolving the jurisdictional issue is sufficient to meet any constitutional requirements. The ICC stated that “[t]he principal issue raised by CNW’s petition is our jurisdiction to review the Board’s award to Mr. Scheele."
This injury is similar to interests held to be sufficient to confer appellate standing on an otherwise prevailing party. In Electrical Fittings Corp. v. Thomas & Betts Co.,
Because the petitioner in this case will be forced to litigate future arbitration awards before the ICC, it has a personal stake sufficient to meet the demands of article III. The union is no less injured by the ICC’s reviewability ruling than it would have been if the Commission had promulgated a rule in an informal rulemaking under 5 U.S.C. § 553 (1982). It will incur the costs of resisting challenges to arbitration awards and the delays that such reviews entail. In other words, there is no doubt as to IBEW’s standing in the classic sense of the term, and there is no doubt that the case before us is not moot.
Second, although neither side raises the point, there is a question whether the instant appeal is ripe for judicial review. The ripeness doctrine is designed
to prevent the courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements over administrative policies, and also to protect the agencies from judicial interference until an administrative decision has been formalized and its effects*108 felt in a concrete way by the challenging parties.
Abbott Laboratories v. Gardner,
[although it is true that “ripeness law overlaps at its borders with Article III requirements of case or controversy,” its application in the present case implicates the doctrine in only its prudential aspects. In that form, the ripeness inquiry takes into account pragmatic concerns regarding “the institutional capacities of, and the relationship between, courts and agencies.” These concerns include “the agency’s interest in crystallizing its policy before that policy is subjected to judicial review,” “the court’s interests in avoiding unnecessary adjudication and in deciding issues in a concrete setting,” and “the petitioner’s interest in prompt consideration of allegedly unlawful agency action.” In Abbott Laboratories, the Supreme Court announced the two-prong test for ripeness that balances these interests. The test requires a court to evaluate “both the fitness of the issues for judicial decision and the hardship to the parties of withholding court consideration.”
Id. at 92 (quoting Eagle-Picher Indus., Inc. v. EPA,
No one disputes that the Commission’s jurisdictional holding is fit for judicial review. The question is a purely legal one; any necessary factual findings have been fully developed in the proceedings below. The ICC’s decision is “crystallized,” Eagle-Picher,
The agency’s labelling of the jurisdictional issue as “principal” confirms the Commission’s position at oral argument that its institutional interests support immediate adjudication. The union has made equally clear that its interests do so as well. In light of the fact that the agency consistently has asserted its right to review arbitration awards since its decision in this case, Joint Brief of Respondents ICC and USA at 11, we can see no judicial institutional interest that militates against review at this time. Thus, we find judicial review appropriate in this case.
B. Statutory Authority
On the merits of this appeal, the petitioner first claims that the ICC is without authority under the ICA to review arbitration awards resolving disputes over labor protective conditions. On this point, the petitioner appears to contend that, under the statute governing the agency, the ICC cannot reclaim the authority that it has delegated to arbitrators to interpret, apply and enforce labor protective conditions. We find this position wholly untenable.
1. Standard of Review
Since the union’s claim under the ICA presents “a pure question of statutory construction, our first job is to try to determine congressional intent, using ‘traditional tools of statutory construction.’ If we can do so, then that interpretation must be given effect____” NLRB v. United Food & Commercial Workers Union, Local 23,
2. The ICA
We begin by examining the ICA itself. The ICA is silent with respect to the ICC’s reviewing powers in arbitration cases. The ICA requires only that the certificates of abandonment issued by the Commission “contain provisions to protect the interests of employees.” 49 U.S.C. § 10903(b)(2). Nothing in the Act either requires or forecloses the agency’s use of arbitration in employee disputes, or limits agency review of arbitration decisions.
Thus, this court must defer to the ICC’s interpretation in filling any gaps in the statute if the ICC has done so in a permissible manner. See Chevron,
3. Judicial and Agency Precedent
The petitioner argues that even if the agency’s present construction of the statute is facially permissible, it should nonetheless be reversed because it is inconsistent with judicial precedent, and because it constitutes an unexplained change in the agency’s construction of the ICA. See King Broadcasting Co. v. FCC,
IBEW claims that several judicial decisions establish that “arbitration has consistently been deemed to be the final step in the [employee protection] process,” Brief for Petitioner at 9, and that the Commission lacks jurisdiction or authority under the ICA to proceed further once arbitration has been imposed. We disagree. The ICC has never before been asked to review an arbitration decision, and no court has directly addressed the issue. This is thus a case of first impression.
IBEW also relies on Leavens v. Burlington Northern, Inc.,
The decision in Bell v. Western Maryland Railway Co.,
Accordingly, we find that the ICC’s construction of the ICA in this case is not inconsistent with its past interpretation of the Act.
4. Conclusion on Statutory Authority
We find that the ICC’s determination that it had statutory authority to review the arbitration award was a permissible construction of the ICA. The statute itself is silent on the issue, and the ICC’s filling in of gaps is consistent with the terms of the ICA itself, the relevant case law involving the employee protective provisions of the ICA, and the ICC’s own decisions. Accordingly, we defer to the agency’s interpretation of its governing statute.
C. Substantive “Arbitrary and Capricious” Review
Our next task is to review the substance of the ICC’s decision independent of questions of statutory authority. See Weyerhaeuser Co. v. Costle,
The Supreme Court has explained substantive review as follows:
The scope of review under the “arbitrary and capricious” standard is narrow and a court is not to substitute its judgment for that of the agency. Nevertheless, the agency must examine the relevant data and articulate a satisfactory explanation for its action including a “rational connection between the facts found and the choice made.” Burlington Truck Lines, Inc. v. United States,371 U.S. 156 , 168 [83 S.Ct. 239 , 246,9 L.Ed.2d 207 ] (1962). In reviewing that explanation, we must “consider whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment.” Bowman Transportation, Inc. v. Arkansas-Best Freight System, Inc., [419 U.S. 281 , 285,95 S.Ct. 438 , 442,42 L.Ed.2d 447 (1974)]; Citizens to Preserve Overton Park v. Volpe, [401 U.S. 402 , 416,91 S.Ct. 814 , 823-24,28 L.Ed.2d 136 (1971)]. Normally, an agency rule would be arbitrary and capricious if the agency has relied on factors which Congress has not intended it to consider, entirely failed to consider an important aspect of the problem, offered an explanation for its decision that runs counter to the evidence before the agency, or is so implausible that it could not be ascribed to a difference in view or the product of agency expertise. The reviewing court should not attempt itself to make up for such deficiencies; we may not supply a reasoned basis for the agency’s action that the agency itself has not given. SEC v. Chenery Corp., 332 U.S. 194, 196 [67 S.Ct. 1575 , 1577,91 L.Ed. 1995 ] (1947). We will, however, “uphold a decision of less than ideal clarity if the agency’s path may reasonably be discerned.” Bowman Transportation, Inc. v. Arkansas-Best Freight System, Inc., supra, at 286. [95 S.Ct. at 442 .] See also Camp v. Pitts,411 U.S. 138 , 142-143 [93 S.Ct. 1241 , 1244,36 L.Ed.2d 106 ] (1973) (per curiam).
Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co.,
First, as we concluded above, the ICC’s decision to review arbitration awards was not inconsistent with its earlier precedent. The issue of its reviewing powers has never before been raised, and the Commission’s resolution of that issue in this case does not conflict with its earlier rulings.
We approved these abandonments and formulated the Oregon III labor protection provisions at issue here. Therefore, we know best what we intended Oregon III (and our .abandonment decisions) to mean. Because this action raises issues within our special competence and expertise, it makes sense that we resolve, in the first instance, whether our intent has been carried out.
Id. at 733-34 (citations omitted).
We conclude that the Commission has offered a reasoned explanation for its decision to review arbitration awards, and that this decision was not arbitrary or capricious. During oral argument, counsel for the petitioner suggested that the ICC will be flooded with arbitration cases, resulting in long delays in litigation over employee protective conditions, if the agency is afforded the power of review. This forecast is founded solely on speculation, so there is no way for us to assess it. If the union proves to be right in its prediction, then the agency may have a problem to deal with in the future. For now, however, it is not our place to second guess the Commission’s expertise in this matter or to “substitute [our] judgment for that of the agency.” State Farm,
The petitioner also suggests that the ICC’s decision should be rejected as arbitrary and capricious because it is patently “implausible.” Id. On this point, the union argues that the decision in Oregon III, requiring parties to use arbitration to resolve disputes over employee protective conditions, rested in part on the Commission’s acknowledged lack of expertise in this area. The union thus asks, if the ICC lacks the expertise to decide the cases that have been delegated to arbitration, how is the agency equipped to review those same cases once arbitration has been completed? This question raises a reasonable inquiry under State Farm, but it assumes too much.
It is true that the ICC in the past has suggested that arbitration is the best mechanism for adjudication of individual labor controversies. See, e.g., Brotherhood of Locomotive Engineers v. Chicago & North Western Transp. Co.,
III. Conclusion
We can find no merit in the petitioner’s claims in the instant case. Therefore, for the reasons discussed in the foregoing opinion, the petition for review is hereby denied.
So ordered.
Notes
. IBEW served as the employees’ collective bargaining representative and as their advocate during the arbitration proceeding.
. On January 28, 1981, and on November 17, 1981, the Commission authorized, respectively, the abandonment of rail lines between Dubuque and Oelwein, Iowa and between Oelwein and Randolph, Minnesota.
.Section 10903(b)(2) instructs that certificates of abandonment issued by the Commission "shall ... contain provisions to protect the interests of employees."
. In particular, the union requested payment of the mortgage interest, the realtor’s commission and the judgment-type interest on all amounts due on the old house, as well as $500 to prepare Scheele’s new home for occupancy. See ICC v. Chicago North Western Transp. Co.—Abandonment,
. CNW also petitioned the U.S. Court of Appeals for the Seventh Circuit for review of the Board's decision. See Chicago & North Western Transp. Co. v. United States and ICC, No. 86-1394 (7th Cir. filed Mar. 12, 1986). CNW, however, asked the court to hold its review in abeyance pending the Commission's decision.
.IBEW also challenged the timeliness of CNW’s petition. The union does not, however, raise this matter in this appeal. Brief for Petitioner at 5 n. 4.
. IBEW’s petition for review was originally filed in the Seventh Circuit. By order of the Seventh Circuit, the review proceeding was transferred to this circuit. See International Bhd. of Elec. Workers v. ICC and Chicago & North Western Transp. Co.,
. The Hobbs Act, which governs judicial review of final orders promulgated by the ICC, requires that a party be aggrieved to petition a court of appeals to review an ICC order. 28 U.S.C. § 2344 (1982).
. See, for example, Brotherhood of Locomotive Eng'rs v. ICC,
In United Transportation Union v. Norfolk & Western Railway Co., 822 F.2d 1114, 1115 (D.C. Cir.1987), cert. denied, — U.S. -,
. The ICC also relied on cases holding that the CAB had authority both to require arbitration of disputes over labor protective conditions and to review the judgments of arbitration panels. See, e.g., Wallace v. CAB,
