INTERN. COMMUNITY CORP. v. Davis Water and Waste Industries, Inc.INTERN. COMMUNITY CORP. v. Davis Water and Waste Industries, Inc.
Appellants, International Community Corporation-Tampa (ICC-T) and The Insurance Company of Florida, seek review of a final summary judgment awarding damages against appellants for $4,736.89 in a mechanic‘s lien action. We affirm.
Appellants raise several points on appeal. First, appellants argue that the trial court erred by granting a materialman‘s lien based upon a pro rata formula pursuant to
ICC-T, as a developer of a subdivision in Pasco County, contracted with Duarte Construction Company, Inc. (Duarte) to construct subdivision improvements. Duarte subcontracted with appellee to supply pipeline materials to the project.
Prior to completion of the project, Duarte defaulted and was removed from the job. ICC-T hired new contractors to complete the work Duarte had contracted to perform and to correct defective work performed by Duarte.
After Duarte‘s default, numerous subcontractors and materialmen, including appellee, filed mechanic‘s liens against the property owned by ICC-T. These liens were transferred to lien transfer bonds pursuant to
On January 4, 1983, appellee filed suit against Duarte and ICC-T. Count II of the complaint dealt only with ICC-T and sought foreclosure of the mechanic‘s lien against the real property owned by ICC-T in Pasco County. On January 10, 1983, appellee‘s mechanic‘s lien was transferred to a
Appellee amended its complaint to add count III, which sued ICC-T as principal and The Insurance Company of Florida as
Appellants moved to dismiss count II of the amended complaint alleging that it did not state a cause of action because the lien had been transferred to the bond. This motion was denied.
The motion for summary judgment directed towards count III of the amended complaint was filed on May 6, 1983. Various affidavits regarding amounts due in attorney‘s fees and costs were attached to the motion for summary judgment. The affidavits indicated that there was approximately $50,000 undistributed by ICC-T, and that there were outstanding liens of approximately $96,000. ICC-T claimed a set off for the cost to complete and correct against the balance held on the original contracts and intended to disburse the remaining balance pro rata on the basis of
On June 3, 1983, appellee‘s attorney agreed to entry of the final summary judgment based on pro rata distribution. On June 7, 1983, appellants’ attorney sent a supplemental memorandum of law to the court, claiming that the proper statute was
On June 24, 1983, the court denied appellants’ motion for leave to file supplemental affidavits and entered a final summary judgment against appellants based on pro rata distribution.
We find that the trial court did not err by ordering pro rata distribution according to
Appellants’ argument that the trial court erred by refusing to allow the filing of supplemental affidavits prior to the entry of a summary judgment must fail. Parties cannot be permitted to assert conflicting affidavits. Grauer v. Occidental Life Insurance Company of California, 363 So.2d 583 (Fla. 1st DCA 1978), cert. denied, 372 So.2d 468 (Fla. 1979).
The failure to attach a copy of the actual surety bond to the complaint does not require dismissal under
Appellants also claim that count I, which intended to foreclose against the real
Finally, appellants claim that the judgment was improperly entered against the property owner; that the summary judgment should have been entered against The Insurance Company of Florida, but due to clerical error, was not. The summary judgment was based on the lien transfer bond which was issued by The Insurance Company of Florida. That bond released the property owner, ICC-T, from liability. Therefore, we find that the entry of the summary judgment against ICC-T was a clerical error because the judgment is clearly based on the lien transfer bond. On remand, the summary judgment should be corrected to reflect that it is a summary judgment against The Insurance Company of Florida rather than ICC-T.
For the foregoing reasons, we affirm the decision of the trial court. However, we remand to the trial court for correction of the summary judgment. On remand, we also direct that the record reflect that count II is dismissed.
OTT, A.C.J., and CAMPBELL and SCHOONOVER, JJ., concur.