OPINION
Coonradt Construction Company (Coon-radt) appeals from a judgment dismissing its mechanics’ hen as untimely filed and thus invahd. We affirm.
FACTS
This case is before us a second time. Detailed facts pertinent to the initial dispute can be found in Interiors Contracting, Inc. v. Smith, Hollander & Smith Associates,
We reversed and remanded. We noted that section 38-1-7 of the Utah Code specifies that an original contractor must file a notice of mechanics’ hen “within 100 days after the completion of his contract,” Utah Code Ann. § 38-1-7 (Supp.1987). We made clear, however, that “[a] contract is ‘completed,’ ” when the work (1) “has been ‘substantially completed,’ leaving only minor or trivial work to be accomplished,” Interiors I,
Our opinion issued March 2,1992. Shortly thereafter, the trial court determined it did not need to hear further evidence to resolve the remanded issue. The parties then briefed the issue based upon the facts developed during the earlier three-day trial, and the trial court ruled “after reviewing all of that evidence, that the job was accepted by the government on or before May 4, 1987.” The court ultimately entered detailed findings of fact and conclusions of law and a judgment declaring Coonradt’s lien invalid.
Coonradt, once again, appeals the trial court’s judgment, arguing: (1) the trial court erred in declining to take additional evidence on the remanded issue; and (2) the trial court’s findings of fact were clearly erroneous.
I. NECESSITY OF TAKING ADDITIONAL EVIDENCE
Coonradt insists that the trial court erred in refusing to allow it “to present additional evidence to clarify the record.” We disagree. Had we felt the trial court needed to take additional evidence, we would have remanded with instructions so specifying, as Utah courts have not hesitated to do in the past. See, e.g., Oates v. Chavez,
II. ADEQUACY OF FINDINGS OF FACT
Rule 52 of the Utah Rules of Civil Procedure provides that “[findings of fact, whether based on oral or documentary evidence, shall not be set aside unless clearly erroneous.” Utah R.Civ.P. 52(a). Findings of fact are clearly erroneous if it can be shown that they are without adequate evi-dentiary foundation or if they are induced by an erroneous view of the law. Western Capital & Secs., Inc. v. Knudsvig,
Coonradt first asserts that the trial court-failed to enter sufficient findings of fact on the issue we specifically identified for resolution on remand. In response to the remanded question of when Coonradt’s work was accepted as complete, the trial court
(1) The contract for the remodeling improvements which are the subject matter of this ease ... required completion of the entire improvement work by April 17, 1987.
(2) ... From and after April 16, 1987, Coonradt considered the work completed and believed that he was entitled to payment.
(3) GSA’s [United States of America, General Services Administration’s] tenant agency moved into the remodeled facility in the last part of April, 1987 and fully occupied the remodeled facility.
(4) GSA, the lessee of the subject budding and the contracting party for whose benefit the improvements were performed, was to determine Coonradt’s entitlement to payment.
(5) GSA made an inspection of the completed work on April 29, 1987 and a final inspection on May 1,1987. There were no other inspections made by GSA at any time prior to the receipt by the owner WMW [Walker, McElliot, Wilkinson & Associates], of full payment from GSA for the completed work.
(6) Prior to the commencement of the work and at all times thereafter, GSA, WMW and Coonradt knew and understood that following GSA’s final inspection and acceptance of the completed work, there would be a normal payment processing period of approximately forty-five (45) days for GSA to make disbursement of full payment for the work.
(7)• Lynn Walker, the budding manager for WMW, testified that he was authorized to submit his final invoice on May 4, 1987, which he did. The invoice was received at the GSA Denver office on May 8,1987 and thereafter GSA processed payment in the usual course of business, without requesting further inspections or reinspection of the premises.
(8) There is no evidence in the record to demonstrate that GSA or the owner WMW insisted upon completion of the minor punch-list items prior to processing WMW’s invoice and GSA’s payment, nor prior to GSA making full payment under the contract. GSA made full payment in their normal processing time even though two of the minor punch-list items were never completed.
(9)Based on the evidence in the record and after reviewing the same, the court finds that under all of the facts and circumstances, the entire work was accepted as complete by GSA and the owner WMW on or before May 4, 1987.
Coonradt’s contention is that the trial court’s Finding No. 9, that “the entire work was accepted as complete by GSA and the owner WMW on or before May 4,1987,” is a conclusion of law, not a finding of fact, and thus the trial court committed reversible error in failing to enter sufficient findings of fact. However, Coonradt ignores the trial court’s preceding eight detailed findings of fact, which form the basis for the trial court’s ultimate determination that the work was accepted on or before May 4,1987. We conclude that the trial court’s findings of fact — Finding No. 9 together with Finding Nos. 1 through 8 — are sufficient.
Next, Coonradt argues that the trial court’s findings are grounded in an erroneous view of the law. We disagree. Under the legal standard we set forth in Interiors I, the trial court’s findings are legally relevant. The sole question in the cases we referenced in Interiors I was whether a contractor’s continued work on trivial tasks at the owner’s request would toll the lien filing period. Each case relied on an estoppel theory in holding that it could. In Gooch v. Hiatt,
In accordance with the theory outlined in these cases, the trial court’s findings properly focus on factors germane to estop-pel. Finding No. 2, that Coonradt considered the work complete as of April 16, 1987, shows Coonradt did not rely on any representation that its work was not accepted as complete. Finding No. 5 shows that GSA did not indicate that Coonradt’s work was not accepted as complete by insisting that further inspections be made. Finding Nos. 6, 7, and 8 show that payment was not conditioned on completion of the four remaining punch-list items. (Finding No. 8 particularly underscores this fact since GSA rendered full payment even though Coonradt never completed two of the punch-list items.) We therefore conclude that the trial court’s findings were grounded in a correct view of the law.
Finally, we address whether the trial court’s findings were supported by sufficient evidence. A finding attacked as lacking adequate evidentiary support is deemed “clearly erroneous” only if the appellate court concludes that the finding is against the clear weight of the evidence. Reid v. Mutual of Omaha Ins. Co.,
Coonradt has not met its burden in this respect. “In order to properly discharge the duty of marshaling the evidence, the challenger must present, in comprehensive and fastidious order, every scrap of competent evidence introduced at trial which supports the very findings the appellant resists.” West Valley,
We therefore hold that the trial court’s findings of fact were supported by sufficient evidence and affirm the trial court’s judgment that Coonradt’s notice of lien was untimely filed.
GREENWOOD and JACKSON, JJ„ concur.
