Opinion
This consolidated
1
appeal arises from an action for the foreclosure of a mechanic’s lien brought by the plaintiff, Intercity Development, LLC, against the defendants,
2
Joao Andrade and Irene Andrade, in connection with a contract entered into
by the parties for the construction of a residence on property owned by the defendants in the town of Oxford. The certified issue in the plaintiffs appeal is whether the Appellate Court properly reversed the judgment for the plaintiff for foreclosure of its mechanic’s lien and attorney’s fees.
Intercity Development, LLC
v.
Andrade,
The Appellate Court opinion sets forth the following relevant facts and procedural history. “On November 26, 2001, having reviewed the plans and specifications prepared for the defendants by an architectural firm, the plaintiff, through its president, Anthony Stewart, entered into a contract with the defendants for the construction of a residence on property owned by the defendants in Oxford for the agreed price of $240,000 payable in five payments of $48,000 each according to a schedule with respect to the work performed. According to the terms of the contract, construction was to be completed within 180 days of commencement. It did not provide for attorney’s fees in case of default.
“Upon the commencement of work, the defendants requested many changes to the plans, causing considerable delays. The requested changes and the additional foundation work increased the cost of completing the contract to $264,441.50.
“On July 17, 2002, Stewart arrived on the job to find certain building supplies missing and to be met by police, who informed him that he was trespassing. Irene Andrade had called the police and directed a letter, through her attorney, terminating the construction contract. According to the letter, the basis for the termination was the plaintiffs failure to complete the construction within the 180 day period as set out in the contract. At the point of termination, the plaintiff claimed that it was owed the sum of $49,933.19 and filed a mechanic’s lien for such sum. The plaintiff then brought this action to foreclose the mechanic’s lien [and for damages for breach of contract]. . . .
“After a four day trial . . . [t]he court found that ‘the allegations of the plaintiffs first and second counts of its [amended] complaint [mechanic’s lien foreclosure and breach of contract, respectively, had] been established by the evidence and [the court] acceptfed] the plaintiffs [calculation] of damages as set out in the damages work sheet attached in the plaintiffs trial brief . . . .’ The court . . . awarded damages to the plaintiff in the amount of $49,933.19, plus costs. The court thus found in favor of the plaintiff on both the claim to foreclose on the mechanic’s lien and the claim for breach of contract. The court also stated that upon the plaintiffs filing of the appropriate motion, the court would entertain the foreclosure of the mechanic’s lien. Thereafter, the plaintiff filed a motion for a judgment of strict foreclosure and a motion for attorney’s fees pursuant to . . . General Statutes § 52-249 (a), both of which were heard by the court and granted. The court allowed the plaintiff attorney’s fees in the amount of $27,225 pursuant to the provisions in the mechanic’s lien statute.”
Intercity Development, LLC
v.
Andrade,
I
On appeal to this court, the plaintiff claims that the Appellate Court improperly ruled in favor of the defendants on the basis of an issue that had not been raised in the trial court. Specifically, the plaintiff asserts that the Appellate Court improperly concluded that the trial court improperly had rendered a judgment of foreclosure of the mechanic’s lien in favor of the plaintiff because of the absence of a finding regarding the value of services rendered or materials furnished in the construction of the defendants’ home, as allegedly required under General Statutes § 49-33 (a). 4 Thus, the plaintiff contends, because the defendants did not challenge the propriety of the method used by the trial court to determine the amount secured by the mechanic’s lien in the trial court, the Appellate Court should not have reviewed this claim, and, further, should not have reversed the judgment of the trial court in favor of the plaintiff. The defendants respond that they could not have raised this issue regarding the amount secured by the mechanic’s lien in the trial court because “the claim of error on the claim for foreclosure of the mechanic’s hen arose after trial.” Specifically, the defendants maintain that they had no duty to anticipate at trial the error that would occur in the trial court’s written memorandum of decision, which was filed approximately five months after the end of the trial. We agree with the plaintiff, and, accordingly, we reverse the judgment of the Appellate Court.
In this state, a “mechanic’s lien is a creature of statute and gives a right of action which did not exist at common law. . . . The purpose of the mechanic’s lien is to give one who furnishes materials or services the security of the building
We begin our analysis with the language of the applicable statute, which provides: “If any person has a claim for more than ten dollars for
materials furnished or services rendered
in the construction, raising, removal or repairs of any building or any of its appurtenances or in the improvement of any lot or in the site development or subdivision of any plot of land, and the claim is by virtue of an agreement with or by consent of the owner of the land upon which the building is being erected or has been erected or has been moved, or by consent of the owner of the lot being improved or by consent of the owner of the plot of land being improved or subdivided, or of some person having authority from or rightfully acting for the owner in procuring the labor or materials, the building, with the land on which it stands or the lot or in the event that the materials were furnished or services were rendered in the site development or subdivision of any plot of land, then the plot of land, is subject to the payment of the claim.” (Emphasis added.) General Statutes § 49-33 (a). The statute is “designed to furnish security for a contractor’s labor and materials” and, as this court has noted previously, “is remedial in nature.”
Rene Dry Wall Co.
v.
Strawberry Hill Associates,
“We have long recognized that [t]he court shall not be bound to consider a claim unless it was distinctly raised at the trial or arose subsequent to the trial. . . . Practice Book § 60-5; see, e.g.,
River Bend Associates, Inc.
v.
Conservation & Inland Wetlands Commission,
In the present case, the trial court determined that the plaintiff had a valid claim for a mechanic’s hen on the defendants’ property, and awarded damages in the amount of $49,933.19 based on an analysis founded on the construction contract between the parties. The Appellate Court reversed the judgment of the trial court,
reasoning that the trial court had “improperly rendered a judgment of foreclosure on the mechanic’s lien in favor of the plaintiff without there being any finding regarding the value of services rendered or materials furnished in the construction of the defendants’ home,” as is purportedly required under § 49-33 (a).
Intercity Development, LLC
v.
Andrade,
supra,
The plaintiff claims that the defendants did not raise the issue of the proper calculation of the lien amount in the trial court, but instead did so for the first time on appeal in the Appellate Court. We agree. The record reveals that from the outset of this action to foreclose the mechanic’s lien, the plaintiff relied on the construction contract to calculate the lien amount. First, paragraph five of the original complaint contains allegations with respect to the contract amount, the extra work done and the payments made. In subsequent paragraphs of that complaint, the plaintiff alleged an unpaid balance due under the contract, and secured by the mechanic’s lien, of $162,000. Next, at trial, counsel for the defendants cross-examined a representative of the plaintiff, who testified that $162,000 was the amount of the
mechanic’s lien. That inquiry confirmed that the plaintiffs claim was based on the contract amount, and not on the value of the work in place at the defendants’ property.
5
6 Finally, in its posttrial brief, the plaintiffs claim for damages was set forth on a document captioned “Damages Work Sheet,” which was attached to the brief. The plaintiff listed $161,117 as the balance due the plaintiff as of the date of termination of the contract. After the contract had been terminated, the defendants made payments to third parties for work performed on the house in the amount of $66,617.81, which decreased the amount owed under the contract to
It is well established that claims that have not been properly raised at trial are not reviewable by this court. See
Simmons
v.
Simmons,
The defendants contend that their appeal of the trial court’s judgment on the claim for foreclosure of the
mechanic’s lien was properly before the Appellate Court because the claim of error arose after trial. We disagree. As previously set forth herein, the plaintiffs method of calculating the lien amount was set forth in its complaint, in testimony at trial and in its posttrial brief. It therefore became the defendants’ responsibility to “distinctly raise” its issue with regard to calculation of the lien amount in order to preserve the issue for appeal in accordance with Practice Book § 60-5. After the trial court’s memorandum of decision was filed, the defendants could have filed a motion to reargue pursuant to Practice Book § 11-12 specifically detailing their dispute regarding the calculation of the mechanic’s
II
On appeal in this court, the defendants claim that the Appellate Court improperly affirmed the decision of the trial court granting the plaintiffs posttrial motion to amend its complaint to include claims for breach of contract. Specifically, the defendants assert that they were prejudiced by the trial court’s decision on this issue because, at the time of trial, they had no notice that their purported breach of contract was a material issue in the plaintiffs case, and, consequently, had no reason to raise appropriate defenses. We find this claim to be unavailing.
“Our standard of review of the [defendants’] claim is well settled. While our courts have been liberal in permitting amendments . . . this liberality has limitations. Amendments should be made seasonably. Factors to be considered in passing on a motion to amend are the length of the delay, fairness to the opposing parties and the negligence, if any, of the party offering the amendment. . . . Whether to allow an amendment is a matter left to the sound discretion of the trial court. This court will not disturb a trial court’s ruling on a proposed amendment unless there has been a clear abuse of that discretion. ... It is the [defendants’] burden in this case to demonstrate that the trial court clearly abused its discretion.” (Internal quotation marks omitted.)
Dow & Condon, Inc.
v.
Brookfield Development Corp.,
In the present case, the mechanic’s lien at issue and the action to foreclose the hen arose out of a dispute between the parties, that in turn, arose out of the contract for the construction of the defendants’ house. As the Appellate Court observed, “the original complaint
for foreclosure of the mechanic’s lien followed from the contractual dealings of the parties. Contrary to the defendants’ assertion that they were prejudiced because ‘at the time of trial [they] had no notice that their own purported breach of contract was a material issue,’ the fulfillment of contractual obligations of the parties constituted the primary focus of the trial. Indeed, the defendants raised the issue of the quality of the
The judgment of the Appellate Court is reversed in part and the case is remanded to that court with direction to affirm the judgment of the trial court.
In this opinion the other justices concurred.
Notes
The plaintiff appealed, and the defendants cross appealed, from the judgment of the Appellate Court. We granted both the plaintiffs petition for certification to appeal and the defendants’ cross petition for certification to appeal.
Intercity Development, LLC
v.
Andrade,
People’s Bank and Eastern Water Development Company, Inc., also were named as defendants in the original action. Another party, Northeast Builders Supply and Home Centers, LLC, subsequently was granted permission to be added as a party defendant. These parties are not involved in this appeal. References herein to the defendants are to Joao Andrade and Irene Andrade only.
The plaintiffs amended complaint added claims for breach of contract and quantum meruit. The trial court found for the plaintiff on the breach of contract count, but found for the defendant on the quantum meruit count.
General Statutes § 49t33 (a) provides: “If any person has a claim for more than ten dollars for materials furnished or services rendered in the construction, raising, removal or repairs of any building or any of its appurtenances or in the improvement of any lot or in the site development or subdivision of any plot of land, and the claim is by virtue of an agreement with or by consent of the owner of the land upon which the building is being erected or has been erected or has been moved, or by consent of the owner of the lot being improved or by consent of the owner of the plot of land being improved or subdivided, or of some person having authority from or rightfully acting for the owner in procuring the labor or materials, the building, with the land on which it stands or the lot or in the event that the materials were furnished or services were rendered in the site development or subdivision of any plot of land, then the plot of land, is subject to the payment of the claim.”
“[The Plaintiff]: . . . [T]he $162,000 was what I was due for the balance of the entire contract. We came up with that number, that’s what I was due on the entire contract.
“[The Defendants’ Counsel]: That’s what you were due under the entire contract?
“[The Plaintiff]: Correct.
“[The Defendants’ Counsel]: That was not the value of the work that you had done up to that point in time?
“[The Plaintiff]: Correct.”
We express no opinion with regard to the correctness of the Appellate Court’s interpretation of § 49-33 (a).
