INTERAMERICAN ENG. v. Palm Beach CountyINTERAMERICAN ENG. v. Palm Beach County
INTERAMERICAN ENGINEERS AND CONSTRUCTORS CORPORATION, Aрpellant,
v.
PALM BEACH COUNTY HOUSING AUTHORITY, Appellee.
District Court of Appeal of Florida, Fourth District.
*880 Robert A. Hingston of Welbaum, Zook & Jones, Coral Gables, for appellant.
Donna H. Stinson of Moyle, Flanigan, Katz, FitzGerald & Sheehan, P.A., Tallahassee, for appellee.
MAY, MELANIE G., Associate Judge.
A contract dispute between Interamerican Engineers and Constructors Corp. and Palm Beach County Housing Authority lies at the heart of this appeal. The nuances of the doctrine of sovereign immunity created the legal issues. From a directed verdict in favor of Palm Beach County Housing Authority, Interamerican appeals.
In 1983, the parties entered into an agreement for the construction of a HUD projeсt. Despite best laid plans, the contractor encountered unexpected obstacles throughout the construction. These obstaсles included the necessity of demucking the construction site, obtaining the proper roof warranty, water hookup to the site, and difficulty with the fire marshal.
These obstacles caused delays in the construction, which the contractor attempted to overcome by accelerating the work, which in turn increased overhead costs and expenses. The contractor sought recovery for these increased сosts and expenses. Despite the contractor's failure to comply with contractual provisions requiring submissions for additional time and expenses in a prescribed manner, the Housing Authority paid some of the claims and denied others. During the litigation, the contractor maintained that the conduct between the parties had waived the contractual prerequisites; however, the County adhered to contractual provisions to ward off the claims.
At the start of the trial, the court granted the Housing Authority's Motion in Limine, prohibiting the contractor from introducing evidence оn the claims for overhead and home office expenses. The trial court subsequently granted the Housing Authority's motion for directed verdict on thе remaining claims and the contractor's request for prejudgment interest. The contractor appeals.
The Motion In Limine A Procedural Error
While the trial court discussed the doctrine of sovereign immunity in granting the Motion in Limine, the contract's wording appears to have been the basis of the court's decision. The contract provided specific allowances for overhead and general office expenses associated with changes in the work. Using this provision, the trial court ruled that the contractor would be limited to the percentage allowance called for in the contract and denied the contractor the opportunity to present any evidence for claims in excess of the designated allowаnce.[1]
*881 A motion in limine is not a substitute for a motion for summary judgment. Buy-Low Save Centers, Inc. v. Glinert,
Sovereign Immunity Immune or Not
After the plaintiff presented evidence on the remaining claims, the Housing Authority moved for directed verdict relying on the doctrine of soverеign immunity. It argued that the damages sought by the contractor were not expressly covered under the written contract. As such, the Housing Authority was immune from suit. Thе contractor argued that the Housing Authority's interpretation of existing case law on sovereign immunity was much too narrow and that as long as a writtеn contract existed between the parties, suit could be brought on express and implied covenants of the written agreement. The trial cоurt took the narrow, constrained interpretation and granted the Housing Authority's motion for directed verdict. In doing so, it erred.
We begin our journey through the land of sovereign immunity as it relates to contractual claims with Pan-Am Tobacco v. Department of Corrections,
Subsequent to Pan-Am, the Second District decided Southern Roadbuilders v. Lee County,
Two years later, this court decided Champagne-Webber, Inc. v. City of Fort Lauderdale,
Apparently, the trial court in this case believed that if the contract was either silent on an issue or required a "written" document to request additional time or make a claim and none existed, then Southern Roadbuilders protected the gоvernment entity from liability. Because the contractor had not complied with the time deadlines or written requirements of the express contrаct in requesting additional time and making claims, the trial court held the sovereign immunity doctrine barred the claim.
In doing so, the trial court appeаrs to have misinterpreted our holding in Champagne-Webber. For this reason, we must reverse and reiterate this court's prior holding. As long as an express written agreement exists, the basis for a breach of contract suit also exists and may include claims *882 based upon implied covenants within the agreement.
Prejudgment Interest
The last issue concerns the trial court's entry of directed verdict on the contractor's only remaining claim for prejudgment interest. The contractor sought to recover interest from the time payment was allegedly due on balances and claims paid by the Housing Authority until the time payment was made. The trial court disallowed the interest claim. We find nо error in the trial court's decision on this issue. See, e.g., Chiles v. United Faculty of Florida,
As the Florida Supreme Court noted in Broward County v. Finlayson,
We, therefore, reverse the trial court's ruling on the Motion in Limine due to the procedural imperfection in its hаndling. We also reverse the court's entry of a directed verdict on the issue of sovereign immunity and remand the case for further handling consistent with this opinion. We affirm the trial court's handling of the prejudgment interest issue.
STONE, J., and WALDEN, JAMES H., Senior Judge, concur.
NOTE: WALDEN, JAMES H., Senior Judge, did not participate in oral argument but has reviewed the presentation made at that proceeding.
NOTES
Notes
[1] The claims for overhead and office expenses were allegedly incurred due to the various delays in the construction process.
[2] The First District noted Champagne-Webber with approval in Phillips & Jordan, Inc. v. Florida Dept. of Transp.,