Case Information
*1 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA INTELECT CORPORATION, :
:
Plaintiff, : Civil Action No.: 15-0902 (RC) :
v. : Re Document Nos.: 5, 11 :
CELLCO PARTNERSHIP GP, et al. , :
:
Defendants. :
MEMORANDUM OPINION
D ENYING D EFENDANTS ’ M OTION TO T RANSFER V ENUE AND G RANTING IN P ART AND D ENYING IN P ART D EFENDANTS ’ M OTION TO D ISMISS I. INTRODUCTION
In 2009, a consortium of four cellular telephone carriers (collectively “Defendants” or the “Carrier Consortium”), entered into a Master License Agreement with the Washington Metropolitan Area Transit Authority (“WMATA”) for the design and construction of a wireless communications infrastructure that would allow WMATA riders to use their cellular phones in Metrorail tunnels and stations. In this action, Plaintiff Intelect Corporation (“Intelect”) claims that the Carrier Consortium failed to ensure that the general contractor they hired to undertake the WMATA project, Powerwave Technologies, Inc. (“Powerwave”), obtained the required surety payment bond covering the entire contract price—upwards of $65 million—in order to assure payment to all of Powerwave’s subcontractors. Powerwave ultimately suffered financial difficulties and has since defaulted on its construction contract with the Carrier Consortium and *2 filed for bankruptcy in the District of Delaware. Because of Powerwave’s default and bankruptcy, Intelect claims that Powerwave failed to make payments on several invoices, and that a total of $1,013,016.83 remains due to Intelect. Intelect initiated this lawsuit not against Powerwave, but directly against the Carrier Consortium, contending that the Carrier Consortium knew that the project was not fully bonded, failed to inform Intelect and other subcontractors about that alleged problem, and, after Powerwave filed for bankruptcy, nevertheless induced Intelect to retain its employees by representing that the project would commence again in Spring 2013.
Now before the Court is Defendants’ motion to transfer venue to the United States District Court for the District of Delaware (ECF No. 5) and Defendants’ motion to dismiss this action for failure to state a claim (ECF No. 11). For the foregoing reasons, the Court will deny Defendants’ motion to transfer venue and will grant in part and deny in part Defendants’ motion to dismiss.
II. FACTUAL BACKGROUND In 2008, as a condition of receiving $1.5 billion in federal funding, Congress required WMATA to ensure “that customers of [WMATA’s] rail service . . . have access within the rail system to services provided by any licensed wireless provider . . . .” Passenger Rail Investment and Improvement Act of 2008, Pub. L. No. 110-432, Div. B, § 601(e)(1), 122 Stat. 4907, 4969; see also Am. Compl. ¶ 10, ECF No. 8. On February 26, 2009, WMATA’s governing board granted approval for WMATA “to enter into a Master License Agreement with the Carrier Consortium to design, build, operate, and maintain seamless wireless communications coverage *3 for 47 underground stations and 50.5 miles of tunnels” for the Carrier Consortium’s own use and for the use of WMATA and its customers. Am. Compl. ¶ 11. The contract required the Carrier Consortium to fund the Project at its own expense, and Intelect alleges that the Defendants essentially “assumed the role of Project Owner.” Id. ¶ 12. On June 18, 2009, Defendants hired Powerwave as the project’s general contractor. Id. ¶ 14. Powerwave, in turn, hired Intelect as a subcontractor on June 16, 2010, entering into a $5,629,122.26 subcontract under which Intelect was to complete a portion of the project. Id. ¶ 17. The specific contours of Intelect’s portion of the project are not described in the complaint.
Intelect alleges that WMATA’s “internal policies and standard contract forms” typically require its contractors to supply a payment bond “in the amount of . . . 100% of the contract” to ensure that all persons who supply labor and materials to the project are paid. Id. ¶ 13. Because the project was a “public-private partnership,” however, WMATA only required the Carrier Consortium to obtain a nominal bond, in lieu of a surety payment bond for the full contract price. Id. Intelect alleges that WMATA “rel[ied] on the Carrier Consortium to require its contractor to bond the Project in the full amount of the contract.” Id. The full amount of the project, according to the Carrier Consortium’s contract with Powerwave, was $65,671,000. Id. ¶ 14. And Intelect claims that, although the contract between the Carrier Consortium and Powerwave divided the project into four milestones, or “phases,” the Carrier Consortium’s contract with Powerwave nevertheless “required Powerwave to provide for bonding in the amount of 100% of the full contract price.” Id. ¶¶ 15–16.
Intelect alleges that Powerwave did obtain a bond, naming Defendants as joint obligees, but that the bond was only valued at $5,000,000—a small fraction of the contract price. ¶¶ 18–20 & Ex. A (providing a copy of the payment bond documents). Intelect thus contends that it *4 was apparent to Defendants on the face of the bond that Powerwave had failed to comply with the terms of the Powerwave-Carrier Consortium contract and had failed to secure the required bond. Id. ¶¶ 20–22.
Powerwave began to suffer financial difficulties in late 2012. As a consequence, Powerwave failed to make several payments to Intelect. In total, Intelect contends that invoices totaling $1,013,016.83 remain unpaid. Id. ¶¶ 23–24. Once Powerwave defaulted on its payment obligations, Intelect claims that one of its officers and its counsel both “requested a copy of the Powerwave Payment Bond” from the Carrier Consortium, which they “refused to provide.” Id. ¶ 30. Intelect states that it was only after it “was able to obtain a copy of the bond, indirectly, through its insurance agent, that Intelect discovered, in January 2013, that the bond was limited in amount and restricted to Phase I, and that the monies then due from Powerwave to Intelect were primarily for work performed in Phases II and III.” Id. ¶ 31.
Notwithstanding Powerwave’s failure to pay Intelect, Intelect “continued to supply labor and materials to the Project for the benefit [of] and use by the Carrier Consortium.” Id. ¶ 26. Intelect further claims that although Defendants “had actual knowledge that Powerwave was financially unstable” as of the fall of 2012, “and that the work being performed by Powerwave’s subcontractors and suppliers were not covered by the Payment Bond . . . the Carrier Consortium continued to accept the benefits of Intelect’s performance.” Id. ¶ 28. Moreover, as relevant to its promissory estoppel claim, Intelect alleges that “the Carrier Consortium represented to Intelect that work on the Project would resume in early Spring 2013, and requested that Intelect leave its equipment and materials on site, and to continue to maintain its labor force in place.” ¶ 80.
On January 28, 2013, Powerwave filed for bankruptcy in the United States Bankruptcy Court for the District of Delaware. See Chapter 11 Voluntary Petition, In re Powerwave Techs., *5 Inc. , No. 13-10134 (Bankr. D. Del. Jan. 28, 2013), ECF No. 1. Intelect filed a proof of claim in those bankruptcy proceedings seeking $1,013,017.00. See Defs.’ Mot. to Dismiss Ex. A, ECF No. 11 (attaching proof of claim). Separately, Intelect commenced this action in District of Columbia Superior Court against the Carrier Consortium. Intelect’s complaint seeks judgment in the amount of $1,013,016.83 on alternative theories of negligence, negligent misrepresentation, implied contract, unjust enrichment, constructive fraud, and as a third-party beneficiary to the various agreements between WMATA, Defendants, and Powerwave. See Am. Compl. at 15. Each of these counts are based on the Carrier Consortium’s alleged failure to ensure that the project was fully bonded or to advise Powerwave’s subcontractors that they might not be paid by the payment bond should Powerwave default on its obligations. See id. ¶¶ 29–77. Intelect also brings a separate claim of promissory estoppel seeking $400,000 it allegedly incurred in continuing to employ its employees when the Carrier Consortium represented that the project would resume in spring 2013 and asked that Intelect maintain its labor force in place. ¶¶ 80– 81.
Defendants removed the action to this Court on June 11, 2015, invoking diversity jurisdiction under 28 U.S.C. § 1332, and bankruptcy jurisdiction under 28 U.S.C. § 1334. See Notice of Removal at 6, ECF No. 1. Defendants have since filed a motion to transfer venue to the United States District Court for the District of Delaware, where Powerwave’s bankruptcy proceedings are ongoing, see Defs.’ Mot. to Transfer Venue, ECF No. 5, and a motion to dismiss Intelect’s Amended Complaint under Federal Rule of Civil Procedure 12(b)(6) for failure to state a claim, see Defs.’ Mot. to Dismiss, ECF No. 11.
III. ANALYSIS
The Court will first consider Defendants’ motion to transfer venue. Finding that the convenience of the parties and witnesses and the interest of justice weigh against transferring this case, the Court will deny that motion. As a result, the Court proceeds to consider Defendants’ motion to dismiss and, as explained below, will grant the motion in part and dismiss Counts II and V of the Amended Complaint, but will otherwise deny the motion.
A. Motion to Transfer Venue
Defendants seek to transfer this case to the United States District Court for the District of Delaware. Changes of venue in civil actions are generally governed by 28 U.S.C. § 1404(a), which states that: “For the convenience of parties and witnesses, in the interest of justice, a district court may transfer any civil action to any other district or division where it might have been brought or to any district or division to which all parties have consented.” 28 U.S.C. § 1404(a). A separate change of venue provision, 28 U.S.C. § 1412, applies when a party seeks to transfer a bankruptcy case or proceeding. Section 1412 provides that: “A district court may *7 transfer a case or proceeding under title 11 to a district court for another district, in the interest of justice or for the convenience of the parties.” 28 U.S.C. § 1412.
Defendants’ motion to transfer venue hollowly invokes 28 U.S.C. § 1412, and does little to justify the existence of bankruptcy jurisdiction. In their opening motion, Defendants argue in a footnote that this action “involves matters that are both ‘core’ and that ‘arise under’ title 11,” specifically referencing Count VII of Intelect’s original complaint. See Defs.’ Mot. to Transfer Venue at 2 n.3; Notice of Removal Ex. A, ¶¶ 78–84 (reproducing initial complaint, including Count VII). That Count alleged that Defendants had converted certain Intelect property Defendants “purported to purchase . . . in a bankruptcy-court approved transaction, notwithstanding actual knowledge that such property was owned by Intelect.” Notice of Removal Ex. A, ¶ 81. Defendants contend that title to this property was transferred to them pursuant to an order of the Bankruptcy Court approving a settlement agreement between Powerwave and Defendants, and therefore argue that Count VII represents a direct challenge to the Settlement Approval Order. See Defs.’ Mot. to Transfer Venue at 2 n.2, 4; Notice of Removal at 8 (arguing that Count VII “‘arises under’ and ‘arises in’ Powerwave’s Bankruptcy Case” because that count “directly implicates—on the face of the Complaint—the Delaware Bankruptcy Court’s Settlement Approval Order”).
Perhaps in an effort to counter that argument, Intelect amended its complaint to omit
Count VII after Defendants filed their motion to transfer venue,
see generally
Am. Compl., and
now argues in a single, four-sentence paragraph in opposition to Defendants’ motion to transfer
that the absence of Count VII from this case “moots the Motion to Transfer.” Pl.’s Opp’n to
under either § 1412 or § 1404(a), the Court need not resolve the question here.
Cf. City of
Liberal
,
Defs.’ Mot. to Transfer Venue at 1, ECF No. 12. Intelect is plainly incorrect. It ignores the bulk of Defendants’ motion, which specifically discusses the remaining counts of the complaint and raises arguments for transferring this case on the basis of those other counts. See Defs.’ Mot. to Transfer Venue at 3–4; Defs.’ Reply Supp. Mot. to Transfer Venue at 1, ECF No. 16 (reiterating these points). Thus, to the extent that Intelect’s unsupported statement is intended to imply that the sole ground for invoking § 1412 in support of transferring this case was Count VII, the Court does not share that understanding. On the contrary, Defendants’ Notice of Removal explicitly contends that “Counts 1 through 6 ‘relate to’ the Powerwave Bankruptcy Case” because “[t]hose counts seek to hold Defendants liable for Powerwave’s debts” and seek to recover the same amount that Intelect seeks on its proof of claim in the bankruptcy proceeding. Notice of Removal at 7–8.
Nevertheless, with Count VII of the original complaint no longer a part of this case, the
application of § 1412 depends upon a finding that Counts I through VI of the Amended
Complaint “relate to” the Powerwave bankruptcy proceedings. Briefly stated, the Court has
considerable doubt that they are. While the D.C. Circuit has not yet discussed the contours of
“related to” bankruptcy jurisdiction, the Supreme Court has generally agreed with the test
expressed by the Third Circuit in
Pacor, Inc. v. Higgins
,
In the circumstances of this case, the question is a close one. On the one hand, it is
somewhat difficult to conclude that this action is “related to” the Powerwave bankruptcy action.
Powerwave is not a party to this action, and no monetary recovery is being sought from directly
from Powerwave.
See Abbey
,
On the other hand, Defendants’ Notice of Removal posits that resolution of Counts I
through VI will have a “conceivable effect” on the Powerwave bankruptcy case because “any
award of damages would relieve Powerwave of its obligation to satisfy these amounts” and
therefore “impact Powerwave’s liability to Intelect.” Notice of Removal at 8;
cf. HH1, LLC v.
Lo’r Decks at Calico Jacks, LLC
, Adv. Case No. 10-02004,
The Court is inclined to think that Intelect’s claims in this case do not “relate to” the Powerwave bankruptcy proceeding in the legal sense. Intelect does not claim that Defendants are guarantors of Powerwave’s obligations to Intelect. And Intelect’s claims here arise out of Defendants’ own actions, so it is therefore unlikely that the Court will have to meaningfully consider Powerwave’s liability to resolve Intelect’s claims against the Carrier Consortium. If the Court is not being asked to determine Powerwave’s liability, then it is not immediately clear that a successful recovery against the Defendants here would lessen or eliminate Powerwave’s liability under the proof of claim. If anything, Defendants’ factual proposition may only follow in the opposite direction: because Intelect is seeking recovery on Counts I through VI of a sum identical to the amount it alleges remain due from Powerwave, if Intelect were to recover from Powerwave to some degree on its proof of claim, that might eliminate some or all of the recovery Intelect seeks from Defendants in this action.
In any event, the Court declines to definitively resolve the question. As several courts
have noted, § 1412 and § 1404(a) demand essentially the same inquiry.
See
15 Charles Alan
Wright, Arthur R. Miller & Edward D. Cooper,
Federal Practice & Procedure
§ 3843, at 45–46
(4th ed. 2013) (explaining that “although bankruptcy matters are governed by their own transfer
statute, 28 U.S.C.A. § 1412, courts have held that this provision requires essentially the same
analysis and turns on the same issues as the transfer of civil actions under Section 1404(a)”);
*12
accord, e.g.
,
New Eng. Wood Pellet, LLC v. New Eng. Pellet, LLC
,
Consequently, the Court will consider Defendants’ motion to transfer venue under § 1404(a) but notes that its conclusion would remain the same if § 1412 applies.
1. Legal Standard
“For the convenience of parties and witnesses, in the interest of justice, a district court
may transfer any civil action to any other district or division where it might have been brought
. . . .” 28 U.S.C. § 1404(a). Section 1404(a) vests “discretion in the district court to adjudicate
motions to transfer according to an ‘individualized, case-by-case consideration of convenience
and fairness.’”
Stewart Org., Inc. v. Ricoh Corp.
,
Accordingly, the defendant must make two showings to justify transfer. First, the
defendant must establish that the plaintiff originally could have brought the action in the
proposed transferee district.
Van Dusen
,
2. Application
Because Defendants focus on § 1412 and assume the existence of bankruptcy
jurisdiction, they do not directly address the first showing under § 1404(a): whether the plaintiff
originally could have brought the action in the proposed transferee district.
Van Dusen
, 376 U.S.
at 616. That showing appears to be satisfied here, even if there is no “related to” bankruptcy
jurisdiction over this action under 28 U.S.C. § 1334(b). “To transfer a case, the transferor
court must find that the intended transferee court has personal jurisdiction and is an appropriate
venue.”
Virts v. Prudential Life Ins. Co.
,
Despite clearing this first hurdle, the Court nevertheless concludes that neither the public nor the private considerations indicate that transferring this case would further the convenience of the parties and the witnesses or the interest of justice.
Considering the private interests, Defendants posit that because the parties have all
“actively participated in the Powerwave Bankruptcy case,” and because Intelect “is
headquartered in Baltimore,” Delaware would be “nearly equally convenient for Plaintiff as is
Washington, D.C.” Defs.’ Mot. to Transfer Venue at 5. Even if Delaware would be equally
convenient, however, “a plaintiff’s choice of forum is ordinarily ‘a paramount consideration’ that
is entitled to ‘great deference’ in the transfer inquiry.”
F.T.C. v. Cephalon, Inc.
, 551 F. Supp. 2d
21, 26 (D.D.C. 2008) (quoting
Thayer/Patricof Educ. Funding LLC v. Pryor Res.
, 196 F. Supp.
2d 21, 31 (D.D.C. 2002)). While “[d]eference to the plaintiff’s chosen forum is minimized . . .
where that forum has no meaningful connection to the controversy,”
United States v. H&R
Block, Inc.
,
Defendants counter that this lawsuit presents “precisely the situation where Plaintiff’s
original choice of venue
should
be disturbed” because it “assert[s] claims that duplicate [the
Plaintiff’s] Proof of Claim.” Defs.’ Mot. to Transfer Venue at 4. But, as already explained, even
though Intelect seeks to recover a value identical to the amount Powerwave owes to it, its
claims
are distinct and raise separate grounds for imposing liability on Defendants, not Powerwave.
And if Defendants’ argument intends to invoke the “home court” presumption that many courts
have applied when considering whether to transfer bankruptcy proceedings, the Court’s doubts
that “related to” jurisdiction exists render that presumption largely inoperative here.
See, e.g.
,
Irwin v. Beloit Corp. (In re Harnischfeger Indus., Inc.)
,
For similar reasons, the Court finds Defendants’ arguments that Powerwave “will be a central party in this action,” that it will be “most convenient for potential witnesses and the parties to adjudicate Plaintiff’s disputes with both Powerwave and Defendants only once,” and that Powerwave “will be subject to third party discovery” all fail to weigh in favor of transfer. Defs.’ Mot. to Transfer Venue at 5. Powerwave is not a party to this dispute, nor does Intelect assert any claim against Powerwave. Although the Court cannot foreclose the possibility of third party discovery, presumably many of the contractual documents relevant to Intelect’s claims against Defendants, specifically the Carrier Consortium-WMATA contract documents and the Carrier Consortium-Powerwave contract, are likely already in Defendants’ possession. And the *16 Defendants do not explain exactly what witnesses or documents they will be unable to obtain if this case is not tried in Delaware, or where those witnesses or documents are actually located. Having failed to address these points, Defendants have likewise failed to carry their burden to show that either the convenience of the witnesses or the ease of access to sources of proof weigh in favor of transfer. Thus, the Court concludes that the private factors weigh against transfer.
The public interests also do not weigh in favor of transfer. Defendants assert that they
will “seek to have this matter referred to the Delaware Bankruptcy Court,” and that the
“Delaware Bankruptcy Court has an interest in adjudicating” Counts I through VI.
Id.
at 1, 4.
Yet, again, the Court emphasizes that Intelect’s claims cover distinct theories of liability against
Defendants, not Powerwave. Given the Court’s skepticism that the remaining counts even
“relate to” the Powerwave bankruptcy proceedings in the legal sense, it is doubtful that judicial
economy will be served through a transfer or that transferring this case will “reduce duplicative
discovery and avoid the risk of inconsistent judgments.” at 3. “Related to” cases are non-
core proceedings under 28 U.S.C. § 157(c), which means that, absent the consent of the parties,
the bankruptcy court may only submit proposed findings of fact and conclusions of law.
See
28
U.S.C. § 157(c);
United States v. Inslaw, Inc.
,
Of course, it is possible that any favorable recovery Intelect obtains from Defendants on Counts I through VI will be offset by Intelect’s recovery, if any, on the proof of claim it has submitted in the Powerwave bankruptcy proceedings. The damages issues in this case may overlap in that respect. But the Court does not believe that the factual and legal questions pertinent to the liability issues concerning Intelect’s distinct claims against the Carrier Consortium are likely to overlap considerably with the Powerwave bankruptcy proceedings. And Intelect’s promissory estoppel claim based on representations Defendants allegedly made *18 directly to Intelect after Powerwave defaulted on its contract obligations to Intelect bears no relation to the bankruptcy proceedings.
Finally, Defendants have not addressed the remaining two public interest considerations:
the “transferee’s familiarity with the governing law” and “the relative congestion of the courts of
the transferor and potential transferee.”
Onyeneho
,
Absent a showing that the District of Delaware would prove more convenient to the
parties or judicial economy would be substantially served by considering this case in tandem
with the Powerwave bankruptcy proceedings, the Court believes that “[t]he deference owed to
the plaintiffs’ choice of forum tips the scale against the transfer motion.”
Sparshott v. Feld
Entm’t, Inc.
,
B. Motion to Dismiss
Defendants have also moved to dismiss all seven counts of Intelect’s Amended Complaint under Federal Rule of Civil Procedure 12(b)(6) for failure to state a claim. As explained below, the Court agrees that Intelect has failed to state a claim for negligent misrepresentation (Count II), constructive fraud (Count VI), and—at least considering complaint’s current factual allegations—promissory estoppel (Count VII). On the remaining counts, however, the Court concludes that Intelect has plausibly stated a claim and therefore will deny Defendants’ motion to dismiss as to Counts I, III, IV, and V.
1. Legal Standard
The Federal Rules of Civil Procedure require that a complaint contain “a short and plain
statement of the claim” in order to give the defendant fair notice of the claim and the grounds
upon which it rests. Fed. R. Civ. P. 8(a)(2);
accord Erickson v. Pardus
,
2. Choice of Law Analysis
The Court must first identify the law that governs Intelect’s claims. The parties dispute what law applies to this action. Defendants urge that Maryland law should apply because Intelect is a corporate citizen of Maryland, because a portion of the project was performed in Maryland, and because, they claim, any injury Intelect suffered occurred in Maryland. See Defs.’ Mem. Supp. Mot. to Dismiss at 7 (“Defs.’ Mem. Supp.”), ECF No. 11; Defs.’ Reply Supp. Mot. to Dismiss at 3 (“Defs.’ Reply”), ECF No. 15. Intelect, by contrast, contends that District of Columbia law should apply because the location of the project at issue here—the Metrorail stations and tunnels—is primarily in the District and the parties’ relationship is therefore centered in the District of Columbia. See Pl.’s Mem. in Opp’n to Defs.’ Mot. to Dismiss at 3–5 (“Pl.’s Mem. Opp’n”), ECF No. 13.
“A federal court sitting in diversity must apply the choice-of-law rules of the forum
state—here, the District of Columbia.”
In re APA Assessment Fee Litig.
,
While the D.C. Circuit has not yet addressed the issue, no party disputes that state law, and not federal law, governs Intelect’s claims against Defendants. In similar circumstances, the D.C. Circuit has held that if “a federal court applies state law when it decides an issue not addressed by federal law, regardless of the source from which the cause of action is deemed to have arisen for the purpose of establishing federal jurisdiction,” a federal court should adopt the choice of law rules of the state in which the court sits because “[a] choice-of-law rule is no less a rule of state law than any other.” A.I. Trade Fin., Inc. v. Petra Int’l Banking Corp. , 62 F.3d 1454, 1463 (D.C. Cir. 1995). As a result, the Court’s choice of law analysis would be identical even if federal jurisdiction in this case is grounded on 28 U.S.C. § 1334.
conflict” does exist, “the court must go on to determine which of the relevant jurisdictions has the ‘more substantial interest’ in having its law applied to the case under review.” To make that determination, a court must consider the four significant relationship factors “enumerated in the Restatement (Second) of Conflict of Laws § 145” which include: (1) “the place where the injury occurred,” (2) “the place where the conduct causing the injury occurred,” (3) “the domicile, residence, nationality, place of incorporation and place of business of the parties,” and (4) “the place where the relationship is centered.” District of Columbia v. Coleman , 667 A.2d 811, 816 (D.C. 1995) (quoting Restatement (Second) of Conflict of Laws § 145).
Here, the parties do not meaningfully engage with the first step of the analysis. By
proceeding directly to analyzing which jurisdiction has the most significant relationship over this
dispute, the parties seem to assume that there is a true conflict among Maryland and District of
Columbia law. That implicit assumption makes some sense, as Maryland would appear to have
an interest in protecting its corporate citizen, Intelect, while the District of Columbia presumably
has an interest in regulating the course of business transactions engaged in the forum and the
agreements governing the projects taking place there.
Cf. Washkoviak
,
But even if Maryland and the District of Columbia both have an interest in having their
law applied to a case like this one, the parties do not discuss whether “the law of the competing
*23
jurisdictions is different.”
GEICO
,
Regardless, upon consideration of the substantial relationship factors and the present
record, the Court concludes that District of Columbia law applies. In their opening
memorandum, Defendants only reference the first factor, the place of the injury, and generally
assert that any injury Intelect suffered “would have occurred in Maryland, the state under which
it is organized and authorized to conduct business.” Defs.’ Mem. Supp. at 7. In reply,
Defendants go a bit further to argue that the injury underlying Intelect’s negligent
misrepresentation claim occurred in Maryland, where Intelect “received the alleged
*24
misrepresentations.” Defs.’ Reply at 3. Plaintiff counters that its location “is sheer
happenstance.” Pl.’s Mem. Opp’n at 3. District of Columbia courts agree that the place of injury
in these types of cases is not particularly significant when weighing the jurisdictions’ relative
connections to the case.
See, e.g.
,
Washkoviak
,
While neither party discusses the second Restatement factor, construing the reasonable
factual inferences from Intelect’s complaint in its favor,
Washkoviak
,
That two factors favor application of Maryland law and two favor District Columbia law
might alone counsel in favor of applying District of Columbia law as a tie-breaker.
Washkoviak
,
The Court does acknowledge that, given “the lack of evidence available in the record defining the connections between appellants’ claims and either jurisdiction,” it is somewhat “difficult to make any kind of qualitative judgment at all.” at 182. The District of Columbia Court of Appeals instructs that “any uncertainty” with respect to choice of law questions at the motion to dismiss stage should be resolved in favor of the plaintiff and, furthermore, that if the court “cannot determine from the pleadings which jurisdiction has a greater interest in the controversy” the court “must apply the law of the forum state”—in this case the District of Columbia. Id. With this guidance in mind, this Court holds that “within the present context of a 12(b)(6) motion to dismiss,” and given the limited factual presentation so far provided by the parties, it is not clear that Maryland law should be applied rather than District of Columbia law. Id. at 183. In so concluding, however, the Court “leave[s] open the possibility that, after both parties have been afforded the opportunity to conduct discovery and present evidence,” it will ultimately be the case that Maryland, rather than the District of Columbia, has “a greater interest . . . in the resolution of this controversy.” Id .
3. Count I: Negligence
Intelect’s first claim is for negligence. To state a claim of negligence under District of
Columbia law, “a plaintiff must allege ‘(1) a duty, owed by the defendant to the plaintiff, to
conform to a certain standard of care; (2) a breach of this duty by the defendant; and (3) an injury
to the plaintiff proximately caused by the defendant’s breach.’”
Friends Christian High Sch. v.
Geneva Fin. Consultants
,
Here, Intelect alleges that “[e]ach of the members of the Carrier Consortium, in their capacities as obligees on the Powerwave Payment Bond, had a duty of care to those persons who supplied labor and materials to the Project to assure them of full and complete coverage, not just partial coverage for Phase I,” and that the Defendants “negligently breached their duty of due care to Intelect by their failure to assure full and complete coverage under the Payment Bond.” Am. Compl. ¶¶ 32, 34. Intelect contends that as a “direct and proximate result” of that breach, *28 it “suffered a loss in the amount of $1,013,016.83 that would have been covered by the Powerwave Payment Bond had the bond covered the entire Project, not just Phase I.” Id. ¶ 35.
Defendants’ motion focuses solely on the duty element, claiming that Intelect has failed to “identify and adequately plead a legal duty the Carriers owe to Intelect.” Defs.’ Mem. Supp. at 7. They cite the Second Restatement of Torts for the proposition that “[t]he fact that [an] actor realizes or should realize that action on his part is necessary for another’s aid or protection does not of itself impose upon him a duty to take such action.” Defs.’ Mem. Supp. at 8 (quoting Restatement (Second) of Torts § 314 (Am. Law Inst. 1965)). They claim that “a contract between third parties . . . is insufficient to establish any duty the Carriers separately owe to Intelect.” at 9–10.
In response, Intelect contends that “having undertaken to obtain a bond, the Carriers had a duty to obtain an effective bond, not one that was the practical equivalent of no bond at all.” Pl.’s Mem. Opp’n at 5 (emphasis in original). And Intelect’s complaint seems to refer generally to a duty arising as a result of the Defendants’ “capacities as obligees on the Powerwave Payment Bond.” Am. Compl. ¶ 32. On the one hand, this allegation, and Intelect’s arguments in its opposition, could be read broadly as a claim that whenever a party requires a payment surety bond from another, that party undertakes a duty to ensure a bond that covers the entirety of the project. Yet, Intelect cites no cases—in the District of Columbia or otherwise—accepting such a far-reaching argument. Intelect does invoke several out-of-jurisdiction cases in which courts have held that plaintiffs could bring a negligence claim against a public entity for its failure to assure full bond coverage of a public project. But in each of those cases the court found that the discussion of that duty until its analysis of the negligent misrepresentation count, and confines its discussion of Count I to Intelect’s alleged duty to assure full bond coverage.
public entity’s duty arose from a specific state or federal statute that required the governmental
entity to verify or ensure the validity of a payment bond that was secured.
[13]
See, e.g.
,
Kammer
Asphalt Paving Co. v. E. China Township Schs.
,
On the other hand, however, when read with reference to the other allegations made in the complaint, Intelect does plausibly allege a source of Defendants’ duty to obtain a payment *30 surety bond that is specific to the circumstances of this case: the WMATA-Carrier Consortium contract. Intellect emphasizes the “public-private partnership” nature of the project, and alleges that “WMATA only required the Carrier Consortium to obtain a nominal bond, relying on the Carrier Consortium to require its contractor to bond the Project in the full amount of the contract.” Am. Compl. ¶ 13. Intelect claims that the “Carrier Consortium assumed the role of Owner” and that “Plaintiff’s cause of action is grounded on the failure of the Carrier Consortium to provide full surety bond coverage, as required by the contract documents, to assure payment to those persons supplying labor and material to the Project.” ¶ 2. Read with reference to these allegations, it is possible to read Intelect’s allegation that the Defendants “negligently breached their duty of due care to Intelect by their failure to assure full and complete coverage under the Payment Bond,” id. ¶ 34, as encompassing a duty that arose as a result of the WMATA-Carrier Consortium contract, see Pl.’s Mem. Opp’n at 5 (“[H]aving undertaken to obtain a bond, the Carriers had a duty to obtain an effective bond, not one that was the practical equivalent of no bond at all.” (emphasis in original)).
As Intelect points out, the Restatement explains that there are exceptions to the general
principle that an actor has no duty to affirmatively act to protect another.
See
Pl.’s Mem. Opp’n
at 7;
see also
Restatement (Second) of Torts § 314 cmt. a (“[A]n actor may have committed
himself to the performance of an undertaking, gratuitously
or under contract
, and so may have
assumed a duty of reasonable care of the other,
or even a third person
.” (emphasis added)). The
District of Columbia Court of Appeals, too, has “acknowledged that a legal duty arises when a
party undertakes to ‘render[] services to another which he should recognize as necessary for the
protection of a third person or his things . . .’”
Presley v. Commercial Moving & Rigging Inc.
,
In Presley , for example, the court considered a plaintiff’s tort claim arising out of injuries he sustained after falling twenty feet from a cooling tower assembly on a State Department construction project. See id. at 880. One of the defendants, CRSS Constructors, Inc., had contracted with the General Services Administration (“GSA”) to serve as the contract compliance consultant for that construction project. Id. at 878. Among other things, CRSS’s contract with the GSA required it “to anticipate problems and immediately act to preclude or mitigate any negative effects on the construction project(s),” and to “employ inspectors who were responsible for scheduling, coordinating, and performing the actual specialized field work . . . .” Id. (internal quotation mark omitted). That contract was essential to the court’s *32 understanding of CRSS’s duty. The court explained that, “[t]hough [the plaintiff’s] claim is premised upon a tort theory,” the relevant contract “nevertheless remains central to our analysis of duty, as it defines the scope of the undertaking and the services rendered by CRSS.” Id. at 889. “[F]inding a common law duty depend[ed] primarily on whether CRSS should have recognized that its undertakings pursuant to the [] contract were necessary for the protection of Presley.” Id. Thus, “[b]y examining the scope of CRSS’[s] undertaking and services pursuant to the [] contract, we can then determine whether CRSS assumed a duty to exercise reasonable care in carrying out its contractual obligations that extended to workers such as Presley on the site.” Id .
The District of Columbia Court of Appeals was ultimately unpersuaded in
Presley
that a
duty arose “based upon the facts in [that] case,” but the court did note that “imposition of a duty
may be appropriate in other cases, with different contractual arrangements.” And that court
has cited approvingly to cases in the D.C. Circuit finding a common law duty to third parties
arising out of a contractual arrangement.
See Haynesworth
,
Here, at the motion to dismiss stage, the relevant contract documents are not before the
Court. Intelect has alleged that WMATA relied upon Defendants to obtain a surety bond and
*33
required only a nominal bond from Defendants. Am. Compl. ¶ 13. The scope of that obligation,
and the terms of those parties’ contract, “remains central” to the Court’s analysis of whether
Defendants owed any duty to Intelect in tort, as a subcontractor for whom the payment bond
would ostensibly benefit.
See Presley
,
Nevertheless, given Intelect’s factual allegations about the relationship between
WMATA and Defendants—and the agreement among those parties about Defendants’ obligation
to obtain a payment surety bond in the full amount of the contract price—the Court concludes
that Intelect has plausibly alleged a duty that could provide recovery in tort. The Court thereby
will deny Defendants’ motion to dismiss with respect to Count I, but declines to definitively
determine at this time whether Defendants owe a duty to Intelect.
Accord Jefferson v. Collins
,
The Court notes that a separate doctrine, the economic loss rule, may or may not pose a
problem for Intelect. Defendants invoke the rule in passing and in a single sentence of their
memorandum, but do not further develop the argument.
See
Defs.’ Mem. Supp. at 8–9.
“Generally, under the economic loss rule, a plaintiff who suffers only pecuniary injury as a result
of the conduct of another cannot recover those loses in tort.”
Aguilar v. RP MRP Wash.
Harbour, LLC
,
Yet, the contours of the economic loss rule are nuanced and it is not immediately clear to
the Court that the economic loss rule would necessarily operate to Intelect’s detriment on the
facts of this case.
See
3 Dan B. Dobbs, Paul T. Hayden & Ellen M. Bublick,
The Law of Torts
§
607 (2d ed. 2011) (“[T]he implication of references to ‘the’ economic loss rule that there is but a
*35
single overarching economic loss rule is misleading. Several discrete rules dominate the
decisions, not a single rule.”). In
Aguilar
, the District of Columbia Court of Appeals appeared to
be confronted with a situation in which plaintiffs claimed that their adverse economic
consequences were foreseeable to the defendants and that that foreseeability
alone
sufficed to
give rise to a duty of care.
See
As far as the Court can tell, the District of Columbia Court of Appeals has not refined or
further developed its economic loss rule since
Aguilar
was decided. Another Court in this
district, in a pre-
Aguilar
decision, seemed to view the doctrine as a limitation on tort recovery
even where an independent duty of care is potentially cognizable.
See Himmelstein
, 908 F.
*36
Supp. 2d at 58 (declining to decide at the motion to dismiss stage whether a “special relationship
between a creditor and debtor” suffices to “create[] an independent duty that would support a
negligence claim,” and permitting the claims to proceed, but nevertheless noting that the court
had “serious concerns” that the claims “may alternatively be barred by the economic-loss
doctrine”).
But see Aguilar
,
At this juncture, however, and pending further information about the parties’ contractual relationships, the Court concludes that Intelect has stated a sufficiently plausible claim of negligence to allow discovery to proceed.
*37 4. Counts II & VI: Negligent Misrepresentation & Constructive Fraud Intelect also brings related claims of negligent misrepresentation and constructive fraud.
Intelect’s negligent misrepresentation claim alleges that by undertaking “the duty to assure meaningful and effective coverage by the surety,” Defendants also undertook a “duty of due care . . . to advise [those persons who supplied labor and materials] that the Project was only partially bonded.” Am. Compl. ¶¶ 37, 40. “By its failure to advise Powerwave’s subcontractors and suppliers that they were at risk in working on Phases II and III of the Project,” Intelect contends that “the Carrier Consortium implicitly represented to such parties, including Intelect, that they would be paid by the Payment Bond surety if not paid by Powerwave.” Id. ¶ 41. Intelect further alleges that it “reasonably relied on the Payment Bond to obtain payment if not paid by Powerwave,” and that it “would not have entered into its Subcontract Agreement with Powerwave had Intelect known that the Project was only partially bonded.” Id. ¶ 39.
In support of its constructive fraud claim, Intelect similarly alleges that, because of the “payment procedures involved in the Project” and “the obligations contained in the Contract Documents that the Project be bonded, a special relationship of trust and confidence existed among the Carrier Consortium, Powerwave, and Intelect.” Id. ¶ 75. Thus, Intelect claims that “[t]he Carrier Consortium’s failure to advise Intelect that Intelect was providing labor and materials to the benefit of the Carrier Consortium at its risk . . . . constituted constructive fraud.” ¶ 76.
To state a claim for negligent misrepresentation under District of Columbia law, the plaintiff must show: (1) that the defendant “made a false statement or omitted a fact that he had a reasonable care by subcontracting with Powerwave without ascertaining whether a bond was in place, or without determining the value for which the project was bonded, contributory negligence might bar Intelect’s recovery.
duty to disclose,” (2) that the statement or omission “involved a material issue,” and (3) that the
plaintiff “reasonably relied upon the false statement or omission to his detriment.”
[17]
Redmond v.
State Farm Ins. Co.
,
Generally, “mere silence does not constitute fraud unless there is a duty to speak.”
Sundberg
,
Here, because Intelect does not allege that Defendants made any affirmative statements, Intelect must rely on a “duty to disclose” information to support its negligent misrepresentation and constructive fraud claims. Intelect does not claim that it has a fiduciary relationship with Defendants. Nor does Intelect allege a partial disclosure—or indeed any direct communication at all—with Defendants prior to either Powerwave’s default or Intelect’s entry into its subcontract with Powerwave on June 16, 2010 (the action it allegedly took after reasonably relying on the payment bond). See Id. at 287–88 (finding “no basis for imposing a duty to speak” where “plaintiffs do not allege any contact with the . . . Defendants prior to closing on the Property”). Finally, there is no indication that the amount of the payment bond obtained by Powerwave was unobservable or undiscoverable, nor does Intelect claim as much. Intelect in fact alleges the opposite. After Defendants allegedly “refused to provide” a copy of the bond, Intelect contends that it “was able to obtain a copy of the bond indirectly, through its insurance agent.” Am. Compl. ¶ 31.
At bottom, Intelect merely alleges that, by undertaking “the duty to assure meaningful
and effective coverage by the surety,” Defendants “
implicitly represented
to those persons who
*40
supplied labor and materials to the Project, including Intelect, that they would be paid by the
surety if not paid by Powerwave,” and had a “duty of due care . . . to advise them that the Project
was only partially bonded.” ¶¶ 37, 40 (emphasis added). But unlike with respect to their
allegations that Defendants had to
secure
the bond, Intelect alleges no duty on Defendants’ part
to affirmatively communicate to Powerwave’s subcontractors whether Powerwave had secured,
or had failed to secure, the bond. It may be that Intelect
assumed
such a bond had been secured,
and that Defendants negligently breached their duty under the WMATA-Carrier Consortium
contract to obtain that bond. But it does not automatically follow that Defendants were under
any additional affirmative duty to inform all subcontractors with whom they had not contracted
about the status or amount of that bond.
Accord Jefferson
,
For much the same reasons, Intelect has not supported its allegation that “a special
relationship of trust and confidence existed among the Carrier Consoritum, Powerwave[,] and
Intelect”—an additional element necessary for its constructive fraud claim. Am. Compl. ¶ 74;
see Cordoba Initiative
,
Intelect has not alleged facts sufficient to plausibly suggest the existence of a confidential relationship in this case; indeed, Intelect has done no more than make a conclusory allegation that a “special relationship of trust and confidence existed” among the parties. Am. Compl. ¶ 74. And based on what can be gleaned from the other allegations in the complaint, no facts plausibly support the existence of a confidential relationship. All parties are sophisticated business entities, and there is no indication that Intelect either entrusted its affairs to Defendants or was particularly susceptible to Defendants’ influence. The parties appear to have had, at most, only limited communication prior to Powerwave’s default and bankruptcy Cf. Cordoba Initiative , 900 F. Supp. 2d at 51 (finding a confidential relationship plausibly alleged where defendants had advised and supported plaintiff “over several years”). Thus, Intelect has not plausibly alleged the confidential relationship necessary to support its constructive fraud claim.
The Court will dismiss Counts II and VI of Intelect’s Amended Complaint.
5. Count III: Third-Party Beneficiary
Intelect also alleges that it is a third-party beneficiary of the contract documents. “A third
party may sue on a contract if the contracting parties intended the third party to benefit,” even if
the third party was not a party to that contract.
District of Columbia v. Campbell
, 580 A.2d
1295, 1302 (D.C. 1990);
see also W. Union Tel. Co. v. Massman Const. Co.
,
Here, Intelect plausibly alleges that it that it was an intended beneficiary of the “Contract Documents requiring full bonding” and the “Powerwave Payment Bond,” albeit by a somewhat attenuated series of incorporations within the contract documents. Am. Compl. ¶¶ 50, 53. As already explained, Intelect alleges that WMATA waived its normal bonding requirements in reliance upon the Carrier Consortium’s promise to obtain a bond, in the full contract price, from *43 its general contractor. ¶¶ 46–47. Accordingly, Intelect claims that the “purpose of the Payment Bond obtained by Powerwave . . . in addition to assuring payment to those persons who supplied labor and materials to the Project under contract with Powerwave, was to substitute the nominal bond which had been jointly obtained by each of the members of the Consortium with the Powerwave Bond.” Id. ¶ 48.
In their opening memorandum, Defendants’ only argument for dismissal is that “Intelect
does not specify any provision of a contract . . . that identifies Intelect as an intended third-party
beneficiary.” Defs.’ Mem. Supp. at 12. Yet, an intention to benefit a party directly need not be
express; it can also be implied.
Fort Lincoln Civic Ass’n
,
Defendants raise an additional argument for the first time in their reply. But “it is a well-
settled prudential doctrine that courts generally will not entertain new arguments first raised in a
reply brief.”
Lewis v. District of Columbia
,
Accordingly, the Court will deny Defendants’ motion with respect to the Count III.
6. Counts IV & V: Implied Contract & Unjust Enrichment
Intelect also asserts claims of implied contract (Count IV) and unjust enrichment (Count
V). “The District of Columbia recognizes causes of action for unjust enrichment and quantum
meruit as implied contract claims in which there is no express contract between the parties but
contractual obligations are implied, either in fact (quantum meruit) or in law (unjust
enrichment).”
Plesha v. Ferguson
,
While “the District of Columbia Court of Appeals uses the term ‘quantum meruit’ to
describe both forms of recovery, it distinguishes between these two causes of action.”
U.S. ex rel
Modern Elec., Inc. v. Ideal Elec. Sec. Co.
,
In urging the Court to dismiss these counts, Defendants’ sole argument is that an express
contract already covers this subject matter. Defs.’ Mem. Supp. at 13. It is true that, under
District of Columbia law, “[n]either form of restitution is available when there is an actual
contract between the parties.”
Ellipso, Inc. v. Mann
,
Moreover, as Intelect notes, the Third Restatement of Restitution definitively anticipates such situations. See Pl.’s Mem. Opp’n at 13. Comment a to § 25 explains that:
Most transactions for which restitution may be available by the rule of this section fall within one of two common (though nonexclusive) patterns. In a first set of cases, A is a subcontractor, B is a property owner, and C (now unavailable) is the general contractor with whom both parties have dealt. . . . In either setting, the exit or insolvency of C leaves A without compensation for work that was performed as requested. If a further consequence of the interrupted transaction is that B stands to obtain a valuable benefit without paying for it, the outcome may be one that the law will characterize as unjust enrichment.
Restatement (Third) of Restitution and Unjust Enrichment § 25 cmt. a (Am. Law Inst. 2010).
And the District of Columbia Court of Appeals has previously invoked § 25 of the Restatement
when considering unjust enrichment claims.
See Jordan Keys
,
*49 Here, while contracts existed between the Defendants and WMATA, the Defendants and Powerwave, and Powerwave and Intelect, there was no contract between the relevant parties: the Defendants and Intelect. Thus, the existence of other contracts will not bar Intelect’s implied-in- fact contract and unjust enrichment claims, and the Court will allow those claims to proceed.
7. Count VII: Promissory Estoppel
Intelect’s final count asserts a promissory estoppel claim. To state a claim for promissory
estoppel, a plaintiff “must show (1) a promise; (2) that the promise reasonably induced reliance
on it; and (3) that the promisee relied on the promise to his or her detriment.”
Myers v. Alutiiq
Int’l Solutions, LLC
,
Taken as true, Intelect’s complaint plausibly alleges a definite promise that it reasonably
relied upon. Intelect alleges that upon Powerwave’s default and bankruptcy, “all progress on the
Project was suspended.” Am. Compl. ¶ 79. Intelect further alleges that, “[i]n order to facilitate
*50
the prompt resumption of work under a replacement contractor, the Carrier Consortium
represented to Intelect that work on the Project would resume in early Spring of 2013, and
requested that Intelect leave its equipment and materials on site, and continue to maintain its
labor force in place.” ¶ 79. With a necessary inference, this promise is sufficiently definite to
state a claim at this stage, despite Defendants’ argument to the contrary.
See
Defs.’ Mem.
Supp. at 14. “[A] promise is ‘an expression of intention that the promisor will conduct himself
in a specified way
or bring about a specified result in the future
. . . .”
Choate v. TRW, Inc.
, 14
F.3d 74, 77–78 (D.C. Cir. 1994) (emphasis added) (quoting 1 Corbin on Contracts § 13 (1963)).
And that intention “need not contain language as specific and definite as that of an enforceable
contract.”
Osseiran v. Int’l Fin. Corp.
,
At present, however, Intelect’s complaint fails to allege how its reliance on that promise
worked to its detriment.
See Osseiran v. Int’l Finance Corp.
,
Accordingly, the Court will dismiss Intelect’s promissory estoppel claim based on the complaint in its current form. The Court will permit Intelect to seek leave to amend its *52 complaint within 14 days from the issuance of this memorandum opinion, however, to clarify the promise it alleges and to properly plead factual allegations supporting the detrimental reliance element of its promissory estoppel claim.
IV. CONCLUSION
For the foregoing reasons, Defendants’ Motion to Transfer Venue (ECF No. 5) is DENIED and Defendants’ Motion to Dismiss (ECF No. 11) is GRANTED IN PART AND DEINED IN PART . An order consistent with this Memorandum Opinion is separately and contemporaneously issued.
Dated: February 5, 2016 RUDOLPH CONTRERAS
United States District Judge
Notes
[1] Defendants claim that Intelect’s complaint fails to name them properly. See Defs.’ Mot. to Transfer Venue at 1 n.1, ECF No. 5. The parties agree, however, that the carriers do business under the following common names: Verizon Wireless, Sprint, AT&T, and T-Mobile. See id. ; Am. Compl. ¶¶ 4–8.
[2] At the motion to dismiss stage, the Court accepts the plaintiff’s factual allegations as
true.
See, e.g.
,
United States v. Philip Morris, Inc.
,
[3] As discussed below, Intelect initially brought a claim of conversion against Defendants but has since amended its complaint to withdraw that count.
[4] In fact, the law is potentially more nuanced. In addition to granting federal courts
exclusive jurisdiction over title 11 cases,
see
28 U.S.C. § 1334(a), Congress has granted original,
but not exclusive, bankruptcy jurisdiction to federal district courts over “all civil proceedings
arising under title 11, or arising in or related to cases under title 11,”
id.
§ 1334(b). There is a
spilt of authority among federal courts regarding whether § 1412 governs the transfer of
proceedings under all three grants of jurisdiction listed in § 1334(b).
See, e.g.
,
City of Liberal,
Kan. v. Trailmobile Corp.
,
[5] Declining to decide this issue does not undermine Defendants’ grounds for removing this action. Defendants alternatively asserted federal diversity jurisdiction which does apply. Intelect is a citizen of Maryland, where it is incorporated, Defendants are all citizens of Delaware, where they are each incorporated, and more than $75,000 is in controversy. See Am. Compl. ¶¶ 3–8; Notice of Removal at 6; 28 U.S.C. § 1332(c)(1).
[6] If there is “related to” jurisdiction, venue would also be proper in the District of Delaware, where the Powerwave bankruptcy is pending. See 28 U.S.C. § 1409 (noting that, barring certain exceptions not relevant here, “a proceeding arising under title 11 or arising in or related to a case under title 11 may be commenced in the district court in which such case is pending”).
[7] Intelect omitted its conversion claim from the Amended Complaint. As a result, the Court need not address whether resolving that claim, which may have required this Court to interpret and enforce the Delaware bankruptcy court’s Settlement Approval Order, would weigh in favor of transfer. See Defs.’ Mot. to Transfer Venue at 4.
[8] In their motion to transfer Defendants argue only that this count (previously numbered
as Count VIII) “concerns ancillary matters with which the Delaware Bankruptcy Court is most
familiar, as it has presided over that bankruptcy case for more than two years,”
see
Defs.’ Mot. to
Transfer Venue at 4, and their notice of removal cites supplemental jurisdiction under 28 U.S.C.
§ 1367 as a basis for federal jurisdiction over this count,
see
Notice of Removal at 6, 8. Despite
Defendants’ assertion that they plan to request this case be referred to the Bankruptcy Court for
the District of Delaware, whether a
bankruptcy court
(as distinguished from the district court) is
permitted to invoke supplemental jurisdiction to consider the promissory estoppel claim
notwithstanding the strictures of 28 U.S.C. § 157 is a question on which the circuits are divided.
See, e.g.
,
Cavalry Const., Inc. v. WDF, Inc. (In re Cavalry Const., Inc.)
,
[9] Although the Court has already expressed doubt that bankruptcy jurisdiction exists in this case, to the extent 28 U.S.C. § 1334 is the proper jurisdictional hook, the choice-of-law rule that applies is murkier. Some circuits apply the choice of law rules of the jurisdiction in which
[10] The one exception is a purported difference Intelect has identified between Maryland
law and “that of other states” with respect to Intelect’s unjust enrichment and quantum meruit
claims. Maryland law apparently will not permit a downstream subcontractor to recover from an
owner in quantum meruit even where an owner fails to pay a general contractor (who, in turn,
fails to pay a subcontractor).
See
Pl.’s Mem. Opp’n at 15 n.7 (citing
Truland Serv. Co. v.
McBride Elec., Inc.
, No. ELH-10-03445,
[11] The Court also leaves open the possibility that the significant relationship factors will
counsel in favor of applying Maryland law to some of Intelect’s claims and District of Columbia
law to others—a possibility the parties wholly overlook. A court is “not bound to decide all
issues under the law of a single jurisdiction; choice of law involves examination of the various
jurisdictional interests as applied to the various distinct issues to be adjudicated.”
Coleman
, 667
A.2d at 817
; see also, e.g.
,
Hercules & Co.
,
[12] Intelect also alleges that “[u]pon learning of Powerwave’s financial instability, each of the other members of the Carrier Consortium had an affirmative duty of due care to notify Intelect that its continued supply of labor and materials to the Project was at Intelect’s risk, in that the outstanding payment bond for which the Carrier Consortium members were obligees did not cover the work that they were performing on Phase II and III, which was then underway.” Am. Compl. ¶ 33. The Court does not understand this “duty,” stylized as a duty to notify or disclose information, to meaningfully differ from the duty Intelect invokes in its separate claim for negligent misrepresentation, in which it alleges that “[t]he Carrier Consortium had a duty of care to those persons, including Intelect, who supplied labor and materials to the Project to advise them that the Project was only partially bonded, and that they were at risk of loss if they continued to work on the Project beyond Phase I.” ¶ 40. Accordingly, the Court defers
[13] In the only comparable District of Columbia case, the District of Columbia Court of appeals declined to consider “the substantive question whether a suit can be maintained against the District for negligence in failing to enforce the payment bond provision of the Little Miller Act,” D.C.’s local statute requiring prime contractors on public work projects to obtain a payment bond, because the plaintiff had failed to comply with the statutory notice requirement for bringing a claim against the District of Columbia. District of Columbia v. Campbell , 580 A.2d 1295, 1301 n. 6 (D.C. 1990).
[14] Intelect cites two additional cases, but the Court finds those cases wholly irrelevant to
the question of whether Defendants had a duty to ensure that Powerwave obtained a payment
bond in the full amount of the project. While Intelect is correct that in
United States ex rel.
Hajoca Corp. v. Associated Mechanical, Inc.
, the district court denied summary judgment and
held that the plaintiff had a valid cause of action against a general contractor who had failed to
obtain a proper bond under the federal Miller Act, the cause of action at issue there was an unjust
enrichment claim, not a negligence claim.
See
No. 2:09-cv-2087,
[15] Section 324A of the Second Restatement provides: One who undertakes gratuitously or for consideration, to render services to
another which he should recognize as necessary for the protection of a third person or his
things, is subject to liability to the third person for physical harm resulting from his
failure to exercise reasonable care to protect his undertaking, if
(a) his failure to exercise reasonable care increases the risk of such harm,
or
(b) he has undertaken to perform a duty owed by the other to the third
person, or
(c) the harm is suffered because of reliance of the other or the third person
upon the undertaking.
Restatement (Second) of Torts, § 324A. In
Presley
the District of Columbia Court of Appeals
directly quoted the Second Restatement, but that court had previously stated that “the
Restatement has not been formally adopted by this Court.”
Haynesworth
,
[16] The Court further notes that the District of Columbia is a pure contributory negligence
jurisdiction.
See Lyons v. Barrazotto
,
[17] “The District of Columbia is one of the minority of jurisdictions that permits an
innocent misrepresentation claim to proceed as either a cause of action to rescind the contract
and restore the status quo
or
a cause of action for damages in tort.”
Cadet v. Draper &
Goldberg, PLLC
, No. 05-2105,
[18] Accordingly, where helpful to explain the “duty to disclose” required, the Court relies on cases discussing common law fraud or fraudulent misrepresentation.
[19] Courts in this district have also held that plaintiffs must plead fraud, constructive fraud,
and negligent misrepresentation claims with particularity pursuant to Federal Rule of Civil
Procedure 9(b).
See, e.g.
,
Jefferson
,
[20] Courts in this district have not been consistent in their use of terminology. The term
“quantum meruit” has also been used narrowly to describe only an “implied-in-fact contract,”
while the term “quasi-contract” has been used to refer to an unjust enrichment claim.
See
Plesha
,
[21] In these cases the District of Columbia Court of Appeals cited to § 29 of the Third
Restatement’s Tentative Draft number 3. Section 29 was renumbered as § 25 in the final version
of the Restatement and, as set forth in the cases, the language is substantively similar.
Compare
Restatement (Third) of Restitution and Unjust Enrichment § 25 (Am. Law Inst. 2010),
with
Jordan Keys
,
[22] While the Court is skeptical that Intelect will be able to show that the limited conduct
between Intelect and Defendants evidenced a contractual relationship sufficient to succeed on an
implied-in-fact contract theory, Defendants have not challenged Intelect’s complaint on this
ground. Regardless, an unjust enrichment claim provides an alternative theory for recovery
“even though no intention of the parties to bind themselves contractually can be discerned.”
Bloomgarden
,
[23] Specifically, while the Amended Complaint is not clairvoyant on this point, the Court infers that the Carrier Consortium promised Intelect that, if it maintained its labor force in place, it would continue as a sub-contractor on the project under the replacement general contractor. Should Intelect seek leave to amend its complaint to provide factual allegations supporting the detrimental reliance element of its promissory estoppel claim—as explained below—it should also make this connection explicit.
