STATEMENT OF THE CASE
Plaintiff-appellant Inman’s Incorporated (Inman) appeals from an adverse judgment by the Hancock Superior Cоurt in an action for money damages for breach of contract against defendant-appellee City of Greenfield (City).
We affirm.
STATEMENT OF THE-FACTS
In 1976, City, through its Board of Public Works and Safety, accepted bids for City’s gasoline supply for the following year. In-man and Shelby Oil Company (Shelby) submitted the only two bids. Inman’s bid was 38.5 cents per gallon for regular gasoline, and 39.5 cents per gallon for unleaded gasoline. Shelby’s bid was 41.0 cents and 42.9 cents, respectively. Each bid contained an escalating clause to protect the bidder from unforeseeable rises in the cost of gasoline, including increases in fuel taxes. City contracted with both Inman and Shelby, but was not bound to purchase a specific amount of gasoline from either supplier. Inman concedes that its contract with City was not exclusive and did not contain a provision setting forth a specified amount of gasoline to be sold.
During the contract period, City ordered 17,859.7 gallons of gasoline from Inman, and 26,508.8 gallons of gasoline from Shelby. At all times Inman’s selling price to City was lower than Shelby’s, sometimes by as much as eight cents per gallon. City does not contend there was a difference in the quality of the product supplied by In- *128 man and Shelby or that Inman was an unreliable or irresponsible supplier. City considered Shelby’s past good services and the existence of the escalating clause as factors in deciding to аward contracts for its gasoline supply to both Inman and Shelby. Also, Shelby’s place of business was across the street from the fire station, and it had made available a key to the premises so the fire department could obtain gasoline аt any time.
ISSUE
Inman contends the trial court’s decision is contrary to law, and advances the following proposition: City would nеver be able to determine, in advance, which bidder actually could provide the lowest gasoline price beсause of wholesale price fluctuations. Inman’s initial, lower price could rise above the price at which Shеlby would supply City. For this reason, Inman agrees City was probably correct for accepting both bids. However, Inman argues City, having accepted both bids, was under a duty to award purchase orders to the bidder whose current price was lowest. Inman further argues that Indiana law binds a public’body to accept the lowest and best bid, and this policy is incorporated into all public contracts. The failure of City to so uphold the law was a breach of contract, Inman concludes, giving rise to money damages.
DISCUSSION AND DECISION
Ind.Code 5-17-1-2, the competitive bidding statute, requires a municipal corporation to award cоntracts for supplies to the “lowest and best bidder.” The general rule allows a taxpayer to enjoin public contracts entered into pursuant to competitive bidding where the contract award is arbitrary, corrupt, or fraudulent. It is immateriаl whether a taxpayer bringing an action against a municipality was an unsuccessful bidder for a public contract beсause his legal status as a taxpayer qualifies him to sue.
In
School City of Gary
v.
Continental Electric Company,
(1971)
In School City of Gary, supra, the court addressed the issue of public policy:
“Whenever public moneys are encumbered by a governmental agency, a solemn duty arises to protect these moneys. Competitive bidding requirements have been legislated to safeguard the public against fraud, favoritism, graft, extrаvagance, improvidence and corruption, and to insure honest competition for the best work or supplies аt the lowest reasonable cost.”
Generally, contracts with public bodies are construed and enforced in the samе manner as any other contracts between private individuals, except as they may be controlled by statute.
State
v.
Feigel,
(1931)
To obtain money damages, Inman must rely on the specific terms of his contract with City. Inman had а non-exclusive contract to furnish an unspecified amount of gasoline. City was free to order its gasoline from either Inman or Shelby.
For the above reasons, the decision of the trial court is affirmed.
Affirmed.
