Ingalls Shipbuilding, Inc. v. John H. Dalton, Secretary of the NavyIngalls Shipbuilding, Inc. v. John H. Dalton, Secretary of the Navy
Ingalls Shipbuilding, Inc. appeals from the final decision of the Armed Services Board of Contract Appeals granting summary judgment for the United States Navy on the ground that payments made by Ingalls under
BACKGROUND
The facts in this case are not in dispute. Ingalls is a shipbuilder in the business of constructing, repairing, and overhauling naval surface combatant ships. In the course of its business, it has entered into numerous contracts with the Navy. Ingalls is subject to the provisions of the Longshore and Harbor Workers’ Compensation Act (LHWCA),
If any installment of compensation payable without an award is not paid within fourteen days after it becomes due, as provided in [§ 914(b) ], there shall be added to such unpaid installment an amount equal to 10 per centum thereof, which shall be paid at the same time as, but in addition to, such installment, unless notice is filed under [§ 914(d) ], or unless such nonpayment is excused by the deputy commissioner after a showing by the employer that owing to conditions over which he had no control such installment could not be paid within the period prescribed for the payment.
Between October 1, 1986 and May 14, 1987, approximately two thousand LHWCA claims were filed against Ingalls alleging noise-induced hearing loss injuries. Ingalls states that it could not prudently and in a timely manner investigate each claim in this unprecedented mass filing. Therefore, because any improvidently issued pre-award payments would not have been not recoverable, and because Ingalls wished to save itself and the Navy unnecessary costs, Ingalls decided not to pay the initial pre-award installments when they became due, but instead responded only by filing generic answers to each claimant. Ingalls then sought and received an excuse for deferring action from the Deputy Commissioner. However, the Fifth Circuit later determined that Ingalls’ generic answers were insufficient to serve as
Ingalls attempted to recover the cost of its
In February 1993, the Defense Contract Audit Agency (DCAA) issued an audit report concerning Ingalls’
Under these regulations, a cost either directly or indirectly incurred in performing a contract may be chargeable to that contract if,
inter alia,
it is “allowable.”
See
FAR § 31.204(a) (1996);
see also
DAR § 15-201.1
Costs of fines and penalties resulting from violations of, or failure of the contractor to comply with, Federal, State, local, or foreign laws and regulations, are unallowable except when incurred as a result of compliance with specific terms and conditions of the contract or written instructions from the contracting officer.
FAE § 31.205-15(a) (1996) (“Fines, penalties, and mischarging costs.”), and
Interest on borrowings (however represented), bond discounts, costs of financing capital (net worth plus long-term liabilities), legal and professional fees paid in connection with preparing prospectuses, costs of preparing and issuing stock rights, and directly associated costs are unallowable except for interest assessed by State or local taxing authorities under the conditions specified in [FAE § ] 31.205-41 (but see [FAE § ] 31.205-28).
FAE § 31.205-20 (1996) (“Interest and other financial costs.”). The corresponding DAE provisions are identical to the FAE provisions in all relevant aspects; DAE § 15-205.13 (1984) pertains to fines and penalties, while DAE § 15-205.17 pertains to interest on borrowings.
3
The exception of § 31.205-15 does not apply because, as explained above, the
Ingalls appealed the CO’s final decision to the board. Before the board, both parties moved for summary judgment, and the board granted the Navy’s motion. The board concluded that the
DISCUSSION
The standard under which we review a decision of the board is dictated by the Contract Disputes Act, which provides in relevant part:
[t]he decision of the agency board on any question of law shall not be final or conclusive, but the decision on any question of fact shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.
Ingalls challenges the board’s legal conclusion that
In response, the Navy argues that although
We first consider the FAR provision. “To interpret a regulation we must look at its plain language and consider the terms in accordance with their common meaning.”
Lockheed Corp. v. Widnall,
Neither this court, our predecessor courts, nor any other circuit or trial court has previously considered the scope of this FAR provision.
4
Apparently, the only tribunals to have interpreted this provision are the agency boards of contract appeals.
See, e.g., Joint Action in Community Serv., Inc.,
LBCA No. 83-BCA-18,
We therefore turn to the statute which imposes the payment in question. When called upon to interpret a statute, our
The LHWCA, read as a whole, specifies how and to what extent injured employees will be compensated. We first note that the title of
Furthermore,
Ingalls has directed our attention to what it considers the most authoritative judicial analysis of penalties,
Huntington v. Attritt,
Thus, consistent with
Huntington,
Finally, we are not persuaded by the Navy’s citation of various judicial opinions, including those in the above-noted Fifth Circuit cases involving Ingalls and an opinion of the Supreme Court, in which
Accordingly, we conclude that the board erred in holding that the payments made pursuant to
B. Interest on Borrowings
The Navy argues an alternative ground, presented to but not decided by the board, on the basis of which it urges us to affirm the board’s decision. It argues that because the
We agree with Ingalls and can resolve this “straight forward and simple” legal issue without remand.
See Riggin v. Office of Senate Fair Employment Practices,
CONCLUSION
The board erred in construing
REVERSED.
Notes
. All references to the United States Code (U.S.C.) are to the 1994 edition.
. The DAR, last codified at 32 C.F.R. pts. 1-39 (1984), was superseded in 1984 by the FAR, which is codified at 48 C.F.R. pts. 1-99 (1996).
. Because the DAR and FAR provisions are identical for purposes of this appeal, we will refer only to the FAR provisions in the remainder of this opinion.
. In
Transtechnology Corp., Space Ordnance Systems Division v. United States,