INDUSTRIAL CUSTOMERS OF NORTHWEST UTILITIES; Bеnton Rural Electric Association; Columbia-Snake River Irrigators Association; Umatilla Electric; Eastern Oregon Irrigators Association, Petitioners v. BONNEVILLE POWER ADMINISTRATION, Respondent
Nos. 03-71626, 03-71894, 03-71931
United States Court of Appeals, Ninth Circuit
May 24, 2005
408 F.3d 638
iii
The third factor is the timeliness of the defendant‘s request. Cassel made his request for new counsel on the day of sentencing. If granted, it would certainly have resulted in some delay, possibly substantial, as a new attorney became familiar enough with the case to represent Cassel at sentencing.
iv
Two of the three relevant factors—the adequacy of the magistrate judge‘s inquiry and the timeliness of the defendant‘s request—weigh heavily in favor of the magistrate judge‘s decision not to grant Cassel‘s request for new counsel. The third factor—the degree of conflict between client and attorney—is slightly more equivocal but still supports the judge‘s decision: Cassel‘s mistrust of his lawyer was real, but nothing suggests that it threatened to affect the attorney‘s ability to represent him. We are therefore satisfied that the magistrate judge did not abuse his discretion in denying Cassel‘s request.
III
Although Cassel‘s facial challenge to
Michael B. Early, Portland, OR, for petitioner Alcoa Inc.
Melinda J. Davison, Irion A. Sanger, Davison Van Cleve, Portland, OR, for petitioners Industrial Customers of Northwest Utilities, Benton Rural Electric Association, Columbia-Snake River Irrigаtors Association, Umatilla Electric, Eastern Oregon Irrigators Association.
Raymond S. Kindley, Schwabe, Williamson & Wyatt, Portland, OR, for petitioners Public Utility District No. 1 of Benton County, Public Utility District No. 1 of Cowlitz County, Public Utility District No. 1 of Franklin County, Public Utility District No. 2 of Grant County, Public Utility District No. 1 of Grays Harbor County, Public Utility District No. 1 of Pendoreille County, the City of Seattle, Seattle City Light Department.
Michael J. Gianunzio, Eric Lee Christensen, Everett, WA, for petitioner Public Utility District No. 1 of Snohomish County, Washington.
Gary A. Dahlke, R. Blair Strong, Paine, Hamblen, Coffin, Brooke, & Miller, LLP, Spokane, WA, for petitioner-intervenor Avista Corporation.
R. Erick Johnson, Portland, OR, for petitioner-intervenor Pacific Northwest Generating Company.
Kirstin S. Dodge, Perkins Coie, LLP, Bellevue, WA, for petitioner-intervenor Puget Sound Energy.
Eric Lee Christensen, Michael J. Gianunzio, Everett, WA, for petitioner-intervenor Public Utility District No. 1 of Snohomish County, Washington.
Randy A. Roach, Marybeth Van Buren, Karin J. Immergut, United States Attorney, District of Oregon, Stephen J. Odell, Assistant U.S. Attorney, Kurt R. Casad, Special Assistant U.S. Attorney, Portland, OR, for respondent Bonneville Power Administration.
Marcus Wood, Stephen C. Hall, Stoel Rives LLP, Portland, OR, for respondent-intervenor Pacificorp.
Loretta Mabinton, Portland, OR, for respondent-intervenor Portland General Electric Company.
THOMAS, Circuit Judge:
This consolidated appeal presents the question, inter alia, of whether the Bonneville Power Administration (“BPA“) determination to commence a rate hearing to decide whether the BPA should impose Safety-Net Cost Recovery Adjustment Charges is a final agency decision subject to judicial review. We conclude that it is not and dismiss the petitions for review for lack of jurisdiction.
I
The BPA is a federal agency within the United States Department of Energy created by Congress in 1937 to market hydroelectric power generated by the Federal Columbia River Power System, a series of dams along the Columbia River in Oregon and Washington.
The BPA‘s general authority is derived from four organic statutes: the Bonneville Project Act of 1937 (“the Project Act“),
The Northwest Power Act requires the BPA to establish rates that will “produce sufficient revenues to ensure BPA‘s fiscal independence and repay the U.S. Treasury for the federal funds that were borrowed to build the projects in the Federal Columbia River Powеr System.” Cal. Energy Comm‘n v. BPA, 909 F.2d 1298, 1303 (9th Cir.1990);
The BPA Administrator is required periodically to revise rates to recover the capital costs and expenses associated with the Columbia River Power System. See
The rate schedules proposed by the BPA are termed “General Rate Schedule Provisions” (“GRSP“). The origins of the present controversy arose out of a supplemental rate proposal promulgated by the BPA in 2001. The BPA had previously proposed new wholesale power rates to be effective on October 1, 2001, 64 Fed. Reg. 44,318 (1999), and different rates to be effective Fiscal Year 2002, 65 Fed. Reg. 44,041 (2000).
After these filings, increased load obligations and higher market prices caused the BPA to determine that its rate proposals would be insufficient to assure it could cover costs and repаy U.S. Treasury obligations. On December 1, 2000, the BPA published its proposed amendments to the 2002 whole-sale power rate adjustment proposal. 65 Fed. Reg. 75,272 (2000). Further market changes caused the BPA to issue supplemental wholesale power rate filing on June 29, 2001. 66 Fed. Reg. 37,664 (2001). The supplemental proposal adjusted the previous GRSP by replacing the capped single Cost Recovery Adjustment Clause (“CRAC“) with a three-component CRAC: the Load-Based CRAC (or “LB CRAC“, as it is referenced in the BPA filings) designed to cover augmentations costs; the Financial-Based CRAC (or “FB CRAC“) designed to cover net revenue, and the Safety-Net CRAC (or “SN CRAC“), available if there were a likelihood of missing a treasury or other creditor payment.
The CRACs were created to allow the BPA to address any financial shortfalls without having to raise base rates. In particular, the CRACs were intended to increase the BPA‘s Treasury Payment Probability to what it considered acceptable levels. FERC granted interim approvаl of the CRAC proposal on September 28, 2001 and final approval on July 21, 2003. 104 FERC ¶ 61,093 (2003).
When triggered, the Safety-Net CRAC allowed “an upward adjustment to posted power rates subject to the FB CRAC by modifying the FB CRAC parameters.” Under the GRSP, the Safety-Net CRAC would be available if the Administrator determined that, after implementation of the Financial-Based CRAC and any adjustments, either of the following conditions existed:
- The BPA forecasts a fifty percent or greater probability that it will nonetheless miss its next payment to Treasury or other creditor, or
- The BPA has missed a payment to the Department of the Treasury or has satisfied its obligation to the Department of the Treasury but has missed a payment to any other creditor.
Under the supplemental proposal, once the BPA Administrator determined that these conditions existed, the BPA would “propose changes to the FB CRAC parameters that will, to the extent market and other risk factors allow, achieve a high probability that the remaindеr of Treasury
When the Administrator determined that the Safety-Net CRAC had been triggered, the BPA would be required to send written notification to customers that purchase power under rates subject to the Financial-Based CRAC and to other interested parties. The notice was required to include “the documentation used by the BPA to determine that the SN CRAC has triggered, the amount of any forecast shortfall, and the time and location of a workshop on the SN CRAC.” The scheduled workshops are to discuss “the cause of shortfall, and any proposed changes to the FB CRAC that will achieve a high probability that the remainder of Treasury payments... will be made timely.”
Additionally, “[a]s soon as practicable after a determination,” the BPA was required to publish “a Federal Register Notice initiating an expedited hearing process to be conducted in accordance with Section 7(i) of the Northwest Power Act.” The hearing was required to be completed within forty days of publication of the notice.
The BPA experienced continued financial problems in the winter of 2003. Due to “lower than expected prices and less than expected hydro production,” the BPA ended up “selling less energy and at lower prices than forecasted in the Supplemental Proposal.” Under the GRSP financial test, the Administrator determined that the BPA had less than a fifty percent probability of making the next Treasury payment, due October 1, 2003. On February 7, 2003, the BPA Administrator commenced an emergency rate adjustment pursuant to the financial test in the Safety-Net CRAC provisions. The BPA issued a letter to “interested parties and customers” informing them of the trigger determination; the letter “included a table summarizing the documentation used by the BPA to determine that the SN CRAC had triggered, the amount of the forecasted shortfall, and the time and location for a workshop on the SN CRAC.”
Pursuant to the GRSP, the BPA conducted workshops in February 2003 to explain the trigger determination. In March, the BPA published a Federal Register Notice of “Proposed Safety-Net Cost Recovery Adjustment Clause Adjustment to 2002 Wholesale Power Rates.” 68 Fed. Reg. 12,048 (2003). The BPA held full evidentiary hearings and allowed a comment period.
In June 2003, the BPA published its “Administrator‘s Final Record of Decision” (“Final ROD“) for the Safety-Net CRAC. The Final ROD contains the BPA analysis and conclusions based on the evidentiary record compiled, with respect to the adoption of the Safety-Net CRAC. Subsequently, the BPA filed its Safety-Net CRAC rate adjustment proposal and record with FERC on July 29, 2003, along with a request for interim and final approval effective October 1, 2003. 105 FERC ¶ 61,006 ¶¶ 2, 3 n. 4 (2003). The effect of the Safety-Net CRAC would be to increase the BPA‘s power rates substantially.
The petitioners in these consolidated petitions for review are various public utilities and private utility consumers who challenge the BPA‘s Final ROD approving the Safety-Net CRAC. They contend that the BPA Administrator was not entitled to impose the Safety-Net CRAC because neither of the two predicate conditions existed. Respondents concede that the BPA had not missed any payments that would cause the trigger. The Petitioners argue
On judicial review under the Administrative Procedures Act, we may grant a petition for review from a final decision of the BPA if it is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.”
II
The threshold question is whether we have jurisdiction over the consolidated petitions for review. The BPA contends that the Administrator‘s decision to trigger the Safety-Net CRAC is not subject to judicial review until FERC confirms and approves the rate,1 reasoning that the final agency action in this instance rests with FERC. We agree and conclude that we lack appellate jurisdiction because the Final ROD was not the final rate dеtermination and therefore, not the final agency action.
A
Under the Northwest Power Act, we have original jurisdiction for all cases brought challenging actions under the Project Act,
Because the BPA‘s decision to trigger the Safety-Net CRAC is ultimately subsumed into the rate subject to FERC approval, this statutory scheme would seem to present a fairly straightforward administrative process for review of the BPA‘s triggеr determination. However, FERC does not have the authority to review the BPA‘s initial trigger decision. Although FERC must approve all rate changes before they become final, FERC‘s power to review the BPA proposals is limited: It can affirm or remand the rates, but cannot modify them.
The basis of the Commission‘s review of regional power and transmission rates is restricted to whether the proposed rates meet the three specific requirements of Section 7(a)(2); namely that they:
- are sufficient to assure repayment of the Federal investment in the Federal Columbia River Power System over a reasonable number of yeаrs after first meeting the Administrator‘s other costs,
- are based upon the Administrator‘s total system costs, and
- insofar as transmission rates are concerned, equitably allocate the costs of the Federal transmission system between Federal and non-Federal power utilizing such system.
FERC reviews non-regional, non-firm rates to determine whether such rates comply with the statutory mandates of the Project Act, the Flood Control Act of 1944, and the Transmission System Act. Id. § 839e(k). These statutes require BPA “to design its non-regional, non-firm rates: (1) to recover the cost оf generation and transmission of such electric energy, including the amortization of investments in the power projects within a reasonable period; (2) to encourage the most widespread use of Bonneville power; and (3) to provide the lowest possible rates to consumers consistent with sound business principles.” 107 FERC ¶ 61,138 ¶ 22.
Given these limitations, the Petitioners quite correctly point out that FERC‘s rate review will not provide them with an opportunity to challenge the BPA‘s trigger decision during FERC‘s review. However, the absence of FERC review does not preclude judicial review of the BPA‘s trigger determination after final FERC action. Indeed, the BPA concedes that the petitioners have the full right to judicial review of its trigger decision as part of the petition for review of the ultimate FERC rate decision. However, because the trigger determination was a component of the rate, it is not subject to judicial review until final agency action with respect to the rate. See Pub. Util. Comm‘r of Oregon v. BPA, 767 F.2d 622, 629 (9th Cir.1985) (noting that challenges to the BPA‘s rate-making process not subject to FERC review may still be raised on judicial review of final FERC rate decision, but cannot be raised in an interlocutory petition for review). In sum, the petitions before us are not ripe for review, but are a proper part of a petition for review of the final FERC rate decision.
B
The petitioners contend that we have appellate jurisdiction pursuant to our “catchall” jurisdiction under the Northwest Power Act, which provides that “[n]othing in this section shall be construed to preclude judicial review of other final actions and decisions by the Council or Administrator.”
In applying these principles, we have determined that certain factors provide an indicia of finality, such as “whether the [action] amounts to a definitive statement of the agency‘s position, whether the [action] has a direct and immediate effect on the day-to-day operations of the party seeking review, and whether immediate compliance [with the terms] is expected.” Cal. Dep‘t of Water Res. v. FERC, 341 F.3d 906, 909 (9th Cir.2003) (citing Mt. Adams Veneer Co. v. United States, 896 F.2d 339, 343 (9th Cir.1990) (citing FTC v. Standard Oil Co., 449 U.S. 232, 239-40 (1980))).
The decision by the BPA Administrator to trigger the Safety-Net CRAC rate adjustment process fails the first prong of the Bennett test of finality, in that it does not “mark the ‘consummation’ of the agеncy‘s decisionmaking process,” but is merely the beginning of the decision-making process. “An interlocutory order or decree is one which does not finally determine a cause of action but only decides some intervening matter pertaining to the cause, and which requires further steps to be taken in order to enable the court to adjudicate the cause on its merits.” Dalton Equip. Co. v. Brown, 594 F.2d 195, 197 (9th Cir.1979).
In the Final ROD, the BPA represented that “[t]he trigger determination for the SN CRAC is purely procedural.” As the Final ROD explаins, “[t]he trigger determination does not propose an SN CRAC or establish an SN CRAC.” Instead, the trigger determination only initiates the process. The Administrator considered the Safety-Net CRAC process to be comprised of three phases, as delineated in the GRSP. The trigger determination constitutes the first phase. The second phase is the “SN CRAC Notification Process,” which is “intended to inform customers and interested third parties of the Administrator‘s determination, and the basis for it.” The third phrase is “SN CRAC Hearing Process,” which is governed by the procedural requirements of § 7(i). After the § 7(i) evidentiary hearing, which must be completed within forty days, the BPA must submit the required documentation, including the administrative record to FERC. Only after FERC‘s confirmation and approval are rate determinations deemed final.
Petitioners argue, with much justification, that the trigger decision is a discrete decision that has immediate financial impact. However, the fact that a statement may be definitive on some issue is insufficient to create a final action subject to judicial review. In Standard Oil, for example, Standard Oil Company of California (“Socal“) brought an action against the
To be sure, the issuance of the complaint is definitive on the question whether the [FTC] avers reason to believe that the respondent to the complaint is violating the Act. But the extent to which the respondent may challenge the complaint and its charges proves that the averment of reason to believe is not “definitive” in a comparable manner to [other cases]. ... [T]he averment of reason to believe is a prerequisite to а definitive agency position on the question whether Socal violated the Act, but itself is a determination only that adjudicatory proceedings will commence.
Although it is the predicate act for rate readjustment, the trigger determination itself has no final consequences. The trigger decision only determines whether a hearing will or will not occur. Like the complaint at issue in Standard Oil, the determination “[s]erv[es] only to initiate the proceedings.” Id. at 242. As the BPA noted in the Final ROD, “[t]he actual determination of whether the BPA will have an SN CRAC and, if so, the nature of the SN CRAC rate adjustment, is determined in the section 7(i) hearing.” Any change in actual rate only occurs after being submitted to and approved by FERC. Because it is not an actual rate decision, the BPA Administrator is allowed, and in fact required, to “make a decision on the trigger determination in the absence of a formal evidentiary record.” The BPA explains that “[t]he requirements for making the trigger determination are very limited, which is perfectly consistent with the nature of the trigger determination ... [which] has no substantive effect on any customer or interested party.”
In the real world, of course, the trigger determination has economic consequences—sometimes profound consequences—because companies must take it into consideration when negotiating power contracts, particularly long-term power contracts. Nonetheless, the companies have a right of judicial review at the conclusion of FERC proceedings and do not waive any of their objections to the predicate determinations by failing to seek judicial review at an earlier stage.
III
For these reasons, we dismiss the petitions for lack of jurisdiction. We need not, and do not, reach any other issue raised by the parties. Each party shall bear its own costs.
PETITION DISMISSED.
UNITED STATES of America, Plaintiff-Appellee, v. Sandee D. DOWLIN and Walter G. Naylor, d/b/a Freship, Provider Corp., Dos Brisas Corporation, Defendants-Appellants.
Nos. 03-8038, 03-8055.
United States Court of Appeals, Tenth Circuit.
May 17, 2005.
