INDIANA & MICHIGAN ELECTRIC COMPANY, Petitioner, v. FEDERAL POWER COMMISSION, Respondent. Richmond Power and Light of the City of Richmond, Indiana, et al., Intervenors.
No. 72-2168.
United States Court of Appeals, District of Columbia Circuit.
Argued Jan. 9, 1974. Decided Feb. 14, 1974.
On Rehearing Aug. 14, 1974.
502 F.2d 336
John Staffier, Atty., F. P. C., for respondent. Leo E. Forquer, Gen. Counsel, George W. McHenry, Jr., Acting Sol., and Platt W. Davis, III, Atty., F. P. C., were on the brief for respondent.
George E. Morrow, Memphis, Tenn., for intervenor, Indiana and Michigan Municipal Distributor Assn.
George Spiegel and Sandra J. Strebel, Washington, D. C., were on the brief for
Wallace L. Duncan, Washington, D. C., was on the brief for intervenor, Anderson Power and Light of the City of Anderson, Ind. Frederick D. Palmer, Washington, D. C., also entered an appearance for intervenor Anderson Power and Light.
Before BAZELON, Chief Judge, and ROBINSON and WILKEY, Circuit Judges.
WILKEY, Circuit Judge:
Indiana & Michigan Electric Company (hereinafter I&M) filed proposed changes in its tariff schedule with the Federal Power Commission on 13 June 1972. By letter of 3 July 1972, the Secretary of the Commission acknowledged I&M‘s filing and advised the company that “[t]he earliest effective date for the increase consistent with [
Because the Commission lacked statutory authority to delay the effective date of I&M‘s filing until 13 August 1972 and to suspend the new rates until 13 January 1973, we vacate the Commission‘s order of 11 August 1972 and remand to the Commission with instructions that I&M‘s 13 June rate filing be given effect as of 14 July 1972.8
I. JURISDICTION OF THE COURT TO CONSIDER THE VALIDITY OF THE COMMISSION‘S 60-DAY REGULATION
The liminal question here is whether this court can, consistent with
While I&M did not expressly raise the legality of the 60-day regulation in its application for rehearing, it did challenge the Commission‘s statutory authority to set an effective date 60 days after I&M‘s filing.10 The Commission characterized I&M‘s position in seeking a rehearing as follows: “I&M asserts that the Commission has no authority to require a notice in excess of the thirty days specified in Section 205(d) of the Federal Power Act.”11 Apparently perceiving I&M‘s position as a challenge to the 60-day regulation, the Commission devoted two of the five pages of its order denying rehearing to an attempted justification of the regulation.12 Commissioner Moody joined issue with the majority and attacked the validity of the regulation in his dissent.13 Clearly, then, I&M brought sufficient attention to the issue to stimulate the Commission‘s consideration of it.
II. THE COMMISSION‘S 60-DAY PREFILING REGULATION
The Commission delayed the effective date of I&M‘s rate filing pursuant to
It seems clear, then, that in order to comply with the requirements of
Unless the Commission otherwise orders, no change shall be made by any public utility in any such rate, charge, classification, or service, or in any rule, regulation, or contract relating thereto, except after thirty days’ notice to the Commission and to the public. Such notice shall be given by filing with the Commission and keeping open for public inspection new schedules stating plainly the change or changes to be made in the schedule or schedules then in force and the time when the change or changes will go into effect. The Commission, for good cause shown, may allow changes to take effect without requiring the thirty days’ notice herein provided for by an order specifying the changes so to be made and the time when they shall take effect and the manner in which they shall be filed and published.23
The Supreme Court has interpreted this language to create not only a minimum notice period for the utility‘s customers and the Commission, but also a maximum waiting period for the filing utility. In United Gas Pipe Line Co. v. Memphis Light, Gas & Water Division,24 the Court construed
The Commission asserts that the 60-day prefiling requirement of
The result we reach here is not foreclosed by this court‘s decision in Municipal Light Boards v. FPC.30 As Commissioner Moody pointed out in his dissent to the Commission‘s denial of I&M‘s application for rehearing, the validity of
Under
III. THE FIVE-MONTH SUSPENSION OF I&M‘S RATES
Once proposed rates have become effective this Commission is powerless to suspend the effectiveness of, or otherwise modify, those rates under § 205 of the Federal Power Act. Our only recourse is to institute a proceeding under § 206(a) of the Act and after hearing determine just and reasonable rates to be thereafter observed and in force.35
IV. CONCLUSION
The Commission has exceeded its statutory authority by delaying the effective date of I&M‘s rate filings beyond the 30 days prescribed by
Vacated and Remanded.
ON PETITIONS FOR REHEARING
PER CURIAM.
ORDER
On consideration of the petitions for rehearing, it is ordered by the Court that the petitions for rehearing are granted and the opinion filed on 14 February 1974 is modified in the manner set out in the third paragraph of the opinion of this Court filed herein this date.
WILKEY, Circuit Judge:
The Commission, with the support of intervenors, has filed a petition for rehearing in which it requests that we modify our main opinion of 14 February 1974 by eliminating therefrom our holdings: (1) that the Commission‘s five-month suspension of the rates filed by Indiana & Michigan Electric Co. (I&M) must be vacated; and (2) that I&M is entitled to collect from its customers the difference between its filed rates, which now must be deemed lawful from their effective date, and the rates actually charged for the six-month period from 14 July 1972 to 13 January 1973.
In our main opinion we explained in Parts III and IV why under
After scrutinizing the various memoranda submitted in connection with this petition,1 we have decided to adhere to our holding that the Commission exceeded its authority when it suspended
- I&M may not collect retroactive rate increases for the five-month period from the effective date of its rate filing, 14 July 1972, through 13 December 1972.
- I&M may collect the difference between its old and new rates for the period from 14 December 1972 through 13 January 1973.
- Should the Commission determine during the course of its current hearings that I&M‘s filed rates are unjust or unreasonable, it may order I&M to refund the amounts collected after 13 December 1972 in excess of the just and reasonable rates.
I. Equitable Factors
Under our original order, I&M‘s customers would be obligated to pay retroactive rate increases for the five-month period during which the Commission‘s unlawful suspension order was in effect. This would create considerable hardship for I&M‘s customers, for, in reliance on the Commission‘s suspension order, they failed to seek increases in their own rates to offset I&M‘s increased charges. Since I&M‘s customers are precluded by federal law2 and the relevant state statutes3 from retroactively raising their rates, our original order would force them to absorb out of their own current assets the five months of retrospective increases in I&M‘s rates. These substantial amounts4 would impose a significant burden on the finances of I&M‘s customers.5
In addition, I&M‘s customers have been paying the higher rates provided for by I&M‘s new tariff schedule since 13 January 1973. Those rates are now subject to scrutiny in Commission hearings to determine whether they are just and reasonable. Our main opinion would deprive the Commission of authority to order refunds by I&M to its customers in the event the Commission finds that some portion of I&M‘s increases are unjustified. The Commission‘s power to order refunds arises from
Under our main opinion, which renders the Commission‘s 11 August 1972 suspension order a nullity, the Commission‘s hearings on the reasonableness of I&M‘s rates cannot rest on the authority of
Our concern about the liability of I&M‘s customers for retroactive rate increases, and payment by those customers of possibly unreasonable rates without right to refunds, is intensified by the fact that the Commission explicitly found in its 11 August 1972 order that I&M‘s filed rates may be unjust or unreasonable. The Commission stated:
The proposed rates and charges . . . have not been shown to be justified and may be unjust, unreasonable, unduly discriminatory, or preferential, or otherwise unlawful. It has also been alleged that I&M‘s proposed tariff changes are contrary to the economic stabilization program and antitrust policies and that interchange of energy should be provided for. It is necessary and appropriate in the public interest and in carrying out the provisions of the Federal Power Act that the Commission enter upon a hearing concerning the lawfulness of the rates, charges, classifications, services, and other provisions contained in I&M‘s proposed FPC Electric Tariff, and the use thereof deferred as hereinafter provided.10
Thus, the strong potential that hardship to I&M‘s customers could result from our main opinion is compelling.
Moreover, the equitable stake of I&M in our main opinion is not significant. I&M sought from the Commission no greater relief than our modified order now grants. In its application for rehearing before the Commission, I&M requested that the Commission
[i]ssue a supplemental order modifying ordering paragraph (C) of its August 11, 1972 Order in this proceeding, so as to provide that I&M‘s
proposed rate schedules are suspended for five months beginning July 14, 1972 and their use deferred until December 14, 1972 . . . .11
By modifying our original order in the manner set out above, we eliminate the potential for hardship to I&M‘s customers and we accord I&M precisely the relief it sought from the Commission. The equities clearly dictate that we reinstate the suspension of I&M‘s rates for the period from 14 July 1972 through 13 December 1972, and restore to the Commission its power under
II. The Court‘s Equity Powers
A court sitting in review of an administrative agency is vested with equity powers which it may employ in a manner defined by the Supreme Court in Ford Motor Co. v. NLRB:12
[W]hile the court must act within the bounds of the statute and without intruding upon the administrative province, it may adjust its relief to the exigencies of the case in accordance with the equitable principles governing judicial action. The purpose of the judicial review is consonant with that of the administrative proceeding itself,—to secure a just result with a minimum of technical requirements.13
By our exercise of equity powers herein, we are “adjust[ing] [our] relief to the exigencies of the case in accordance with the equitable principles governing judicial action.” In so doing, we are acting, we believe, “within the bounds” of the Federal Power Act; indeed, our main opinion promotes the Act by confining the Commission to its statutory authority, and this supplemental opinion is designed to advance the policies and procedural safeguards of
The Supreme Court‘s decision in United States v. Morgan15 is instructive here. Under the authority of the
Congress having by the Packers and Stockyards Act established the public policy of maintaining reasonable rates
for stockyard services, and having prohibited and declared unlawful any unjust or unreasonable rate, a court of equity should be astute to avoid the use of its process to effectuate the collection of unlawful rates . . . .18
The Court so held although it conceded that the Secretary could prescribe lawful rates only for the future and could not act with respect to charges collected in the past.19 It reasoned that the Secretary had already found the stockyard rates unlawful, although he had done so in a procedurally defective manner. If the Secretary subsequently decided to reaffirm his earlier decision through proper procedures, he could not directly order refunds of the excessive amounts paid by stockyard customers in the past. However, such a decision would justify restitution to the customers of the amounts held by the clerk of the District Court. Similarly, we have found an order of the Commission invalid on the basis of a procedural defect (untimeliness). But in order to advance the Federal Power Act‘s policy of maintaining just and reasonable rates, we have provided that refunds to the filing utility‘s customers will be appropriate if the Commission subsequently makes definite its earlier finding that I&M‘s filed rates may be unlawful by so holding in a final decision.
Finally, we are not “intruding upon the administrative province” by our actions herein. Our denial to I&M of retroactive relief for the period 14 July 1972 through 13 December 1972 is not an infringement upon the Commission‘s exclusive suspension power.20 The Commission explicitly determined that suspension was appropriate but failed to issue its suspension order in a timely fashion. Nor are we interfering with the Commission‘s statutory role as the sole body responsible for determining whether an electric utility‘s filed rates are just and reasonable. We have not relieved I&M‘s customers of the burden of paying I&M‘s filed rates. We have merely provided that if the Commission subsequently determines that the filed rates are unjust or unreasonable, it may order I&M to refund the excess amounts paid by its customers.21 Thus, we are
Our decision draws support from Mississippi River Fuel Corp. v. FPC,22 in which the Third Circuit held that the Commission had acted outside its authority by summarily rejecting the filing utility‘s rate schedule without a hearing. This rejection, the court found, violated the procedural requirements of
The filing utility subsequently moved to modify the court‘s order by making its rate filing effective retroactively to 1 June 1952, or 31 days after the date of filing. The court denied the motion, thus in effect imposing a de facto suspension of several months on the filed rates. The court justified its decision by reasoning that granting the retroactive relief requested (1) would force the filing utility‘s principal customer “to pay additional retroactive charges of about $3,000,000 for gas it already has resold to its own customers on the basis of [the filing utility‘s] existing rate to it”25 and (2) would fly in the face of “an affirmative though legally misconceived rejection of [the] proposed rate increase by the administrative body which had jurisdiction over the subject matter.”26 In the instant case, we have justified our modified relief herein in part on the basis that (1) granting I&M fully retroactive relief would impose substantial, irrecoverable costs on I&M‘s customers,27 and (2) the Commission has affirmatively found that I&M‘s rates may be unjust or unreasonable, although it implemented its finding in a procedurally defective manner.28 Therefore, we believe our exercise of equity powers can rest on the authority of Mississippi River Fuel as well as United States v. Morgan.
III. Conclusion
For the reasons stated herein, we grant the petitions for rehearing and modify our main opinion of 14 February 1974 in the manner set out in the third paragraph of this opinion.
So ordered.
Notes
Except as provided in subdivision (ii) of this subparagraph, if the rate schedule provides for an increased rate, then 60 days prior to the date that such changed rate is proposed to become effective the filing public utility shall submit a statement showing its cost of the service to be supplied under the new rate schedule according to supporting statements A through O as described below. Simultaneously, the public utility shall submit the material on sales and revenues described in paragraph (a) of this section and, unless the rate schedule containing the proposed increased rate is likewise simultaneously filed, a summary statement of such proposed increased rate: Provided, however, That the submittal of such summary statement of the rate schedule shall not be in lieu of the rate schedule as required to be filed with the Commission pursuant to the regulations in this part.
Supporting statements A through O specify filing of the following data: balance sheet, income statements, earned surplus statement, cost of plant, accumulated depreciation, average working capital, rate of return, debt capital, operating expenses, depreciation expense, income taxes, other taxes, overall cost of service, allocated cost of service, comparison of cost of service, and “fuel adjustment factor.”
In addition,
See FPC v. Tennessee Gas Transmission Co., 371 U.S. 145, 152-153, 83 S.Ct. 211, 9 L.Ed.2d 199 (1962); State Corp. Comm‘n v. FPC, 215 F.2d 176, 184 (8th Cir. 1954). These cases interpretedA utility filing for an increase in rates and charges shall be prepared to go forward at a hearing on reasonable notice on the data which have been submitted and sustain the burden of proof, imposed by the Federal Power Act, of establishing that its proposed charges are just and reasonable and not unduly discriminatory or preferential or otherwise unlawful within the meaning of the Act. The Commission is desirous of avoiding delay in processing rate filings. To this end, if the rate schedule provides for an increase in rate which exceeds $30,000 in revenues for the test period, the filing utility shall submit with its rate increase filing 60 days prior to the proposed effective date of such increased rates, testimony and exhibits of such composition, scope and format that they would serve as the company‘s case-in-chief in the event the matter is set for hearing. In addition to whatever material the utility chooses to submit as part of its case, except for increases resulting from changes made in fuel clauses and increases of rates comprising an integral part of coordination and interchange arrangements in the nature of power pooling transactions, the exhibits shall include full cost of service data, as identified in subparagraph (4) (iv) of this paragraph, statements A through O, and the accompanying testimony should include an explanation of these exhibits.
That in the event the Court‘s opinion remains unmodified with respect to requiring that Indiana & Michigan Electric Company‘s June 13, 1972, rate filing should become effective as of July 14, 1972, the sum required to be paid for the period of July 14, 1972, through January 13, 1973, will amount to approximately Four Hundred Seventy Thousand Dollars ($470,000.00), the payment of which will cause considerable hardship to the City of Fort Wayne. The City will be unable to adequately maintain its system as by law required as a direct result of being required to make such payment. The City cannot recover this $470,000 payment since the City‘s rates were not increased for this item and cannot be increased retroactively.
That if the Court‘s opinion remains unmodified, the impact on the financial condition of the City of Fort Wayne‘s City Light and Power Utility will be extremely detrimental in that said City will have to absorb the increased rates without having the ability to raise its retail rates to provide for these additional past costs.
This will involve collection by I&M from its customers of the difference between the increased rates and the rates actually charged for the six-month period from 14 July 1972 to 13 January 1973. There is precedent in this circuit for ordering retroactive rate adjustments. See Tennessee Valley Municipal Gas Ass‘n v. FPC, 152 U.S.App.D.C. 298, 470 F.2d 446 (1972), a case that arose under the Natural Gas Act,
As recognized by this court in Pennsylvania Gas & Water Co. v. FPC, 150 U.S.App.D.C. 151, 463 F.2d 1242 (1972) (Natural Gas Act § 4(e),
We may distinguish the instant case from United States v. SCRAP, 412 U.S. 669, 93 S.Ct. 2405, 37 L.Ed.2d 254 (1973), and Arrow Transp. Co. v. Southern Ry. Co., 372 U.S. 658, 83 S.Ct. 984, 10 L.Ed.2d 52 (1963), which interpreted the suspension provision of the Interstate Commerce Act, § 15(7),
Congress, in its wisdom, has fixed seven months as the maximum period of suspension. It seems clear to us that if the courts extend that period, they are in effect amending the statute and that is a matter beyond their power.
372 U.S. at 662, 83 S.Ct. at 986, quoting 308 F.2d 181, 186 (1962). In SCRAP the District Court enjoined collection of railroad freight surcharges despite the fact that the ICC had denied requests to suspend the surcharges for the statutory seven-month period under section 15(7). The Supreme Court reversed, noting that the District Court‘s “injunction constitutes a direct interference with the Commission‘s discretionary decision whether or not to suspend the rates.” 412 U.S. at 692, 93 S.Ct. at 2418. In the case at bar, our denial of retroactive increases to I & M for the five-month period from 14 July 1972 through 13 December 1972 does not extend the statutory five-month suspension period as was the case in Arrow. Moreover, our order does not interfere with the Commission‘s “discretionary decision whether or not to suspend“; rather, it gives effect to the Commission‘s decision that suspension was appropriate.
The Commission‘s staff reached this conclusion in a letter to the Commission captioned “Commission Staff Response to Application of Indiana & Michigan Electric Company” and dated 28 July 1972. The letter stated:
In I & M‘s case, if five months’ suspension is ordered and the 60-day rule is invoked, the proposed rates would not go into effect until six months after the proposed effective date. If the rate changes are accepted for filing without suspension, the effective date would be 60 days after the proposed effective date. It may be observed further that the Commission‘s Regulations Under the Natural Gas Act do not prescribe a 60-day filing requirement and that the same threshold decision as to whether to order an investigation and hearing, or a suspension, or both, must be made. Since both Section 4(d) of the Natural Gas Act and Section 205 (d) of the Federal Power Act require only 30 days’ notice of rate changes, the staff respectfully submits that it would be inappropriate to require more of I & M.
Joint App. at 87.
Joint App. at 200: A similar recognition occurred in Central Maine Power Co., F.P.C. Docket Nos. E-7824 and E-8038 (8 June 1973), in which the Commission stated:
With respect to the request for suspension of Central Maine‘s proposed amendment and for refund protection thereunder, we find that the proposed amendment became effective by operation of law on March 16, 1973, thirty days after filing and prior to the issuance of the Commission‘s order on April 10, 1973. We are without authority under the Federal Power Act to rescind or suspend the effectiveness of the proposed amendment.
See also Phillips Petroleum Co. v. FPC, 227 F.2d 470 (10th Cir. 1955), cert. denied, 350 U.S. 1005, 76 S.Ct. 649, 100 L.Ed. 868 (1956).
It is to be observed that I & M‘s application of 18 July 1972, asking for a Commission order making the new rate schedule effective retroactively as of 14 July, would possibly have permitted the Commission to issue a suspension order for five months from the valid effective date of 14 July 1972. At least, it is clear that I & M would not have been in a position to challenge such an order as it has now, and that I & M was not seeking a procedural gimmick which would have resulted, as now has occurred, in voiding the Commission‘s five-month suspension order. However we do not reach the question suggested by this discussion since the Commission has never asserted that I & M‘s 18 July application for a 14 July effective date gave the Commission jurisdiction to suspend I & M‘s rates retroactively from 14 July; rather, the Commission has been consistent in contending that 13 August was the effective date and that the 11 August suspension was therefore valid.
Joint App. at 202.
Whenever the Commission, after a hearing had upon its own motion or upon complaint, shall find that any rate, charge, or classification, demanded, observed, charged, or collected by any public utility for any transmission or sale subject to the jurisdiction of the Commission, or that any rule, regulation, practice or contract affecting such rate, charge, or classification is unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate, charge, classification, rule, regulation, practice, or contract to be thereafter observed and in force, and shall fix the same by order.
