OPINION
Indiаna Erectors, Inc. appeals the judgment entered in favor of the Trustees of Indiana University [I.U.] after a jury trial in the amount of $1,900,000.00 representing damages caused by a fire, and an additional $899,090.96 representing pre-judgment interest. Indiana Erectors raises two issues, neither of which constitutes reversible error.
FACTS
The operative facts are not disputed. In December of 1990, I.U. contracted with Go-heen General Construction, Inc., as one of three prime contractors, to renovаte the Student Building on the Bloomington, Indiana campus. The three prime contractors included a General Contractor (Goheen), a Mechanical Contractor, and an Electrical Contractor. Goheen then entered into а subcontract with Structural Components, Inc. [SCI], which in turn entered into a subcontract with Indiana Erectors. On December 17,1990, employees of Indiana Erectors caused a fire which damaged the Student Building. Water used to put out the blaze damaged аn adjacent building.
I.U.’s general insurance carrier, the Allen-dale Mutual Insurance Company, paid I.U. approximately $1.9 million dollars for the loss. No additional insurance policy had been obtained to cover the renovation prоject. Accordingly, none of the contractors or subcontractors on the project were specifically named as insureds under any I.U. insurance policy. In December of 1992, I.U.’s trustees brought the present lawsuit against *880 Indiana Erectоrs seeking damages under the alternate theories of 1) negligence, and 2) the breach of the SCI/Indiana Erectors subcontract of which I.U. was a third-party beneficiary. The present lawsuit may appropriately be characterizеd as an insurance subrogation action brought by Allendale in the name of I.U. After the trial, the jury returned a verdict in favor of I.U. in the amount of $1.9 million. The amount of the verdict/judgment reveals that the judgment was based on the breach of contract theory because, as revealed by the jury verdict forms, the jury had reduced I.U.’s recovery under its negligence theory by 25% (representing fault allocated to I.U.) producing a verdict in the amount of $1,425 million. Additional facts are supplied as necessary.
DECISION
I.
Whether Indiana Erectors was an Intended Insured.
It is not an uncommon practice in construction contracts for the owner to agree to purchase insurance to protect the interests of some or all of the contractors, subcontractors, and materialmen.
LeMaster Steel Erectors, Inc. v. Reliance Insurance Co.,
In an arrangement where one party agrees to purchase insurance for the benefit of both parties, the first party in effect agrees to waive the intended insured’s liability.
LeMaster,
Indiana Erectors asserts that it had been entitled to judgment as a matter of law in the present subrogation action because it had been an intended insured under the interdependent, contractual relationships between I.U., Goheen, and the subcontractors. The trial court determined that, from a plain reading of the contract between I.U. and Goheen, that I.U. had not аgreed to purchase insurance to benefit any of the subcontractors. Accordingly, the trial court denied Indiana Erectors’ motion for summary judgment.
It is the duty of the courts to interpret a contract to ascertain the intent of the pаrties.
First Federal Savings Bank of Indiana v. Key Markets, Inc.,
*881 Indiana University and Goheen, the prime cоntractor over Indiana Erectors, entered into a 63 page written construction contract. The contract consisted of a standard printed form which had been extensively modified by typewritten provisions inserted in a column providеd for such modifications parallel to the printed form language. Article 11 of the contract governed insurance. All of the Article 11 form language had been expressly deleted and replaced with typewritten terms. Article 11.2.1 governed Builder’s Risk Insurance, and provided as follows:
The Owner shall maintain during the course of construction, Builder’s Risk Insurance ... The insured shall he the Owner and the Contractor(s) as their interest may appear; and loss, if any, is to be adjusted with and payable to the Contractor upon written request to the Owner. The Contractor shall be responsible for and insure, if desired, all materials, equipment, supplies not on the site and to become a part of the completed building, Contractor’s equipment, tools, scaffolding, staging, towers, forms and temporary buildings, and other materials, equipment and supplies not intended to become a part of the construction.
Anything herein contained to the contrary notwithstanding, the Owner and Contractor waive all rights, each against the other, for damаges caused by perils covered by any insurance purchased in accordance with the provisions of this subsection (Builder’s Risk Insurance), except such rights as they may have to the proceeds of such insurance. This provision shall not rеlease the Contractor from his obligation to complete, according to plans and specifications, the project covered by the Contract and the Contractor and his surety shall be obligated to full performance of the Contractor’s undertaking.
When requested, a certificate of the Builder’s Risk Insurance will be issued to each prime contractor.
(Emphasis added).
Indiana Erectors argues that it is an intended insured as one of the “Contractors” involved in the projeсt. We disagree.
The term “Contractor” is defined under Art. 4.1.1.2 of the contract as:
all the Prime contractors, unless reference is made to the intended specific Prime Contractor.
Paragraph 4.1.1.1 provides:
The work of this Project has been divided into the following parts, for which there will be separate Prime Contractors as indicated below:
.1 General Construction work, by the General Contractor,
.2 Mechanical Construction work, by the Mechanical Contractor.
.3 Electrical Construction work, by Electrical Contractor.
.4 Other.
As noted earlier, this project involved three Prime Contractors and Goheen was the рrime contractor under which SCI and Indiana Erectors were subcontracted. The term “Subcontractor” was defined under Art. 5.1.1 as:
a person or entity who has a direct contract with the Contractor to perform any of the Work at the site.
Additionally, Art. 5.2.4 provides:
Nothing contained in this Contract shall create any contractual relation between any subcontractor and the Owner.
Accordingly, the use of the term “Contractor(s)” unambiguously refers to a Prime Contractor or the Prime Contractors, and dоes not include subcontractors.
Thus, the present case is analogous to
LeMaster
where we concluded that, under the unambiguous language of the Article 11 insurance provisions of the construction contract, the general contractor was an intended insured, but the subcontractor wаs not.
The trial court correctly determined that no subcontractor was an intended insured under the unambiguous terms of the construction contract between I.U. and Goheen. Thus, LeMaster, and not South Tippecanoe, controls the disposition of the present case. The present insurance subrogation action was appropriately maintained against Indiana Erectors, and the trial court correctly denied Indiana Erectors’ motion for summary judgmеnt.
Indiana Erectors argues that Goheen’s subcontract with SCI and SCI’s subcontract with Indiana Erectors gave rise to a legitimate expectation that Indiana Erectors was an intended insured under I.U.’s contract with Goheen. Again,
LeMaster
controls. Neither аn owner nor the owner’s insurer can be bound by a subcontract to which neither was a party.
II.
Waiver, Estoppel or Release
Indiana Erectors points out that its subcontract was not terminated after the fire, and in fact, it continued to work on the Student Building and was paid from the insuranсe proceeds. Indiana Erectors asserts that it was given the impression that the fire was covered by I.U.’s insurance and, that Indiana Erectors was not given notice until long after its work had been completed that I.U. (or its insurer) intended to hold Indianа Erectors responsible for the fire. Indiana Erectors argues that I.U. cannot be permitted to bring a breach of contract after it had accepted and paid for Indiana Erectors work.
In support of its argument, Indiana Erectоrs cites cases similar to those discussed under Issue I involving subrogation claims involving named or intended insureds. As discussed above, as I.U. had not agreed to provide insurance for the subcontractors, Indiana Erectors was neither a named or intended insured, and I.U.’s insurer was not barred from seeking subrogation for the proceeds paid for the losses incurred for the fire.
We must conclude that Indiana Erectors has cited no authority, nor are we aware of any, which supports the novel argument advanced. We agree with I.U. that this “void speaks for itself.” Frankly, we see no incongruity, impropriety, or problem in I.U.’s conduct of keeping Indiana Erectors on the job and paying it for the work which was ultimately performed satisfactorily, while, at the same time, demanding that it be responsible for the damages caused by the fire. Therefore, we find no error.
III.
Prejudgment Interest
Indiana Erectors’ sole attack on the award of prejudgment interest is its assertion that I.U. failed to comply with the provisiоns of Ind.Code 34-4-37-1 et seq. Effective in 1988, this statutory provision provided
tort
claimants with a new substantive right to recover prejudgment interest as a component of compensatory damages.
In re Johnson,
As noted in the FACTS section, the verdiсt and judgment in the present case were based on a breach of contract theory. Therefore, the award of prejudgment interest was not based on the statute providing for awards of prejudgment interest on tort judgments and any noncompliance with the procedures outlined under this statute is irrelevant. Therefore, we find no error.
Judgment affirmed.
