32 N.Y.S. 640 | N.Y. Sup. Ct. | 1895
Plaintiffs’ former action was brought on the equity side of the court, and sustained, because of the alleged wrongs and wrongful acts of the defendant mentioned in the complaint in that action. Plaintiffs’ action was maintained by reason of the alleged wrongs and trespasses of the defendant under the acknowledged head of equity giving power to the court to prevent a multiplicity of suits, and alleging a recovery of damages as incidental .to the equity relief. Williams v. Railroad Co., 16 N. Y. 111; Davis v. Lambertson, 56 Barb. 480; Hutchins v. Smith, 63 Barb. 252. In that action plaintiffs were entitled to recover all the damages sustained up to the time of the trial thereof. Beir v. Cooke, 37 Hun, 38; Robinson v. Smith (Sup.) 7 N. Y. Supp. 38, and eases there cited. In Meyer v. Phillips, 97 N. Y. 485, it appeared an action was brought to restrain defendants from floating saw logs in the waters of a stream, and in dealing with that action the court said that the defendants “threatened to commit, and claimed the right to repeat, the trespass every year. Here a preventive action was proper to prevent an irreparable injury, within the meaning of the equitable rule, and also to avoid a multiplicity of suits”; and in such an action it was said that damages sustained may be awarded to the plaintiff. In Shapard v. Railroad Co., 117 N. Y. 442, 23 N. E. 30, it was held that property owners have a remedy in a court of equity in cases where the trespass is continuous in its nature, in order to avoid a multiplicity of suits, “and they can recover the damages they have sustained, as incidental to the granting of the equitable relief”; and it was further said that, the violation of the rights to property having been adjudged in such an action, “the awarding of damages, sustained in the past from the defendants, follows, they being, on equitable principles, deemed incidental to the main relief sought.” In Thomas v. Railroad Co., 76 Hun, 603, 28 N. Y. Supp. 201, -the right to maintain an equity action was asserted, and it was said that in
“The cause of action, both at law and equity, in such cases, arises out of the trespasses committed, and is based on the ownership of the property upon which the injuries are inflicted. * * * The existence óf a legal cause of action is' not only a prerequisite to the maintenance of the equitable action, but is also the foundation of the jurisdiction which equity courts possess in r.espect to the subject-matter. * * Inasmuch as the equitable remedy depends, among other things, upon the existence of a legal cause of action, it follows that those facts which will bar the legal action will also afford an answer to the equitable remedy, and that, so long as a legal remedy exists, •an equity court is open to aid in the enforcement of the leghl claim.” ■
If the former case had been a mere law action, the damages recoverable would have been limited to such as occurred prior to the commencement of the action, Uline v. Railroad Co., 101 N. Y. 98, 4 N. E. 536; Rumsey v. Railroad Co., 63 Hun, 205, 17 N. Y. Supp. 672; Galway v. Railroad Co., supra.
In Hunter v. Railway Co., 141 N. Y. 281, 36 N. E. 400, it was said that, inasmuch as the action was on the equity side—
“Where the main relief sought was an injunction against the continuance by the defendants of acts in violation of the plaintiffs’ property rights, an award of damages for what past injuries might be shown to have been inflicted would follow as incidental to the main relief. In such an action it is the settled rule that, if the court decides that the claim for the equitable relief is well founded, it may proceed to assess the damages sustained, in its own •discretion, and no absolute right exists to have them determined by a jury.”
In Lynch v. Railway Co., 129 N. Y. 274, 29 N. E. 315, it was held, viz.:
“Where a court of equity gains jurisdiction of a cause for one purpose, it ■may maintain it generally, and, to do complete justice between the parties, -ascertain and award damages as incidental to the main relief sought. Where, therefore, an equity court assumes jurisdiction to restrain a continuous trespass, in order to prevent a multiplicity of suits it may proceed to give full relief, both for the tortious act and the resulting damages.”
In Van Allen v. Railroad Co., 144 N. Y. 178, 38 N. E. 997, the •question arose as to what damages might be recovered, and O’Brien, •J., said:
“The facts showing the right to the injunction are undoubtedly the basis ’-for equitable relief in such cases, and the claim for damages is an incident •which equity draws into the litigation in order to prevent a multiplicity of suits and to completely adjust all the rights of the parties. * * * The ■measure of the relief is adapted to the situation at the time of the decree. '* * * No principle is better established, or more frequently asserted, than that, when a court of equity has once acquired jurisdiction over a cause for any purpose, it may retain the cause for all purposes, and proceed to a final determination of all the matters at issue.”
It must be assumed that in the former action the plaintiffs could have recovered all damages which accrued prior to the decision which was made of that action apparently in September, 1887, upon which decision judgment was entered January 12, 1888. It was said in the opening in this case that in the former action evidence
“The main facts are in the former adjudication, and we shall ask this jury to give their attention more particularly to the amount of damages which the plaintiffs, the Inderlieds, have suffered. The former action found all the facts substantially that were necessary to substantiate our action, but in that action there was no proof as to the value of the damages.”
It follows from the cases to which reference has been made that the plaintiffs were entitled to recover such damages as they had sustained by reason of the wrongful acts of the defendant done at the time of the making of the decree in that action. The pleadings and concessions made upon the trial indicate that no wrongful acts were perpetrated by the defendant after the decree made in the former action. We are inclined to think that that judgment is a bar to the plaintiffs’ right to recover for the matters referred to in the complaint in this action and in the opening made at the trial.
In Smith v. Smith, 79 N. Y. 634, it was held that:
“An estoppel by judgment in a former action arises when the same matter was at issue therein, and was either litigated by the parties and determined, or it might have been litigated, and a decision had upon it. * * * It is sufficient if there might have been judgment in the first action for the same cause alleged in the second.”
The same doctrine was laid down in Clemens v. Clemens, 37 N. Y. 74, and referred to approvingly in Bloomer v. Sturges, 58 N. Y. 176. And in Jordan v. Van Epps, 85 N. Y. 436, it was said:
“The judgment is final and conclusive between the parties, not only as to the matter actually determined, but as to every other matter which the parties might have litigated and have decided as incident to, or essentially connected with, the subject-matter of the litigation within the purview of the original action, either as a matter of claim or of defense.”
In Lorillard v. Clyde, 122 N. Y. 47, 25 N. E. 292, it was said the omission to give proof of the damages would not affect the force to be given to the judgment In the course of the opinion it is said:
“Evidence merely tending to show that the defendants omitted to produce, upon the trial, all the evidence that was admissible in their behalf, was immaterial. A judgment rendered on the merits is coextensive with the issues upon which it is founded, and is conclusive between the parties thereto, not only as to the matters actually proved, argued, and submitted for decision, but also as to every other matter directly at issue by the pleadings which the defendant partly might have litigated.”
Numerous cases are then cited in support of the proposition thus stated. In the case before us, the complaint, after setting out the various grounds for the supposed right to recover in this action, expressly avers, viz.:
“That in an action in this court, wherein Inderlied, Son & Co., were plaintiffs, and these defendants were defendants, it was found, adjudged, determined, and decreed that the defendants herein had wrongfully done all the acts herein alleged, and wrongfully caused all the damages and loss herein set forth.”
The plaintiffs were entitled to recover such damages in that action “as would necessarily and naturally result or be incurred
In McGean v. Railroad Co., 133 N. Y. 9, 30 N. E. 647, it was held that a party was entitled.to preventive relief, “and the court, as a court of equity, thus having jurisdiction for this purpose, had power to award the past damages”; and in the course of the opinion delivered in that case, at page 16, 133 N. Y. and page 647, 30 N. E., it is said that:
“If the controversy contains an equitable feature, or requires any purely equitable relief belonging to the exclusive jurisdiction of equity, or pertaining to the concurrent jurisdiction of equity and law, and a court of equity thus acquires a partial cognizance of the action, it may go on to a complete adjudication, and establish purely legal rights, and grant legal remedies, which would otherwise be beyond the scope of its authority. Pom. Eq. Jur. §§ .181, 231, 242. So long as one of the grounds of equitable interference in this class of cases is the avoidance of a multiplicity of suits, this rule must prevail.”
The foregoing views lead "to the conclusion that the result reached at the circuit should be sustained. Judgment and order affirmed, with costs. All concur.