This is a bankruptcy case. Morse Electric Co., the bankrupt, took part in the construction of a toll plaza and utility building on the Indiana Toll Road. The project was covered by a performance bond, as state law required. The bond secures payment to suppliers that “furnished material or other service in the construction of any highway”, Ind. Code § 8-13-5-9.2. The parties have treated claims against the bond as secured claims for purposes of bankruptcy law.
When Morse filed its petition in bankruptcy, it was owed a substantial sum for its work on the highway and three other projects. Morse filed an adversary proceeding in the bankruptcy demanding that the money be turned over to it and naming 21 firms that might claim an interest in the money. After some preliminary proceedings that are no longer important, the money was tendered into court. Because the bonding company, if called on to pay, would be subrogated to any claims to this fund, the parties have agreed to proceed in its absence and to treat all claims covered by the construction bond as secured claims against the fund. One of the claims is before us now: Hoosier Fence Co. seeks $65,000 plus interest for five large concrete barriers sold to Morse.
The bankruptcy judge concluded that the barriers, designed to separate traffic from hazards and people during a construction project, are movable and reusable. They were not incorporated in the project and so were covered by the bond, the judge concluded, only to the extent of their implicit rental value for the duration of the project. The bankruptcy judge fixed this at $40,000, giving Hoosier a secured claim for $40,000 and an unsecured claim for $25,000. On appeal by Morse, the district court concluded that because the barriers are reusable they are not covered by the bond at all. This left Hoosier with an unsecured claim for $65,000, and it appealed to us.
I
The jurisdictional section of Hoosier’s brief states that this court “has jurisdiction over this cause in accordance with 28 U.S.C. § 1291 (1976), in that it is an appeal from a final judgment” of a district court. Section 1291 is the wrong statute in bankruptcy cases — at least as a rule, and we need not consider whether there are exceptions. Cf.
In re Memorial Estates, Inc.,
The memoranda were filed, but neither mentions Rule 54(b) or the word “Westinghouse”. Hoosier, the appellant, does not say a thing about which claims remain to be resolved in the adversary proceeding. Morse’s memorandum catalogs some of the remaining parties, of which there are at least seven, but does not describe their claims. These submissions are unresponsive to the court’s request. We wanted to know the status of Westinghouse and any order under Rule 54(b). Neither side supplied the information that the court requested.
The court needs — more, is entitled to— the scrupulous assistance of the bar in determining jurisdiction. Jurisdiction is the first question in every appeal.
In re Boomgarden,
A disposition of a creditor’s claim in a bankruptcy is “final” for purposes of § 158(d) when the claim has been accepted and valued, even though the court has not yet established how much of the claim can be paid given other, unresolved claims. See
In re Fox,
If Hoosier’s claim were a suit outside of bankruptcy, the district court’s disposition would be “final”. The district court held Hoosier entitled to $65,000 but determined that none of Hoosier’s claim is secured. All that remains is the decision what percentage of Morse’s unsecured claims will be paid. That will be influenced by whether the bankruptcy court allows other claims to Morse’s assets, but these third-party disputes do not involve Hoosier or pose a risk of a second appellate go-round on additional issues peculiar to it. If the district judge had affirmed the bankruptcy judge, however, things might have been otherwise. (“Might” because the parties have not furnished enough information to enable us to tell.) There are other claims against the fund, and these competing claims may have led to a reassessment of how much of Morse’s claim would be deemed secured. The total of allowed “secured” claims cannot exceed the amount of the fund, posing a risk that Hoosier’s claim would be back for further proceedings. On the other hand, we have held that an order fixing the amount of a secured claim may be appealed even though the priority of the claim is not yet settled.
In re J. Catton Farms, Inc.,
Although, as we have emphasized, the disposition of one but not all claims in a larger case is not final under § 1291 in the absence of separate judgment under Rule 54(b), such separate judgments are not necessary in bankruptcy cases. Rule 54(b) is a device to make a judgment “final” and allow immediate execution — or allow a prevailing party to go his way secure that the case against him is over. The filing of the Rule 54(b) judgment starts a mechanical process: appeal now or never.
Exchange National Bank v. Daniels,
An adversary proceeding may produce a traditional judgment (for example, an order adjudicating a claim that the debtor committed a tort) but need not. The more an adversary proceeding looks like an independent lawsuit, attached to a bankruptcy case only because someone happens to be bankrupt, the more we will insist on adherence to the norms of finality under § 1291 and Rule 54(b). But when, as here, the adversary proceeding is a core proceeding to value a creditor’s undisputed claim, see 28 U.S.C. § 157(b)(2), a resolution of one creditor’s full position is “final” under § 158(d) without the need for a formal entry of a separate judgment under Rule 54(b). The district court’s order is therefore appeal-able.
II
The huge concrete barriers can be reused unless destroyed by the impact of a truck. *266 The district court reasoned that because the barriers are reusable and are not physically incorporated into the highway or toll plaza, they are not covered by the statute and bond. The court thought that only goods and services used “solely” in a construction project are covered by the bond. This makes the bond a substitute for a mechanic’s or materialman’s lien; the state gets its project without liens, and the former lien holder receives a claim against a solvent bonding company. The use of the barriers during the course of construction would not have given rise to a lien against the toll plaza. They are not incorporated into the building. The seller of the barriers could have taken a security interest in the barriers themselves under the Uniform Commercial Code. As the district court characterized the transactions, the barriers were no different from trucks Morse used to move materials or from the desks in Morse’s office: none was incorporated in a road or building, so none was covered by the bond. The district judge also thought that there was “no evidence” to show that some portion of the price of the barricades was incorporated into the toll plaza project. He held the entire $65,000 claim to be unsecured.
The bankruptcy judge, on the other hand, characterized the case as one in which Morse devoted the barriers to the toll plaza project exclusively for a period of time. The desk and the trucks served many projects simultaneously; the barriers served but one, and their cost therefore could be charged against that project’s bond. As the bankruptcy judge saw things, the function of the bond was to assure suppliers of payment and make it easier for the state to employ a full range of subcontractors — including subcontractors that might be too shaky to attract credit — in its construction projects. The statutory requirement, according to the bankruptcy judge, is not physical incorporation but exclusive use, and then only for a period of time. The barriers were delivered to the toll plaza project for use on the site; they were used exclusively there until Morse went bankrupt. This left for the bankruptcy judge the problem of valuing the use. He solved this by observing that Hoosier had sold the five barricades to Morse for $13,000 apiece and had offered to repurchase the barriers from Morse for $5,000 each if they were undamaged at the end of the project. This led the bankruptcy judge to conclude that $8,000 of each barrier, or $40,000 in all, “went into” the toll plaza project and could be recovered from the bond. The remaining $25,000 became an unsecured claim.
Hoosier offers still a third position. It insists that the barriers were delivered to a construction site for use in the process of construction. According to Hoosier, that alone shows that the full purchase price of each barrier is covered by the bond.
The bankruptcy judge had it right in principle. The statute in question, Ind. Code § 8-18-5-9.2, does not limit the coverage of the bond to materials physically incorporated into the project. It protects those who have “performed any labor or furnished material or other service
in
the construction of any highway or bridge in the state highway system” (emphasis added). The courts of Indiana have treated this language as covering materials dedicated exclusively to some project for a period of time or used up in the project, even if not incorporated into a building, road, or bridge. For example,
George T. Miller Constr. Co. v. Standard Oil Co.,
*267 What happened here is fundamentally the same as in Middle West, with the difference that Morse bought the barriers (and an option to resell) rather than renting them. The barriers, like the trucks, were devoted exclusively to the construction project for a period of time and in all likelihood had some value at the end of the project. Counsel for Morse conceded at oral argument that if Morse had purchased trucks and used them exclusively in the toll plaza project for a year, the seller of the trucks would be protected by the bond to the extent of the first year’s depreciation of the trucks — the amount of their value that was consumed by the project. The same principle logically applies to the barriers.
Morse replies that
Southern Surety Co. v. National Lumber Co.,
Both parties argue that the record is missing some fact vital to the other party’s case. Hoosier contends that the record does not show what has become of the barriers. They were removed from the toll plaza, but in what condition? If they were demolished, then they were used up in the project and logically are covered in full by the bond. * Morse replies that the record does not show that the barriers were affected in the least by their tenure at the toll plaza and insists that because they may be used elsewhere, nothing was consumed and nothing is covered by the bond. Each of these points is logical. Ordinarily a judge may assume that a heavy chunk of concrete, like an automobile, will survive longer than a year, but these barriers were targets for speeding trucks, and their condition is unknown. The bankruptcy judge should have ascertained their condition before deciding the case.
The bankruptcy judge also should have invited the parties to submit evidence on the value of the barriers at the end of their stay at the toll plaza. The parties treated the case in the bankruptcy court as an all-or-nothing matter; neither side offered evidence of the current value of the barriers because neither thought it mattered. The bankruptcy judge introduced the idea that the bond covers the amount by which the barriers depreciated while in use at the project. The judge seized on Hoosier’s offer to repurchase barriers in good condition for $5,000, and this suggests that the depreciation was $8,000. We therefore do not agree with the district judge that the record contains “no evidence” that the barriers had value after the toll plaza project. The $5,000 bid by Hoosier and the physical characteristics of the barriers are “evidence”. See
Kendall Lumber & Coal Co. v. Roman,
So although we believe that the bankruptcy judge took the right approach to the meaning of the statute, and that some of the value of the barriers is covered by the bond, the parties should be asked for evidence showing how much. The judgment of the district court is reversed, and the case is remanded with instructions to remand to the bankruptcy court for further proceedings consistent with this opinion.
Notes
Unless the bond covers only the portion expected to be consumed, rather than the portion actually consumed. But neither party raises this possibility, and we do not pursue options that were not offered to the district judge. We therefore assume, without saying that this is the inevitable reading of the statute, that the coverage of the bond depends on how things turn out rather than what was expected to happen.
