The petition filed alleged that on August 6, 1928, the Petroleum Navigation Company
The charter contained an arbitration clause reading: “Any dispute arising during performance of this Charter-Party shall be settled by arbitration in New York, Owner and Charterer each appointing an Arbitrator, and the two thus chosen, if they cannot agree, nominating a third whose decision shall he final. Should one of the parties neglect or refuse to appoint an Arbitrator within twenty-one days after receipt of request from the other party, the single Arbitrator appointed shall have the right to decide alone, and his decision shall he binding on both parties. For the purpose of enforcing any award this agreement shall he made a Rule of Court.”
’The appellee filed a libel in admiralty against the appellant and refuses to arbitrate the dispute. Thereupon this petition was filed. In support of the petition, the appellant invokes section 4 of the United States Arbitration Act (U. S. C. section 4, title 9 [9 USCA § 4]) which provides: “A party aggrieved by the alleged failure, neglect, or refusal of another to arbitrate under a written agreement for arbitration may petition any court of the United States which, save for such agreement, would have jurisdiction under the judicial code at law, in equity, or in admiralty of the subject matter of a suit arising out of the controversy between the parties, for an order directing that such arbitration proceed in the manner provided for in such agreement. * * * ” It further provides : “The court shall hear the parties, and upon being satisfied that the making of the agreement for arbitration or the failure to comply therewith is not in issue, the court shall make an order directing the parties to proceed to arbitration in accordance with the terms of the agreement. * * * ”
The petition sufficiently sets forth the refusal to arbitrate and the grievance of the appellant thereby under the terms of the agreement so to do.
It is to be noted that the agreement to arbitrate was for a dispute arising during the performance of the charter party. The parties had entered into the performance of this contract. According to the appellant’s petition, the denial of which raises the issue, there was a termination of performance by the appellant, on breach of the appellee; thus the question presented is whether, on the shipowner’s breach of the charter during performance, the charterer is entitled to have the respective rights of the parties determined by an arbitration under the arbitration clause.
The court below, resting its decision on The Atlanten,
The Atlanten, supra, was decided before the effective date of the United States Arbitration Act (February 12, 1925). Prior thereto an agreement to arbitrate was not recognized as a valid defense to an action, nor was it specifically enforceable in admiralty. Red Cross Line v. Atlantic Fruit Co.,
There is sufficient averment in the petition that the vessel did not report unloaded as required under the terms of the charter, and a breach on the part of the owner is thereby alleged. It is sufficiently alleged that the ship should have been at Trinidad, British West Indies, ready for loading not later than March 22, 1933, but instead she was engaged on business other than the charterer’s, between New York and Gulf ports. There is no provision of the charter which granted an exception of this kind to the vessel owner which would avoid a breach by the owner of the entire engagement. Hasler v. West India S. S. Co.,
It is not a- repudiation of the contract, as was the -case in The Atlanten, supra. A dispute arose under the contract, for here one of the parties, in the opinion of the other, failed to perform. Arbitration clauses are designed to provide remedies for such situations. The fact that the appellant did not continue performance after breach by the appellee did not deprive it of the right to rely on the arbitration clause. Matter of General Footwear Corp. v. Lawrence Leather Co.,
Nothing in the clause requires performance tó continue during the dispute or during the arbitration. Performance by the appellant did not end until it exercised its right to terminate performance by the alleged breach of the appellee. It is clear that the parties intended the words “arising during performance” to attach to all disputes arising although performance on both sides had terminated. This dispute arose during performance and is within the scope of the clause.
No sufficient reason is advanced why the purposes of this arbitration clause should not be carried out and' the appellee held bound by its agreement.
Order reversed.
